Ohio Revised Code homeSearch Ohio
Ohio Rev. CodeChapter 153

Ohio Rev. Code § 153.12 (2026)

Awarding and executing contract

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1980–2017 21citing cases
At a glance

Courts have cited this section in 21 opinions since 1980. The most litigated part is subsection (B) (10 cases).

(A) With respect to award of any contract for the construction, reconstruction, improvement, enlargement, alteration, repair, painting, or decoration of a public improvement made by the state, or any county, township, municipal corporation, school district, or other political subdivision, or any public board, commission, authority, instrumentality, or special purpose district of or in the state or a political subdivision or that is authorized by state law, the award, and execution of the contract, shall be made within sixty days after the date on which the bids are opened. The failure to award and execute the contract within sixty days invalidates the entire bid proceedings and all bids submitted, unless the time for awarding and executing the contract is extended by mutual consent of the owner or its representatives and the bidder whose bid the owner accepts and with respect to whom the owner subsequently awards and executes a contract. The public owners referred to in this section shall include, in the plans and specifications for the project for which bids are solicited, the estimate of cost. The bid for which the award is to be made shall be opened at the time and place named in the advertisement for bids, unless extended by the owner or its representative or unless, within seventy-two hours prior to the published time for the opening of bids, excluding Saturdays, Sundays, and legal holidays, any modification of the plans or specifications and estimates of cost for the project for which bids are solicited is issued and mailed or otherwise furnished to persons who have obtained plans or specifications for the project, for which the time for opening of bids shall be extended one week, with no further advertising of bids required. The contractor, upon request, is entitled to a notice to proceed with the work by the owner or its representative upon execution of the contract. No contract to which this section applies shall be entered into if the price of the contract, or, if the project involves multiple contracts where the total price of all contracts for the project, is in excess of ten per cent, in the case of a contract made by the state or a public board, commission, authority, or instrumentality of the state, or twenty per cent, in the case of a contract made by a county, township, municipal corporation, school district, special purpose district, or other political subdivision or a public board, commission, authority, or instrumentality of the political subdivision, above the entire estimate thereof, nor shall the entire cost of the construction, reconstruction, repair, painting, decorating, improvement, alteration, addition, or installation, including changes and estimates of expenses for architects or engineers, exceed in the aggregate the amount authorized by law.

The unit or lump sum price stated in the contract shall be used in determining the amount to be paid and shall constitute full and final compensation for all the work.

Partial payment to the contractor for work performed under the lump sum price shall be based on a schedule prepared by the contractor and approved by the architect or engineer who shall apportion the lump sum price to the major components entering into or forming a part of the work under the lump sum price.

Partial payments to the contractor for labor performed under either a unit or lump sum price contract shall be made at a rate of not less than ninety-six per cent of the estimates prepared by the contractor and approved by the architect or engineer. No subcontract shall be paid at a rate lower than the rate being paid to the contractor by the public authority.

The amounts and time of payments of any public improvements contract made by the state or any county, township, municipal corporation, school district, or other political subdivision, or any public board, commission, authority, instrumentality, or special purpose district of or in the state or a political subdivision or that is authorized by state law, except as provided in section 5525.19 of the Revised Code, shall be governed by this section and sections 153.13 and 153.14 of the Revised Code. If the time for awarding the contract is extended by mutual consent, or if the owner or its representative fails to issue a timely notice to proceed as required by this section, the owner or its representative shall issue a change order authorizing delay costs to the contractor, which does not invalidate the contract. The amount of such a change order to the owner shall be determined in accordance with the provisions of the contract for change orders or force accounts or, if no such provision is set forth in the contract, the cost to the owner shall be the contractor's actual costs including wages, labor costs other than wages, wage taxes, materials, equipment costs and rentals, insurance, and subcontracts attributable to the delay, plus a reasonable sum for overhead. In the event of a dispute between the owner and the contractor concerning such change order, procedures shall be commenced under the applicable terms of the contract, or, if the contract contains no provision for resolving the dispute, it shall be resolved pursuant to the procedures for arbitration in Chapter 2711. of the Revised Code, except as provided in division (B) of this section. Nothing in this division shall be construed as a limitation upon the authority of the director of transportation granted in Chapter 5525. of the Revised Code.

(B) If a dispute arises between the state and a contractor concerning the terms of a public improvement contract let by the state or concerning a breach of the contract, and after administrative remedies provided for in such contract and any alternative dispute resolution procedures provided in accordance with guidelines established by the executive director of the Ohio facilities construction commission are exhausted, the contractor may bring an action to the court of claims in accordance with Chapter 2743. of the Revised Code. The state or the contractor may request the chief justice of the supreme court to appoint a referee or panel of referees in accordance with division (C)(3) of section 2743.03 of the Revised Code. As used in this division, "dispute" means a disagreement between the state and the contractor concerning a public improvement contract let by the state.

(C) When utilizing an industry standard published construction management contract form, the public authority shall provide the contract form in a manner that indicates any alteration to the standard form by striking through and underlining any changes to the original language of the standard form, by cross-referencing conditions that are supplemental to the standard form, or by including conditions that are supplemental to the standard form that cross-reference the section or sections of the standard form being altered. Failure to indicate an alteration to the original language of the standard form in the manner required above results in the alteration being void and without effect such that the original language prevails.

Last updated July 6, 2026 at 10:00 AM

The 20 cases that cite Ohio Rev. Code § 153.12 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENPrime Contractors, Inc. v. City of Girard, 655 N.E.2d 411 (Ohio Ct. App. 11th Dist. 1995).
cites § 153.12 14×cited by 6 cases
Where it cites § 153.12
“” In addition to responding to the foregoing assignments, appellee has advanced two cross-assignments: *254 “The trial court erred in applying R.C. 153.12 to the award of a contract for a road resurfacing project by a municipal corporation through the competitive bidding process.”
2
GREENWhite Hat Mgmt., L.L.C. v. Ohio Farmers Ins., 856 N.E.2d 991 (Ohio Ct. App. 9th Dist. 2006).
cites § 153.12 7×subsections: (A) 2×cited by 6 cases
Where it cites § 153.12
“Metro contends that the evidence supports application of the two-part acceptance process detailed in Hughes .”
Later courts cite it for
“a statement by the obligor to the obligee indicating that the obligor will commit a breach that would of itself give the obligee a claim for damages for total breach.” · 1 citing court
3
GREENHughes-Bechtol, Inc. v. Ohio (In re Hughes-Bechtol, Inc.), 124 B.R. 1007 (Bankr. S.D. Ohio 1991).
cites § 153.12 6×subsections: (A) 2×cited by 11 cases
Where it cites § 153.12
“COUNT VII: The debtor alleges that at a hearing, provided for pursuant to O.R.C. § 153.12, held by the Deputy Director on December 15, 1988, the debtor presented evidence which demonstrated that due to the negligence of AA in the preparation of the drawings and specifications,…”
cites § 153.12 2×cited by 30 cases
Where it cites § 153.12
“03(C)(3) states: “When any dispute under division (B) of section 153.12 of the Revised Code is brought to the court of claims, upon request of either party to the dispute, the chief justice of the supreme court shall appoint a single referee or a panel of three referees.”
The case’s holding
A plain and unambiguous construction contract is enforced as written, and does not become ambiguous merely because it works a hardship on one party, including for plan-change delay claims.
5
GREENHughes-Bechtol, Inc. v. State (In re Hughes-Bechtol, Inc.), 141 B.R. 946 (Bankr. S.D. Ohio 1992).
cites § 153.12 3×subsections: (B) 2×cited by 19 cases
Where it cites § 153.12
“Although administrative remedies have been sought by Hughes as contemplated by Ohio Revised Code § 153.12, and pursuant to these administrative remedies an “Article VIII hearing” was held on December 15, 1988 (Doc.”
Later courts cite it for
“a proceeding, as a whole, is determined to be core or non-core; however, in reaching this determination, each cause of action and each cause of action asserted against each defendant, is separately examined.” · 3 citing courts
6
GREENErnst v. Ohio Dep't of Admin. Servs., 590 N.E.2d 812 (Ohio Ct. App. 10th Dist. 1990).
cites § 153.12 5×subsections: (B) 3×cited by 5 cases
Where it cites § 153.12
“02(A) since R.C. 153.12 expressly refers to R.C. Chapter 2743.”
Later courts cite it for
“the common-law defense of recoupment to reduce damages sought to be recovered by a plaintiff.” · 2 citing courts
7
GREENOhio Bus Sales, Inc. v. Toledo Bd. of Educ., 610 N.E.2d 1164 (Ohio Ct. App. 6th Dist. 1992).
cites § 153.12 2×cited by 18 cases
Where it cites § 153.12
“The board may reject all the bids, or accept any bid for both labor and material for such improvement or repair, which is the lowest in the aggregate.”
8
GREENConti Corp. v. Ohio Dep't of Admin. Servs., 629 N.E.2d 1073 (Ohio Ct. App. 10th Dist. 1993).
cites § 153.12 2×subsections: (B)cited by 16 cases
Where it cites § 153.12
“14 is the approval of the “architect or engineer” referred to in R.C. 153.12. Ernst, 69 Ohio App.3d at 337-338 , 590 N.”
9
GREENDies Elec. Co. v. City of Akron, 405 N.E.2d 1026 (Ohio 1980).
cites § 153.12 1×cited by 30 cases
Where it cites § 153.12
“13 provides, in applicable part: “***From the date the contract is fifty percent complete, as evidenced by payments in the amount of at least fifty per cent of the contract to the person with whom the owner has contracted, all funds retained pursuant to sections 153.12 and…”
The case’s holding
A charter municipality may enact retainage provisions for municipal property improvement contracts that differ from state statutory provisions through its powers of local self-government.
Later courts cite it for
“a charter municipality, in the exercise of its powers of local self-government under section 3 of article xviii of the constitution of ohio, may, pursuant to its charter, enact retainage provisions for a contract for improvements to municipal property which differ from the retainage provisions prescribed in r.c. 153.13 .” · 2 citing courts
10
GREENWood Elec., Inc. v. Ohio Facilities Constr. Comm'n, 2017-Ohio-2743, 90 N.E.3d 371.
cites § 153.12 1×subsections: (B)cited by 3 cases
Where it cites § 153.12
“) To support this proposition, the OFCC relies on R.C. 153.12(B) and cases stating that, as a matter of statute, a contractor in a public contract with the State must exhaust contractual remedies before pursuing a suit in the Court of Claims.”
11
GREENOhio Contractors Ass'n v. City of Columbus, 733 F. Supp. 1156 (S.D. Ohio 1990).
cites § 153.12 5×cited by 1 case
Where it cites § 153.12
“Defendants argue that the City of Columbus is a chartered home rule municipality exercising the powers of self-government under Ohio’s Home Rule Amendment, Art.”
12
NEUTRALMacKinnon-parker, Inc. v. Lucas Metro. Hous. Auth., 616 N.E.2d 1204 (Ohio Ct. App. 6th Dist. 1992).
cites § 153.12 4×cited by 6 cases
Where it cites § 153.12
“Appellee argues that no contract existed because no formal written contract was executed in this case, as required by the bid documents and by R.C. 153.12. Summary judgment is appropriate if: “the pleading, depositions, answers to interrogatories, written admissions, affidavits,…”
Later courts cite it for
“this two-part acceptance of the contract may be imposed by the invitation to accept the bids or by virtue of the fact that the party seeking the bid is authorized by statute to contract only under certain circumstances, i. e., by a formal written contract.” · 1 citing court
cites § 153.12 18×subsections: (A) 3× (B)cited by 0 cases
Where it cites § 153.12
“54; listed bidding procedures must be followed, but “in all other respects,” the award of the contract shall be pursuant to R.C. 153.12; and the board shall pay the contract price for the work pursuant to R.”
cites § 153.12 5×subsections: (B) 3×cited by 1 case
Where it cites § 153.12
“After the end of this one hundred twenty-day period, the contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of section 153.12 of the Revised Code.” Case No.”
15
NEUTRALConn Constr. Co. v. Ohio Dep't of Transp., 470 N.E.2d 176 (Ohio Ct. App. 10th Dist. 1983).
cites § 153.12 1×cited by 7 cases
Where it cites § 153.12
“Second, R.C. 153.12 (C) provides that the parties may request the Court of Claims to appoint a referee or panel of referees in accordance with R.”
16
NO FLAGChaney v. Vill. of Lordstown, 486 N.E.2d 233 (Ohio Ct. App. 1984).
cites § 153.12 13×cited by 0 cases
Where it cites § 153.12
“Chaney’s first contention is that the original plans and specifications did not include an estimate of the costs of the project as required by R.C. 153.12. R.C. 153.12, in pertinent part, provides: “(A) * * * The public owners referred to in this section shall include, in the…”
cites § 153.12 6×subsections: (B) 4×cited by 0 cases
Where it cites § 153.12
“After the end of this one hundred twenty-day period, the contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of section 153.12 of the Revised Code.” See Painting Co.”
cites § 153.12 8×cited by 0 cases
Where it cites § 153.12
“THE TRIAL COURT ERRED, AS A MATTER OF LAW, BY ALLOWING DEFENDANTS-APPELLEES TO MODIFY PUBLICLY ADVERTISED BID SPECIFICATIONS AFTER BID OPENING AND TO AWARD A PUBLIC WORKS CONTRACT BASED ON UNADVERTISED BID SPECIFICATIONS IN VIOLATION OF O.R.C. § 153.12. {¶16} “II. THE TRIAL…”
cites § 153.12 3×subsections: (B) 2×cited by 0 cases
Where it cites § 153.12
“1 Pursuant to R.C. 153.12 (B) and 153.16 (B), plaintiff’s administrative remedies were deemed to have been exhausted 120 days after the claim was submitted under Article 8.”
cites § 153.12 3×subsections: (B) 3×cited by 0 cases
Where it cites § 153.12
“R.C. 153.12(B) provides in relevant part: “If a dispute arises between the state and a contractor concerning the terms of a public improvement contract let by the state or concerning a breach of the contract, and after the administrative remedies provided for in such a contract…”

Show all 21 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198019982017

One bar per year. Tallest: 3 cases in 1992. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ohio Ct. App.12Ohio Ct. Cl.4Ohio2Bankr. S.D. Ohio2S.D. Ohio1
By subsection
(A)3 cases
White Hat Mgmt., L.L.C. v. Ohio Farmers Ins., 856 N.E.2d 991 (Ohio Ct. App. 9th Dist. 2006).“Metro contends that the evidence supports application of the two-part acceptance process detailed in Hughes .”
Hughes-Bechtol, Inc. v. Ohio (In re Hughes-Bechtol, Inc.), 124 B.R. 1007 (Bankr. S.D. Ohio 1991).“COUNT VII: The debtor alleges that at a hearing, provided for pursuant to O.R.C. § 153.12, held by the Deputy Director on December 15, 1988, the debtor presented evidence which demonstrated that due to the negligence of AA in the preparation of the drawings and specifications,…”
Colaianni Constr., Inc. v. Indian Creek Local Sch. Dist., 2016-Ohio-8156.“54; listed bidding procedures must be followed, but “in all other respects,” the award of the contract shall be pursuant to R.C. 153.12; and the board shall pay the contract price for the work pursuant to R.”
(B)10 cases
Hughes-Bechtol, Inc. v. State (In re Hughes-Bechtol, Inc.), 141 B.R. 946 (Bankr. S.D. Ohio 1992).“Although administrative remedies have been sought by Hughes as contemplated by Ohio Revised Code § 153.12, and pursuant to these administrative remedies an “Article VIII hearing” was held on December 15, 1988 (Doc.”
Ernst v. Ohio Dep't of Admin. Servs., 590 N.E.2d 812 (Ohio Ct. App. 10th Dist. 1990).“02(A) since R.C. 153.12 expressly refers to R.C. Chapter 2743.”
Conti Corp. v. Ohio Dep't of Admin. Servs., 629 N.E.2d 1073 (Ohio Ct. App. 10th Dist. 1993).“14 is the approval of the “architect or engineer” referred to in R.C. 153.12. Ernst, 69 Ohio App.3d at 337-338 , 590 N.”
Wood Elec., Inc. v. Ohio Facilities Constr. Comm'n, 2017-Ohio-2743, 90 N.E.3d 371.“) To support this proposition, the OFCC relies on R.C. 153.12(B) and cases stating that, as a matter of statute, a contractor in a public contract with the State must exhaust contractual remedies before pursuing a suit in the Court of Claims.”
Aggressive Mech., Inc. v. Ohio Sch. Facilities Comm., 2012-Ohio-6332.“After the end of this one hundred twenty-day period, the contractor shall be deemed to have exhausted all administrative remedies for purposes of division (B) of section 153.12 of the Revised Code.” Case No.”
Showing the top 5 of 10. More in the list view →

Show all 21 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Ohio Revised Code Home  |  Search Ohio  |  Search cases for this section  |  syfert.com