Nevada Revised Statutes homeSearch Nevada
Nev. Rev. Stat.Nrs: Chapter 533 - Adjudication of Vested Water Rights; Appropriation of Public Waters

Nev. Rev. Stat. § 533.380 (2026)

Time for completion of work and application of water to beneficial use; limitations and extensions; regulations

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1957–2019 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1957. The most litigated part is subsection (3) (5 cases).

NRS 533.380  Time for completion of work and application of water to beneficial use; limitations and extensions; regulations.

      1.  Except as otherwise provided in subsection 5, in an endorsement of approval upon any application, the State Engineer shall:

      (a) Set a time before which the construction of the work must be completed, which must be within 5 years after the date of approval.

      (b) Except as otherwise provided in this paragraph, set a time before which the complete application of water to a beneficial use must be made, which must not exceed 10 years after the date of the approval. The time set under this paragraph respecting an application for a permit to apply water to a municipal or quasi-municipal use on any land:

             (1) For which a final subdivision map has been recorded pursuant to chapter 278 of NRS;

             (2) For which a plan for the development of a project has been approved by the local government pursuant to NRS 278.010 to 278.460, inclusive; or

             (3) On any land for which a plan for the development of a planned unit development has been recorded pursuant to chapter 278A of NRS,

Ê must not be less than 5 years.

      2.  The State Engineer may limit the applicant to a smaller quantity of water, to a shorter time for the completion of work, and, except as otherwise provided in paragraph (b) of subsection 1, to a shorter time for the perfecting of the application than named in the application.

      3.  Except as otherwise provided in subsection 4 and NRS 533.395 and 533.4377, the State Engineer may, for good cause shown, grant any number of extensions of time within which construction work must be completed, or water must be applied to a beneficial use under any permit therefor issued by the State Engineer, but a single extension of time must not exceed 5 years. An application for the extension must in all cases be:

      (a) Made within 30 days following notice by registered or certified mail that proof of the work is due as provided for in NRS 533.390 and 533.410; and

      (b) Accompanied by proof and evidence of the good faith and reasonable diligence with which the applicant is pursuing the perfection of the application.

Ê The State Engineer shall not grant an extension of time unless the State Engineer determines from the proof and evidence so submitted that the applicant is proceeding in good faith and with reasonable diligence to perfect the application. The failure to provide the proof and evidence required pursuant to this subsection is prima facie evidence that the holder is not proceeding in good faith and with reasonable diligence to perfect the application.

      4.  Except as otherwise provided in subsection 5 and NRS 533.395, whenever the holder of a permit issued for any municipal or quasi-municipal use of water on any land referred to in paragraph (b) of subsection 1, or for any use which may be served by a county, city, town, public water district or public water company, requests an extension of time to apply the water to a beneficial use, the State Engineer shall, in determining whether to grant or deny the extension, consider, among other factors:

      (a) Whether the holder has shown good cause for not having made a complete application of the water to a beneficial use;

      (b) The number of parcels and commercial or residential units which are contained in or planned for the land being developed or the area being served by the county, city, town, public water district or public water company;

      (c) Any economic conditions which affect the ability of the holder to make a complete application of the water to a beneficial use;

      (d) Any delays in the development of the land or the area being served by the county, city, town, public water district or public water company which were caused by unanticipated natural conditions; and

      (e) The period contemplated in the:

             (1) Plan for the development of a project approved by the local government pursuant to NRS 278.010 to 278.460, inclusive; or

             (2) Plan for the development of a planned unit development recorded pursuant to chapter 278A of NRS,

Ê if any, for completing the development of the land.

      5.  The provisions of subsections 1 and 4 do not apply to an environmental permit or a temporary permit issued pursuant to NRS 533.436 or 533.504.

      6.  For the purposes of this section, the measure of reasonable diligence is the steady application of effort to perfect the application in a reasonably expedient and efficient manner under all the facts and circumstances. When a project or integrated system is composed of several features, work on one feature of the project or system may be considered in finding that reasonable diligence has been shown in the development of water rights for all features of the entire project or system.

      7.  The State Engineer shall:

      (a) Adopt any regulation necessary to carry out the provisions of this section; and

      (b) Provide a copy of such regulations to any person upon request.

      [65:140:1913; A 1951, 132]—(NRS A 1967, 193; 1981, 113, 1838; 1989, 1052, 1400; 1991, 759; 1993, 2349; 2009, 644; 2011, 1568; 2013, 501, 3679; 2017, 3500; 2019, 2623)

     

The 8 cases that cite Nev. Rev. Stat. § 533.380 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENDesert Irrigation, Ltd. v. State of Nevada, 944 P.2d 835 (Nev. 1997).
cites § 533.380 9×cited by 31 cases
Where it cites § 533.380
“The Court is more troubled with the State Engineer’s failure to address whether NRS 533.380(4) should apply as to a proposed transfer of the rights to a non-contiguous parcel and to which the petitioner sought to remove the water.”
The case’s holding
An extension of a water right requires actual evidence of reasonable diligence rather than mere statements of intent to put water to beneficial use.
Later courts cite it for
“even those holding certificated, vested, or perfected water rights do not own or acquire title to water. they merely enjoy the right to beneficial use.” · 7 citing courts
2
GREENSierra Pac. Indus. v. Wilson, 440 P.3d 37 (Nev. 2019).
cites § 533.380 12×subsections: (3) 4× (3)(b) 2×cited by 4 cases
Where it cites § 533.380
“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
The case’s holding
The anti-speculation doctrine applies to water permit extension requests, requiring evidence of a formal relationship with a third party to demonstrate reasonable diligence.
Later courts cite it for
“we review the state engineer's factual findings for an abuse of discretion and will only overturn those findings if they are not supported by substantial evidence.” · 1 citing court
3
GREENBailey v. State, 594 P.2d 734 (Nev. 1979).
cites § 533.380 2×subsections: (1)(a) (1)(c)cited by 16 cases
Where it cites § 533.380
“This principle has been incorporated into the state water law, and is reflected in NRS 533.380(l)(a) which requires that in his endorsement of approval upon an application for the appropriation of water the State Engineer shall “[s]et a time prior to which actual construction…”
The case’s holding
A water rights permittee is entitled to equitable relief from cancellation if they continuously worked the land despite failing to timely file proof of beneficial use.
4
GREENEngelmann v. Westergard, 647 P.2d 385 (Nev. 1982).
cites § 533.380 2×subsections: (3) 2×cited by 15 cases
Where it cites § 533.380
“Where a water permit is in poor standing or subject to cancellation, NRS 533.380(3) provides: The state engineer shall have authority, for good cause shown, to extend the time within which construction work shall begin, within which construction work shall be completed, or water…”
The case’s holding
Exhaustion of administrative remedies is not required when the administrative process is futile or the agency lacks jurisdiction.
Later courts cite it for
“agency clearly lacks jurisdiction.” · 2 citing courts
5
NO FLAGSierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).
cites § 533.380 32×subsections: (3) 12× (3)(b) 4×cited by 0 cases
Where it cites § 533.380
“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
6
GREENAnsolabehere v. Laborde, 310 P.2d 842 (Nev. 1957).
cites § 533.380 1×cited by 12 cases
Where it cites § 533.380
“Prior to the Taylor Grazing Act federal permission to graze the public lands was not involved in the making of proof of application to beneficial use under stockwatering applications and could be made through the showing that a specified number of the applicant’s sheep, cattle,…”
The case’s holding
State statutes governing the grazing use of public lands are superseded and rendered ineffective by the enactment of the Taylor Grazing Act.
Later courts cite it for
“govern the grazing use of the public lands it was superseded and rendered ineffective by the enactment by congress of what is known as the taylor grazing act.” · 2 citing courts
7
NO FLAGSierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).
cites § 533.380 16×subsections: (3) 6× (3)(b) 2×cited by 0 cases
Where it cites § 533.380
“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
8
NO FLAGState Eng'r v. Happy Creek, Inc., 2019 NV 41 (Nev. 2019).
cites § 533.380 4×subsections: (3) 4×cited by 0 cases
Where it cites § 533.380
“See NRS 533.380(3); NRS 533.410. On May 19, 2016, the State Engineer mailed Happy Creek notice that it needed to file the PBUs (or EOTs) within 30 days to avoid cancellation.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195719882019

One bar per year. Tallest: 4 cases in 2019. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By subsection
(1)(a)1 case
Bailey v. State, 594 P.2d 734 (Nev. 1979).“This principle has been incorporated into the state water law, and is reflected in NRS 533.380(l)(a) which requires that in his endorsement of approval upon an application for the appropriation of water the State Engineer shall “[s]et a time prior to which actual construction…”
(1)(c)1 case
Bailey v. State, 594 P.2d 734 (Nev. 1979).
(3)5 cases
Sierra Pac. Indus. v. Wilson, 440 P.3d 37 (Nev. 2019).“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
Engelmann v. Westergard, 647 P.2d 385 (Nev. 1982).“Where a water permit is in poor standing or subject to cancellation, NRS 533.380(3) provides: The state engineer shall have authority, for good cause shown, to extend the time within which construction work shall begin, within which construction work shall be completed, or water…”
Sierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
Sierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).“Intermountain has since applied for and received numerous extensions pursuant to NRS 533.380 to extend the time of construction and to put the water to beneficial use.”
State Eng'r v. Happy Creek, Inc., 2019 NV 41 (Nev. 2019).“See NRS 533.380(3); NRS 533.410. On May 19, 2016, the State Engineer mailed Happy Creek notice that it needed to file the PBUs (or EOTs) within 30 days to avoid cancellation.”
(3)(b)3 cases
Sierra Pac. Indus. v. Wilson, 440 P.3d 37 (Nev. 2019).
Sierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).
Sierra Pac. Indus. v. Wilson, 2019 NV 13 (Nev. 2019).
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Nevada Revised Statutes Home  |  Search Nevada  |  Search cases for this section  |  syfert.com