Ohio Rev. Code § 1311.13 (2026)
Attaching of liens - continuance and priority
Edition and currency
Other sources
Courts have cited this section in 25 opinions since 1958. The most litigated part is subsection (A)(2) (4 cases).
(A)(1) All liens under sections 1311.01 to 1311.22 of the Revised Code for labor or work performed or materials furnished to the same improvement prior to the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code are effective from the date the first visible work or labor is performed or the first materials are furnished by the first original contractor, subcontractor, material supplier, or laborer to work, labor on, or provide materials to the improvement.
(2) Except as provided in division (A)(3) of this section, liens under sections 1311.01 to 1311.22 of the Revised Code for labor or work performed or materials furnished after the recording of a notice of commencement pursuant to section 1311.04 of the Revised Code are effective from the date of the recording of the notice of commencement.
(3) Notwithstanding division (A)(2) of this section, if there is a valid and recorded lien with an effective date described in division (A)(1) of this section which has not been released at the time a lien is filed by a laborer after the recording of the notice of commencement or if a valid lien against the improvement pursuant to division (A)(1) of this section is filed subsequent to the filing of a laborer's lien, the lien of the laborer is effective from the date the first visible labor or work was performed or materials were furnished by the original contractor, subcontractor, material supplier, or laborer at the site of the improvement.
(B)(1) Except for the liens of laborers as provided in division (B)(2) of this section, a lien securing the claim of a claimant who has performed labor or work or furnished materials both prior to and after the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code has two effective dates. That portion of the lien which arises from labor or work performed or materials furnished prior to the filing of the notice of commencement has the effective date described in division (A)(1) of this section and that portion of the lien which arises from labor or work performed or materials furnished on or after the filing of the notice of commencement has the effective date described in division (A)(2) of this section. Any payment received by the lien claimant both before and after the filing of a lien shall be applied first to the labor or work performed or materials furnished prior to the filing of the notice of commencement, and then to labor or work performed or materials furnished on and after the filing of the notice of commencement.
(2) A lien filed by a laborer for labor or work performed both prior to and after the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code has one effective date as described in division (A)(1) of this section.
(C) Liens under sections 1311.01 to 1311.22 of the Revised Code continue in force for six years after an affidavit is filed in the office of the county recorder under section 1311.06 of the Revised Code. If an action is brought to enforce the lien within that time, the lien continues in force until final adjudication thereof.
(D) If several liens are obtained by several persons upon the same improvement they have no priority among themselves, except as follows:
(1) Liens which have an effective date described in division (A)(1) of this section have priority over all other liens, except for liens described in divisions (A)(3), (B)(2), or (D)(2) of this section, to the extent of the value of the work and labor performed and materials furnished prior to the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code.
(2) Liens filed by laborers have priority over all other liens whether the labor or work was performed before or after the recording of the notice of commencement pursuant to section 1311.04 of the Revised Code.
(E)(1) Except as provided in division (E)(2) of this section, liens which have an effective date described in division (A)(1) of this section shall be preferred to the extent of the value of the labor or work performed or materials furnished prior to the recording of the notice of commencement, to all other titles, liens, or encumbrances which may attach to or upon the improvement or to or upon the land upon which it is situated, which either shall be given or recorded subsequent to the effective date of the liens described in division (A)(1) of this section.
(2) Liens recorded by laborers which have an effective date described in division (A)(1) or (3) of this section shall be preferred to all other titles, liens, or encumbrances which may attach to or upon the improvement or to or upon the land upon which it is situated which are given or recorded subsequent to the effective date of such laborers' liens.
(F) Liens which have an effective date described in division (A)(2) of this section shall be preferred to all other titles, liens, or encumbrances which may attach to or upon such improvement or to or upon the land upon which it is situated, which either are given or recorded subsequent to the recording of the notice of commencement.
(G) Unless otherwise stipulated in a mortgage securing financing for the construction of an improvement, if a mortgage securing financing for the construction of an improvement and notice of commencement for said improvement are recorded on the same day, the mortgage shall be considered recorded before the notice of commencement for purposes of priority described in this section.
(H) The recorder may destroy the record of all mechanics' liens which have been recorded for a period of ten years or longer.
- Where it cites § 1311.13
- “First, Guernsey assets that appellees cannot rely upon R.C. 1311.13 to claim priority over its mortgage.”
- The case’s holding
- Actions to enforce a mechanic's lien are in rem and do not entitle a lienholder to recover prejudgment interest.
- Later courts cite it for
- “all actions to enforce a mechanics' lien are in rem whenever a holder of a mechanics' lien enforces its lien in court, it recovers against the property based upon a statutorily-granted right” · 2 citing courts
- Where it cites § 1311.13
- “The case of a vendee’s payment after the attaching of mechanics’ liens is covered by Section 1311.13, Revised Code, which provides as follows: “Liens under Sections 1311.01 to 1311.24, inclusive, of the Revised Code are effective from the date the first labor is performed, or the first machinery, materials, or fuel is furnished by the contractor under the original contract, and shall continue for six years after an affidavit is filed in the office of the County Recorder under Section 1311.06 of the Revised Code.”
- The case’s holding
- A deed passes title upon its proper execution and delivery regardless of whether it is recorded.
- Later courts cite it for
- “when work is done pursuant to a contract with the vendee, mechanics' liens attach ... at the time of the commencement of construction ...” · 3 citing courts
- Summary
- No passage or summary on file for this case yet.
- Where it cites § 1311.13
- “14, not R.C. 1311.13 applies in the case sub judice.”
- Where it cites § 1311.13
- “14 have priority over mechanics’ liens. “R.C. 1311.14, .”
- Where it cites § 1311.13
- “The appellants base their claim to priority upon the provisions of Paragraph (B) of Section 1311.13, Revised Code. That section, so far as pertinent, reads: “Liens under Sections 1311.01 to 1311.24, inclusive, of the Revised Code are effective from the date the first labor is performed, or the first machinery, materials, or fuel is furnished by the contractor under the original contract * *.”
- Where it cites § 1311.13
- “The trial court erred in finding the Contractors’ mechanic’s liens were effective pursuant to R.C. 1311.13 prior to the recording of Home Savings’ Mortgage.”
- Later courts cite it for
- “in accord with the understanding of all parties, the trial court specifically stated that the issues of validity and amounts owed to the lienholders were matters for later decision.” · 2 citing courts
- Where it cites § 1311.13
- “Ohio law provides the owner of property encumbered by a mechanics’ lien with the right to serve a notice to the lienholder to commence suit, thereby compelling the lien-holder to either enforce his lien or forfeit it.”
- Where it cites § 1311.13
- “(“Baumann”) requests a determination that its mechanics’ liens have priority over a mortgage on property held by National City Bank (“NCB”) as per O.R.C. § 1311.13. This Court is vested with jurisdiction over this matter pursuant to 28 U.”
- Where it cites § 1311.13
- “Ohio Revised Code § 1311.13 provides that after the filing of a mechanics’ or materialmen lien affidavit the liens “are *886 effective from the date the first labor is performed, or the first machinery, materials, or fuel is furnished by the contractor under the original contract ____” Ohio Rev.Code…”
- Where it cites § 1311.13
- “Ohio Rev.Code § 1311.13. The lien is a statutory lien, and not a judicial lien, because no judicial action was necessary for its creation.”
- Later courts cite it for
- “the fact that the state court judgment later recognized the lien and empowered the harlans to enforce it does not change its character to a judicial lien.” · 2 citing courts
- Where it cites § 1311.13
- “According to Ohio Rev.Code Ann. § 1311.13 (Baldwin 1992), the mechanic’s lien is effective either upon the first day that performance commences or delivery of the first material.”
- Where it cites § 1311.13
- “In its first assignment of error, Huntington quarrels with the trial court’s application of only one portion of R.C. 1311.13 — its interpretation of the meaning of the term “commencement of * * * construction” within the context of the circumstances of this case.”
- Later courts cite it for
- “in order for the work to be deemed the commencement of construction, it must form a part of the work necessary for the construction and be of a nature that can afterward be considered a component part of the structure.” · 2 citing courts
- Where it cites § 1311.13
- “Section 1311.13(272). “Liens under Sections 1311.01 to 1311.-24, inclusive, of the Revised Code are effective from the date the first labor is performed, or the first machinery, materials, or fuel is furnished by the contractor under the original contract, and shall continue for six years after an affidavit is filed in the office of the county recorder under section 1311.06 of the Revised Code.”
- Where it cites § 1311.13
- “14, ... directs that mortgages used to finance improvements to real estate and which are otherwise in compliance with the requirements outlined therein, have priority over subsequently filed R.”
- Where it cites § 1311.13
- “s mortgage and for which the mortgage ostensibly stands as security, who, as between the mortgagee and a materialman, has priority and what is the extent of such priority! Since the mortgage agreement in the instant case does not impose upon appellee the duty to make mandatory…”
- Where it cites § 1311.13
- “Ohio Rev.Code § 1311.13. Based on these statutes, Basic’s efforts to perfect its liens are outside the scope of the automatic stay’s protective parameters.”
- Where it cites § 1311.13
- “R.C. 1311.13. However, Ohio’s construction mortgage statute, R.”
- Where it cites § 1311.13
- “See Ohio Rev.Code § 1311.13(F). On October 7, 2002, Hotel Builders amended its complaint to clarify that the actual filing date of the Notice of Commencement was April 9, 2001.”
- Where it cites § 1311.13
- “amended affidavit for record at any time during the time that the lien acquired by the original affidavit continues in effect under section 1311.13 of the Revised Code. In no event shall the amended affidavit extend such time period.”
Show all 25 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 4 cases in 2003. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(A)3 cases
(A)(1)3 cases
(A)(2)4 cases
(A)(3)1 case
(B)4 cases
(B)(1)1 case
(C)1 case
(F)2 cases
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.