Nebraska Revised Statutes homeSearch Nebraska
Neb. Rev. Stat.Chapter 52

Neb. Rev. Stat. § 52-136 (2026)

Amount of lien

Edition and currency
text as last checked Oct. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Oct. 2026 (this copy records no edition or section history) cited 1988–2022 12citing cases
At a glance

Courts have cited this section in 12 opinions since 1988, 1 of them in the last five years. The most litigated part is subsection (1)(a) (4 cases).

(1) Subject to subsection (3) of this section:

(a) The lien of a prime contractor is for the unpaid part of his or her contract price; and

(b) Except as against a protected party contracting owner, the lien of a claimant other than a prime contractor is for the amount unpaid under the claimant's contract.

(2) Except as modified by subsections (4) and (5) of this section, as against a protected party contracting owner, the lien of a claimant other than a prime contractor is for the lesser of:

(a) The amount unpaid under the claimant's contract; or

(b) The amount unpaid under the prime contract through which the claimant claims at the time the contracting owner receives the claimant's notice of the right to assert a lien.

(3) The lien of a claimant is reduced by the sum of the liens of claimants who claim through him or her.

(4) If a protected party contracting owner's lien liability under a particular prime contract as provided in subsection (5) of this section is less than the sum of claims of all claimants claiming through that particular prime contractor:

(a) Lien claimants whose liens attach at different times have liens in the order of attachment until the owner's lien liability is exhausted; and

(b) Among claimants whose liens attach, or may attach, at the same time, each claimant's lien is for his or her pro rata portion of the amount of the contracting owner's lien liability to claimants whose liens attach at that time.

(5) A protected party contracting owner's lien liability under a particular prime contract is the prime contract price less payments properly made thereon. A payment is properly made on a prime contract to the extent that the payment:

(a) Is made in good faith before the receipt by the contracting owner of a copy of a recorded lien or of a notice of the right to assert a lien; or

(b) If made after receipt by the contracting owner of a copy of a recorded lien or of a notice of the right to assert a lien, is made in good faith and leaves unpaid a part of the prime contract price sufficient to satisfy the unpaid claims of all claimants who have provided a copy of a recorded lien or who have given notice of the right to assert a lien and whose claims are not being satisfied by the payment.

The 12 cases that cite Neb. Rev. Stat. § 52-136 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENLincoln Lumber Co. v. Lancaster, 618 N.W.2d 676 (Neb. 2000).
cites § 52-136 8×subsections: (5) 4× (2) 3× (1)cited by 24 cases
Where it cites § 52-136
“Both Kaser and Lincoln Lumber were entitled to the unpaid part of their contract price under § 52-136(1). Because Daugherty’s notice of commencement was in effect at the time they filed their liens, both liens attached on the date the notice of commencement was filed pursuant to…”
2
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).
cites § 52-136 5×subsections: (1)(a) 4×cited by 42 cases
Where it cites § 52-136
“Section 52-136(1)(a) provides that “[t]he lien of a prime contractor is for the unpaid part of his or her contract price .”
The case’s holding
A person who furnishes services or materials pursuant to a real estate improvement contract has a construction lien.
Later courts cite it for
“who furnishes services or materials pursuant to a real estate improvement contract has a construction lien,” · 2 citing courts
3
GREENSorenson v. Dager, 601 N.W.2d 564 (Neb. Ct. App. 1999).
cites § 52-136 5×subsections: (1)(a) 3×cited by 31 cases
Where it cites § 52-136
“The Dagers contend that Sorenson cannot recover under the provisions of § 52-136, which apply to the lien of a claimant other than a prime contractor, because Sorenson did not substantially perform his contract with Niemeyer.”
cites § 52-136 8×subsections: (3) 2× (1)(a) (2) (4)cited by 8 cases
Where it cites § 52-136
“The provisions of § 52-136 make it clear that a prime contractor is not entitled to payment from the owner until the liens of the subcontractors are satisfied.”
5
NEUTRALGoes v. Vogler, 937 N.W.2d 190 (Neb. 2020).
cites § 52-136 3×cited by 120 cases
Where it cites § 52-136
“Eric Vogler testified that he had paid $203,485 on the contract with Shelton, but the contract provided for $282,000 even before the cost of changes and extras were added.”
6
GREENTilt-Up Concrete, Inc. v. Star City/Fed., Inc., 621 N.W.2d 502 (Neb. 2001).
cites § 52-136 1×subsections: (1)cited by 105 cases
Where it cites § 52-136
“Cizek, supra (money collected on personal judgment to be credited to mechanic’s lien); § 52-136(1) (amount of lien is for unpaid part of contract price).”
The case’s holding
The Nebraska Construction Lien Act does not preclude a concurrent breach of contract action, nor does a supersedeas bond toll the statute of limitations.
Later courts cite it for
“the amount unpaid for the services and materials furnished.” · 2 citing courts
7
GREENEcho Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).
cites § 52-136 2×subsections: (2)(a)cited by 8 cases
Where it cites § 52-136
“” 27 The amount of the lien is specified by § 52-136, 28 which provides, under the circumstances here, that the lien is for the amount unpaid under Echo’s contract.”
The case’s holding
Under the Nebraska Construction Lien Act, substituting a lien release surety bond for a construction lien does not cap recovery, and prejudgment interest may be awarded in lien foreclosure actions.
Later courts cite it for
“a formal legal document entailing rights and obligations, such as a contract, deed, legislative act, etc.; any document formally drawn up so as to have legal effect.” · 2 citing courts
cites § 52-136 5×subsections: (2) (2)(b)cited by 6 cases
Where it cites § 52-136
“According to Neb. Rev. Stat. § 52-136 (2) (Reissue 1993), a claimant’s lien, as against a “protected party contracting owner,” is the lesser of “(a) [t]he amount unpaid under the claimant’s contract; or (b) [t]he amount unpaid under the prime contract through which the claimant…”
9
GREENBlue Tee Corp. v. CDI Contractors, Inc., 529 N.W.2d 16 (Neb. 1995).
cites § 52-136 1×cited by 35 cases
Where it cites § 52-136
“Because we find that Blue Tee is entitled to a lien, we must consider Blue Tee’s claim that it is entitled to interest on the amount due it from the date 30 days after Blue Tee’s last steel delivery.”
The case’s holding
A fabricator that custom-manufactures unique building materials to a prime contractor's specifications, performing substantial labor, is a subcontractor, so its supplier may claim a construction lien.
10
GREENOmaha Constr. Indus. Pension Plan v. Child.'s Hosp., 642 N.W.2d 849 (Neb. Ct. App. 2002).
cites § 52-136 1×subsections: (1)(b)cited by 6 cases
Where it cites § 52-136
“Further, § 52-136(l)(b) provides that “the lien of a claimant other than a prime contractor is for the amount unpaid under the claimant’s contract.”
11
NEUTRALFreedom Specialty Contracting v. Nichol Flats, 950 N.W.2d 109 (Neb. Ct. App. 2020).
cites § 52-136 5×subsections: (1)(a)cited by 1 case
Where it cites § 52-136
“Stat. § 52-136 (1)(a) (Reissue 2010) speaks clearly as to the right to a construction lien only with respect to services performed or materials furnished, not with respect to services intended to be performed or materials intended to be furnished.”
12
NEUTRALGoes v. Vogler, 304 Neb. 848 (Neb. 2020).
cites § 52-136 3×cited by 0 cases
Where it cites § 52-136
“Eric Vogler testified that he had paid $203,485 on the contract with Shelton, but the contract provided for $282,000 even before the cost of changes and extras were added.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198820052022

One bar per year. Tallest: 3 cases in 2020. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Neb.9Neb. Ct. App.3
By subsection
(1)2 cases
Tilt-Up Concrete, Inc. v. Star City/Fed., Inc., 621 N.W.2d 502 (Neb. 2001).“Cizek, supra (money collected on personal judgment to be credited to mechanic’s lien); § 52-136(1) (amount of lien is for unpaid part of contract price).”
Lincoln Lumber Co. v. Lancaster, 618 N.W.2d 676 (Neb. 2000).“Both Kaser and Lincoln Lumber were entitled to the unpaid part of their contract price under § 52-136(1). Because Daugherty’s notice of commencement was in effect at the time they filed their liens, both liens attached on the date the notice of commencement was filed pursuant to…”
(1)(a)4 cases
Tilt-Up Concrete, Inc. v. Star City/Fed., Inc., 582 N.W.2d 604 (Neb. 1998).“Section 52-136(1)(a) provides that “[t]he lien of a prime contractor is for the unpaid part of his or her contract price .”
Sorenson v. Dager, 601 N.W.2d 564 (Neb. Ct. App. 1999).“The Dagers contend that Sorenson cannot recover under the provisions of § 52-136, which apply to the lien of a claimant other than a prime contractor, because Sorenson did not substantially perform his contract with Niemeyer.”
Action Heating & Air Conditioning, Inc. v. Petersen, 429 N.W.2d 1 (Neb. 1988).“The provisions of § 52-136 make it clear that a prime contractor is not entitled to payment from the owner until the liens of the subcontractors are satisfied.”
Freedom Specialty Contracting v. Nichol Flats, 950 N.W.2d 109 (Neb. Ct. App. 2020).“Stat. § 52-136 (1)(a) (Reissue 2010) speaks clearly as to the right to a construction lien only with respect to services performed or materials furnished, not with respect to services intended to be performed or materials intended to be furnished.”
(1)(b)1 case
Omaha Constr. Indus. Pension Plan v. Child.'s Hosp., 642 N.W.2d 849 (Neb. Ct. App. 2002).“Further, § 52-136(l)(b) provides that “the lien of a claimant other than a prime contractor is for the amount unpaid under the claimant’s contract.”
(2)3 cases
Lincoln Lumber Co. v. Lancaster, 618 N.W.2d 676 (Neb. 2000).
Midlands Rental & Mach., Inc. v. Christensen Ltd. P'ship, 566 N.W.2d 115 (Neb. 1997).“According to Neb. Rev. Stat. § 52-136 (2) (Reissue 1993), a claimant’s lien, as against a “protected party contracting owner,” is the lesser of “(a) [t]he amount unpaid under the claimant’s contract; or (b) [t]he amount unpaid under the prime contract through which the claimant…”
(2)(a)1 case
Echo Grp. v. Tradesmen Internat., 980 N.W.2d 869 (Neb. 2022).“” 27 The amount of the lien is specified by § 52-136, 28 which provides, under the circumstances here, that the lien is for the amount unpaid under Echo’s contract.”
(2)(b)1 case
(3)1 case
(4)1 case
(5)2 cases
Lincoln Lumber Co. v. Lancaster, 618 N.W.2d 676 (Neb. 2000).
(5)(a)1 case
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.