(1) It is the intent of the Legislature to establish a means by which excavators may notify operators of underground facilities in an excavation area so that operators have the opportunity to identify and locate the underground facilities prior to excavation and so that the excavators may then observe proper precautions to safeguard the underground facilities from damage.
(2) It is the purpose of the One-Call Notification System Act to aid the public by preventing injury to persons and damage to property and the interruption of utility services resulting from accidents caused by damage to underground facilities.
Notes of Decisions
Cited in 3
cases (1 in the last 5 years), 2003–2021 · leading case: Mercer v. North Cent. Serv., 308 Neb. 224 (Neb. 2021).
Mercer v. North Cent. Serv., 308 Neb. 224 (Neb. 2021). “224 In order to accomplish this purpose, the participating utili- ties must comply with § 76-2323: (1) Upon receipt of the information contained in the notice pursuant to section 76-2321, an operator shall advise the excavator of the approximate location of under- ground…”
Hughes v. Omaha Pub. Power Dist., 735 N.W.2d 793 (Neb. 2007). “[19] § 76-2302(1). [20] § 76-2302(2). [21] § 76-2317.”
Galaxy Telecom, L.L.C. v. J.P. Theisen & Sons, Inc., 656 N.W.2d 444 (Neb. 2003). “§ 76-2302(1). The purpose of the Act is “to aid the public by preventing injury to persons and damage to property and the interruption of utility services resulting from accidents caused by damage to underground facilities.”
— Neb. Rev. Stat. § 76-2302(1) — 3 cases
Mercer v. North Cent. Serv., 308 Neb. 224 (Neb. 2021). “224 In order to accomplish this purpose, the participating utili- ties must comply with § 76-2323: (1) Upon receipt of the information contained in the notice pursuant to section 76-2321, an operator shall advise the excavator of the approximate location of under- ground…”
Galaxy Telecom, L.L.C. v. J.P. Theisen & Sons, Inc., 656 N.W.2d 444 (Neb. 2003). “§ 76-2302(1). The purpose of the Act is “to aid the public by preventing injury to persons and damage to property and the interruption of utility services resulting from accidents caused by damage to underground facilities.”
Hughes v. Omaha Pub. Power Dist., 735 N.W.2d 793 (Neb. 2007). “[19] § 76-2302(1). [20] § 76-2302(2). [21] § 76-2317.”
— Neb. Rev. Stat. § 76-2302(2) — 3 cases
Mercer v. North Cent. Serv., 308 Neb. 224 (Neb. 2021). “224 In order to accomplish this purpose, the participating utili- ties must comply with § 76-2323: (1) Upon receipt of the information contained in the notice pursuant to section 76-2321, an operator shall advise the excavator of the approximate location of under- ground…”
Hughes v. Omaha Pub. Power Dist., 735 N.W.2d 793 (Neb. 2007). “[19] § 76-2302(1). [20] § 76-2302(2). [21] § 76-2317.”
Galaxy Telecom, L.L.C. v. J.P. Theisen & Sons, Inc., 656 N.W.2d 444 (Neb. 2003). “§ 76-2302(1). The purpose of the Act is “to aid the public by preventing injury to persons and damage to property and the interruption of utility services resulting from accidents caused by damage to underground facilities.”