U.S.C. homeSearch U.S. Code
U.S. CodeTitle 16Chapter 12— Federal Regulation and Development of PowerSubchapter I— Regulation of the Development of Water Power and Resources

16 U.S.C. § 803 (2026)

Conditions of license generally

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1929–2025 256citing cases
At a glance

Courts have cited this section in 256 opinions since 1929, 15 of them in the last five years. The most litigated part is subsection (c) (4 cases).

All licenses issued under this subchapter shall be on the following conditions:(a) Modification of plans; factors considered to secure adaptability of project; recommendations for proposed terms and conditions(1) That the project adopted, including the maps, plans, and specifications, shall be such as in the judgment of the Commission will be best adapted to a comprehensive plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, for the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat), and for other beneficial public uses, including irrigation, flood control, water supply, and recreational and other purposes referred to in section 797(e) of this title 11 So in original. Probably should be followed by “; and”. if necessary in order to secure such plan the Commission shall have authority to require the modification of any project and of the plans and specifications of the project works before approval.(2) In order to ensure that the project adopted will be best adapted to the comprehensive plan described in paragraph (1), the Commission shall consider each of the following:(A) The extent to which the project is consistent with a comprehensive plan (where one exists) for improving, developing, or conserving a waterway or waterways affected by the project that is prepared by—(i) an agency established pursuant to Federal law that has the authority to prepare such a plan; or(ii) the State in which the facility is or will be located.(B) The recommendations of Federal and State agencies exercising administration over flood control, navigation, irrigation, recreation, cultural and other relevant resources of the State in which the project is located, and the recommendations (including fish and wildlife recommendations) of Indian tribes affected by the project.(C) In the case of a State or municipal applicant, or an applicant which is primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities), the electricity consumption efficiency improvement program of the applicant, including its plans, performance and capabilities for encouraging or assisting its customers to conserve electricity cost-effectively, taking into account the published policies, restrictions, and requirements of relevant State regulatory authorities applicable to such applicant.(3) Upon receipt of an application for a license, the Commission shall solicit recommendations from the agencies and Indian tribes identified in subparagraphs (A) and (B) of paragraph (2) for proposed terms and conditions for the Commission’s consideration for inclusion in the license.(b) Alterations in project works

That except when emergency shall require for the protection of navigation, life, health, or property, no substantial alteration or addition not in conformity with the approved plans shall be made to any dam or other project works constructed hereunder of an installed capacity in excess of two thousand horsepower without the prior approval of the Commission; and any emergency alteration or addition so made shall thereafter be subject to such modification and change as the Commission may direct.

(c) Maintenance and repair of project works; liability of licensee for damages

That the licensee shall maintain the project works in a condition of repair adequate for the purposes of navigation and for the efficient operation of said works in the development and transmission of power, shall make all necessary renewals and replacements, shall establish and maintain adequate depreciation reserves for such purposes, shall so maintain, and operate said works as not to impair navigation, and shall conform to such rules and regulations as the Commission may from time to time prescribe for the protection of life, health, and property. Each licensee hereunder shall be liable for all damages occasioned to the property of others by the construction, maintenance, or operation of the project works or of the works appurtenant or accessory thereto, constructed under the license and in no event shall the United States be liable therefor.

(d) Amortization reserves

That after the first twenty years of operation, out of surplus earned thereafter, if any, accumulated in excess of a specified reasonable rate of return upon the net investment of a licensee in any project or projects under license, the licensee shall establish and maintain amortization reserves, which reserves shall, in the discretion of the Commission, be held until the termination of the license or be applied from time to time in reduction of the net investment. Such specified rate of return and the proportion of such surplus earnings to be paid into and held in such reserves shall be set forth in the license. For any new license issued under section 808 of this title, the amortization reserves under this subsection shall be maintained on and after the effective date of such new license.

(e) Annual charges payable by licensees; maximum rates; application; review and report to Congress(1) That the licensee shall pay to the United States reasonable annual charges in an amount to be fixed by the Commission for the purpose of reimbursing the United States for the costs of the administration of this subchapter, including any reasonable and necessary costs incurred by Federal and State fish and wildlife agencies and other natural and cultural resource agencies in connection with studies or other reviews carried out by such agencies for purposes of administering their responsibilities under this subchapter; for recompensing it for the use, occupancy, and enjoyment of its lands or other property; and for the expropriation to the Government of excessive profits until the respective States shall make provision for preventing excessive profits or for the expropriation thereof to themselves, or until the period of amortization as herein provided is reached, and in fixing such charges the Commission shall seek to avoid increasing the price to the consumers of power by such charges, and any such charges may be adjusted from time to time by the Commission as conditions may require: Provided, That, subject to annual appropriations Acts, the portion of such annual charges imposed by the Commission under this subsection to cover the reasonable and necessary costs of such agencies shall be available to such agencies (in addition to other funds appropriated for such purposes) solely for carrying out such studies and reviews and shall remain available until expended: Provided, That when licenses are issued involving the use of Government dams or other structures owned by the United States or tribal lands embraced within Indian reservations the Commission shall, subject to the approval of the Secretary of the Interior in the case of such dams or structures in reclamation projects and, in the case of such tribal lands, subject to the approval of the Indian tribe having jurisdiction of such lands as provided in section 5123 of title 25, fix a reasonable annual charge for the use thereof, and such charges may with like approval be readjusted by the Commission at the end of twenty years after the project is available for service and at periods of not less than ten years thereafter upon notice and opportunity for hearing: Provided further, That licenses for the development, transmission, or distribution of power by States or municipalities shall be issued and enjoyed without charge to the extent such power is sold to the public without profit or is used by such State or municipality for State or municipal purposes, except that as to projects constructed or to be constructed by States or municipalities primarily designed to provide or improve navigation, licenses therefor shall be issued without charge; and that licenses for the development, transmission, or distribution of power for domestic, mining, or other beneficial use in projects of not more than two thousand horsepower installed capacity may be issued without charge, except on tribal lands within Indian reservations; but in no case shall a license be issued free of charge for the development and utilization of power created by any Government dam and that the amount charged therefor in any license shall be such as determined by the Commission: Provided however, That no charge shall be assessed for the use of any Government dam or structure by any licensee if, before January 1, 1985, the Secretary of the Interior has entered into a contract with such licensee that meets each of the following requirements:(A) The contract covers one or more projects for which a license was issued by the Commission before January 1, 1985.(B) The contract contains provisions specifically providing each of the following:(i) A powerplant may be built by the licensee utilizing irrigation facilities constructed by the United States.(ii) The powerplant shall remain in the exclusive control, possession, and ownership of the licensee concerned.(iii) All revenue from the powerplant and from the use, sale, or disposal of electric energy from the powerplant shall be, and remain, the property of such licensee.(C) The contract is an amendatory, supplemental and replacement contract between the United States and: (i) the Quincy-Columbia Basin Irrigation District (Contract No. 14–06–100–6418); (ii) the East Columbia Basin Irrigation District (Contract No. 14–06–100–6419); or, (iii) the South Columbia Basin Irrigation District (Contract No. 14–06–100–6420).This paragraph shall apply to any project covered by a contract referred to in this paragraph only during the term of such contract unless otherwise provided by subsequent Act of Congress. In the event an overpayment of any charge due under this section shall be made by a licensee, the Commission is authorized to allow a credit for such overpayment when charges are due for any subsequent period.(2) In the case of licenses involving the use of Government dams or other structures owned by the United States, the charges fixed (or readjusted) by the Commission under paragraph (1) for the use of such dams or structures shall not exceed 1 mill per kilowatt-hour for the first 40 gigawatt-hours of energy a project produces in any year, 1½ mills per kilowatt-hour for over 40 up to and including 80 gigawatt-hours in any year, and 2 mills per kilowatt-hour for any energy the project produces over 80 gigawatt-hours in any year. Except as provided in subsection (f), such charge shall be the only charge assessed by any agency of the United States for the use of such dams or structures.(3) The provisions of paragraph (2) shall apply with respect to—(A) all licenses issued after October 16, 1986; and(B) all licenses issued before October 16, 1986, which—(i) did not fix a specific charge for the use of the Government dam or structure involved; and(ii) did not specify that no charge would be fixed for the use of such dam or structure.(4) Every 5 years, the Commission shall review the appropriateness of the annual charge limitations provided for in this subsection and report to Congress concerning its recommendations thereon.(f) Reimbursement by licensee of other licensees, etc.

That whenever any licensee hereunder is directly benefited by the construction work of another licensee, a permittee, or of the United States of a storage reservoir or other headwater improvement, the Commission shall require as a condition of the license that the licensee so benefited shall reimburse the owner of such reservoir or other improvements for such part of the annual charges for interest, maintenance, and depreciation thereon as the Commission may deem equitable. The proportion of such charges to be paid by any licensee shall be determined by the Commission. The licensees or permittees affected shall pay to the United States the cost of making such determination as fixed by the Commission.

Whenever such reservoir or other improvement is constructed by the United States the Commission shall assess similar charges against any licensee directly benefited thereby, and any amount so assessed shall be paid into the Treasury of the United States, to be reserved and appropriated as a part of the special fund for headwater improvements as provided in section 810 of this title.

Whenever any power project not under license is benefited by the construction work of a licensee or permittee, the United States or any agency thereof, the Commission, after notice to the owner or owners of such unlicensed project, shall determine and fix a reasonable and equitable annual charge to be paid to the licensee or permittee on account of such benefits, or to the United States if it be the owner of such headwater improvement.

(g) Conditions in discretion of commission

Such other conditions not inconsistent with the provisions of this chapter as the commission may require.

(h) Monopolistic combinations; prevention or minimization of anticompetitive conduct; action by Commission regarding license and operation and maintenance of project(1) Combinations, agreements, arrangements, or understandings, express or implied, to limit the output of electrical energy, to restrain trade, or to fix, maintain, or increase prices for electrical energy or service are hereby prohibited.(2) That conduct under the license that: (A) results in the contravention of the policies expressed in the antitrust laws; and (B) is not otherwise justified by the public interest considering regulatory policies expressed in other applicable law (including but not limited to those contained in subchapter II of this chapter) shall be prevented or adequately minimized by means of conditions included in the license prior to its issuance. In the event it is impossible to prevent or adequately minimize the contravention, the Commission shall refuse to issue any license to the applicant for the project and, in the case of an existing project, shall take appropriate action to provide thereafter for the operation and maintenance of the affected project and for the issuing of a new license in accordance with section 808 of this title.(i) Waiver of conditions

In issuing licenses for a minor part only of a complete project, or for a complete project of not more than two thousand horsepower installed capacity, the Commission may in its discretion waive such conditions, provisions, and requirements of this subchapter, except the license period of fifty years, as it may deem to be to the public interest to waive under the circumstances: Provided, That the provisions hereof shall not apply to annual charges for use of lands within Indian reservations.

(j) Fish and wildlife protection, mitigation and enhancement; consideration of recommendations; findings(1) That in order to adequately and equitably protect, mitigate damages to, and enhance, fish and wildlife (including related spawning grounds and habitat) affected by the development, operation, and management of the project, each license issued under this subchapter shall include conditions for such protection, mitigation, and enhancement. Subject to paragraph (2), such conditions shall be based on recommendations received pursuant to the Fish and Wildlife Coordination Act (16 U.S.C. 661 et seq.) from the National Marine Fisheries Service, the United States Fish and Wildlife Service, and State fish and wildlife agencies.(2) Whenever the Commission believes that any recommendation referred to in paragraph (1) may be inconsistent with the purposes and requirements of this subchapter or other applicable law, the Commission and the agencies referred to in paragraph (1) shall attempt to resolve any such inconsistency, giving due weight to the recommendations, expertise, and statutory responsibilities of such agencies. If, after such attempt, the Commission does not adopt in whole or in part a recommendation of any such agency, the Commission shall publish each of the following findings (together with a statement of the basis for each of the findings):(A) A finding that adoption of such recommendation is inconsistent with the purposes and requirements of this subchapter or with other applicable provisions of law.(B) A finding that the conditions selected by the Commission comply with the requirements of paragraph (1).Subsection (i) shall not apply to the conditions required under this subsection.(June 10, 1920, ch. 285, pt. I, § 10, 41 Stat. 1068; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 206, 212, 49 Stat. 842, 847; Pub. L. 87–647, Sept. 7, 1962, 76 Stat. 447; Pub. L. 90–451, § 4, Aug. 3, 1968, 82 Stat. 617; Pub. L. 99–495, §§ 3(b), (c), 9(a), 13, Oct. 16, 1986, 100 Stat. 1243, 1244, 1252, 1257; Pub. L. 99–546, title IV, § 401, Oct. 27, 1986, 100 Stat. 3056; Pub. L. 102–486, title XVII, § 1701(a), Oct. 24, 1992, 106 Stat. 3008.)Editorial NotesReferences in Text

The Fish and Wildlife Coordination Act, referred to in subsec. (j)(1), is act Mar. 10, 1934, ch. 55, 48 Stat. 401, which is classified generally to sections 661 to 666c–1 of this title. For complete classification of this Act to the Code, see section 661(a) of this title, Short Title note set out under section 661 of this title, and Tables.

Amendments

1992—Subsec. (e)(1). Pub. L. 102–486, in introductory provisions, substituted “administration of this subchapter, including any reasonable and necessary costs incurred by Federal and State fish and wildlife agencies and other natural and cultural resource agencies in connection with studies or other reviews carried out by such agencies for purposes of administering their responsibilities under this subchapter;” for “administration of this subchapter;” and inserted “Provided, That, subject to annual appropriations Acts, the portion of such annual charges imposed by the Commission under this subsection to cover the reasonable and necessary costs of such agencies shall be available to such agencies (in addition to other funds appropriated for such purposes) solely for carrying out such studies and reviews and shall remain available until expended:” after “as conditions may require:”.

1986—Subsec. (a). Pub. L. 99–495, § 3(b), designated existing provisions as par. (1), inserted “for the adequate protection, mitigation, and enhancement of fish and wildlife (including related spawning grounds and habitat),” after “water-power development”, inserted “irrigation, flood control, water supply, and” after “including”, which words were inserted after “public uses, including” as the probable intent of Congress, substituted “and other purposes referred to in section 797(e) of this title” for “purposes; and”, and added pars. (2) and (3).

Subsec. (e). Pub. L. 99–546 inserted proviso that no charge be assessed for use of Government dam or structure by licensee if, before Jan. 1, 1985, licensee and Secretary entered into contract which met requirements of date of license, powerplant construction, ownership, and revenue, etc.

Pub. L. 99–495, § 9(a), designated existing provisions as par. (1) and added pars. (2) to (4).

Subsec. (h). Pub. L. 99–495, § 13, designated existing provisions as par. (1) and added par. (2).

Subsec. (j). Pub. L. 99–495, § 3(c), added subsec. (j).

1968—Subsec. (d). Pub. L. 90–451 provided for maintenance of amortization reserves on and after effective date of new licenses.

1962—Subsecs. (b), (e), (i). Pub. L. 87–647 substituted “two thousand horsepower” for “one hundred horsepower”.

1935—Subsec. (a). Act Aug. 26, 1935, § 206, substituted “plan for improving or developing a waterway or waterways for the use or benefit of interstate or foreign commerce, for the improvement and utilization of water-power development, and for other beneficial uses, including recreational purposes” for “scheme of improvement and utilization for the purposes of navigation, of water-power development, and of other beneficial public uses,” and “such plan” for “such scheme”.

Subsec. (b). Act Aug. 26, 1935, § 206, inserted “installed” before “capacity”.

Subsec. (d). Act Aug. 26, 1935, § 206, substituted “net investment” for “actual, legitimate investment”.

Subsec. (e). Act Aug. 26, 1935, § 206, amended subsec. (e) generally.

Subsec. (f). Act Aug. 26, 1935, § 206, inserted last sentence to first par., and inserted last par.

Subsec. (i). Act Aug. 26, 1935, § 206, inserted “installed” before “capacity”, and “annual charges for use of” before “lands” in proviso.

Statutory Notes and Related SubsidiariesEffective Date of 1986 Amendment

Amendment by Pub. L. 99–495 effective with respect to each license, permit, or exemption issued under this chapter after Oct. 16, 1986, see section 18 of Pub. L. 99–495, set out as a note under section 797 of this title.

Savings Provision

Pub. L. 99–495, § 9(b), Oct. 16, 1986, 100 Stat. 1252, provided that: “Nothing in this Act [see Short Title of 1986 Amendment note set out under section 791a of this title] shall affect any annual charge to be paid pursuant to section 10(e) of the Federal Power Act [16 U.S.C. 803(e)] to Indian tribes for the use of their lands within Indian reservations.”

Termination of Reporting Requirements

For termination, effective May 15, 2000, of provisions in subsec. (e)(4) of this section relating to reporting recommendations to Congress every 5 years, see section 3003 of Pub. L. 104–66, as amended, set out as a note under section 1113 of Title 31, Money and Finance, and page 91 of House Document No. 103–7.

Obligation for Payment of Annual Charges

Pub. L. 115–270, title III, § 3001(c), Oct. 23, 2018, 132 Stat. 3862, provided that: “Any obligation of a licensee or exemptee for the payment of annual charges under section 10(e) of the Federal Power Act (16 U.S.C. 803(e)) for a project that has not commenced construction as of the date of enactment of this Act [Oct. 23, 2018] shall commence not earlier than the latest of—“(1) the date by which the licensee or exemptee is required to commence construction; or“(2) the date of any extension of the deadline under paragraph (1).”

The 20 cases that cite 16 U.S.C. § 803 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENUnited States v. S. California Edison Co., 300 F. Supp. 2d 964 (E.D. Cal. 2004).
cites § 803 8×cited by 74 cases
Where it cites § 803
“Defendant correctly points out that 16 U.S.C. § 803 does not create a private cause of action against a FERC licensee by a party injured by the operation of its utility plant.”
The case’s holding
A court may take judicial notice of the existence and authenticity of public records but not of the veracity or validity of the arguments and disputed facts contained therein.
Later courts cite it for
“while the 21 authenticity and existence of a particular order, motion, pleading or judicial proceeding, 22 which is a matter of public record, is judicially noticeable, veracity and validity of its 23 contents . . . are not.” · 10 citing courts
2
GREENDaniel Allen v. United States, 83 F.4th 564 (6th Cir. 2023).
cites § 803 13×cited by 9 cases
Where it cites § 803
“16 U.S.C. § 803 (c). The parties’ competing interpretations focus largely on one clause, “constructed under the license.”
Later courts cite it for
“rule reflects the basic intuition that when a modifier appears at the end of a list, an ordinary reader would apply that modifier only to the item directly before it.” · 2 citing courts
3
GREENNez Perce Tribe v. Idaho Power Co., 847 F. Supp. 791 (D. Idaho 1994).
cites § 803 22×cited by 16 cases
Where it cites § 803
“The Tribe asserts that even if this Court finds that the Tribe’s cause of action is grounded in state common law, that this Court has jurisdiction pursuant to 16 U.S.C. § 803 (c). In the alternative, the Tribe argues that rather than preempting its cause of action, 16 U.”
cites § 803 4×cited by 262 cases
Where it cites § 803
“National Grid argues that the District’s assessment and apportionment scheme is federally preempted by the Federal Power Act (“FPA”), see 16 U.S.C. §§ 803 (f), 821, and that even if the assessment authority exists, all assessments made prior to 2010 violated National Grid’s…”
The case’s holding
The Federal Power Act does not preempt state authority to assess benefits on non-licensed, non-hydropower properties related to water-control projects.
Later courts cite it for
“a federal court may abstain from exercising jurisdiction when parallel state-court litigation could result in comprehensive disposition of litigation and abstention would conserve judicial resources.” · 28 citing courts
5
GREENJeff Simmons v. Sabine River Auth., 732 F.3d 469 (5th Cir. 2013).
cites § 803 4×cited by 66 cases
Where it cites § 803
“16 U.S.C. § 803 (a). Third, Section 10(c) of the Act is central to Plaintiffs’ arguments and our analysis.”
The case’s holding
The Federal Power Act preempts state law negligence claims where the alleged duty of care consists of actions that the federal regulator expressly declined to mandate.
Later courts cite it for
“damages claims can serve the same effect as regulations.” · 7 citing courts
cites § 803 4×cited by 209 cases
Where it cites § 803
“the power and development purposes for which licenses are issued, [FERC] shall give equal consideration to the purposes of energy conservation, the protection, mitigation of damage to, and enhancement of, fish and wildlife (including related spawning grounds and habitat), the…”
The case’s holding
The Clean Water Act requires the EPA to establish and enforce technology-based limitations on point source discharges into navigable waters.
Later courts cite it for
“is a comprehensive water quality statute designed to 'restore and maintain the chemical, physical, and biological integrity of the nation's waters.” · 16 citing courts
cites § 803 4×cited by 156 cases
The case’s holding
Statutory language is conclusive unless Congress expresses a contrary intention through its chosen words (interpreting the word shall as mandatory).
Later courts cite it for
“all aspects of indian sovereignty are subject to defeasance by congress.” · 4 citing courts
cites § 803 4×cited by 14 cases
Where it cites § 803
“; see 16 U.S.C. § 803 (f). In the wake of Albany, Erie petitioned FERC to credit it for costs the District had assessed it in excess of the federally mandated costs.”
Later courts cite it for
“if an agency action fails to comply with its own regulations, that action may be set aside as arbitrary and capricious.” · 3 citing courts
cites § 803 6×cited by 166 cases
Where it cites § 803
“*751 The Cities alleged that Gulf, in concert with two other investor-owned utilities, Louisiana Power and Light Company (LP&L) and Central Louisiana Electric Company (CLECO), had engaged in activities "apparently violative of the anti-trust laws," as well as of § 10 (h) of the…”
The case’s holding
The Federal Power Commission interprets the public interest standard under the Federal Power Act (construing public interest standard under Federal Power Act).
Later courts cite it for
“to provide effective federal regulation of the expanding business of transmitting and selling electric power in interstate commerce.” · 9 citing courts
10
GREENNat'l Wildlife Fed'n v. Fed. Energy Regulatory Comm'n, 912 F.2d 1471 (D.C. Cir. 1990).
cites § 803 6×cited by 36 cases
Where it cites § 803
“16 U.S.C. § 803 (a)(1). The NWF, relying on this statute and LaFlamme v.”
The case’s holding
An environmental impact statement need only address the specific proposal at issue and other pending or recently approved connected proposals rather than hypothetical or speculative future projects.
Later courts cite it for
“an eis need not delve into the possible effects of a hypothetical project, but need only focus on the impact of the particular proposal at issue and other pending or recently approved proposals that might be connected to ... the proposal at issue” · 3 citing courts
11
GREENCity of Vanceburg v. Fed. Energy Regulatory Comm'n, 571 F.2d 630 (D.C. Cir. 1978).
cites § 803 6×cited by 35 cases
The case’s holding
The Commission may base dam-use charges on the actual value of the benefit received by a licensee, including real tax savings.
Later courts cite it for
“as the supreme court has stated, it is the purpose of this provision to give the commission notice of its alleged errors so that it may have the opportunity to correct them.” · 2 citing courts
12
GREENDep't of Ecology v. Pub. Util. Dist. No. 1, 849 P.2d 646 (Wash. 1993).
cites § 803 4×cited by 82 cases
Where it cites § 803
“16 U.S.C. § 803 (a). In order to ensure this, the FPA requires FERC to consider recommendations from state and federal agencies and Indian tribes.”
The case’s holding
A state may use section 401 of the Clean Water Act to impose conditions based on any appropriate state water quality-related law, including requirements to maintain base flows.
Later courts cite it for
“plerennial rivers and streams of the state shall be retained with base flows necessary to provide for the preservation of wildlife, fish, scenic, aesthetic and other environmental values, and navigational values.” · 2 citing courts
13
GREENAlbany Eng'g Corp. v. Fed. Energy Regulatory Comm'n, 548 F.3d 1071 (D.C. Cir. 2008).
cites § 803 4×cited by 27 cases
Where it cites § 803
“To enable the upstream firms to recoup part of the cost of conferring these "headwater benefits," Congress in § 10(f) of the Federal Power Act ("FPA"), 16 U.S.C. § 803 (f) (2006), directed the Federal Energy Regulatory Commission (technically the direction was to its…”
The case’s holding
Section 10(f) of the Federal Power Act preempts state laws authorizing headwater benefit assessments on downstream licensees for costs beyond interest, maintenance, and depreciation.
Later courts cite it for
“a complete scheme of national regulation, promoting the comprehensive development of the water resources of the nation.” · 3 citing courts
14
GREENUdall v. Fed. Power Comm'n, 387 U.S. 428 (1967).
cites § 803 6×cited by 101 cases
Where it cites § 803
“842 , 16 U. S. C. § 803 (a). The issues of whether deferral of construction would be more in the public interest than immediate construction and whether preservation of the reaches of the river affected would be more desirable and in the public interest than the proposed…”
The case’s holding
The primary test for licensing a hydroelectric project is whether the project serves the public interest.
Later courts cite it for
“future power demand and supply, alternative sources of power, the public interest in preserving reaches of wild rivers and wilderness areas, the preservation of anadromous fish for commercial and recreational purposes, and the protection of wildlife.” · 4 citing courts
15
GREENState of Wyoming v. United States, 279 F.3d 1214 (10th Cir. 2002).
cites § 803 2×cited by 119 cases
Where it cites § 803
“See 16 U.S.C. § 803 (a)(1)-(3) (FERC to issue license on conditions that protect fish and wildlife, after considering recommendations of state agencies), as amended by .”
The case’s holding
Sovereign immunity shields the United States from suits for specific relief unless Congress provides a waiver, and the Property Clause grants Congress plenary power to manage federal lands.
Later courts cite it for
“sovereign immunity generally shields the united states, its agencies, and officers acting in their official capacities from suit.” · 7 citing courts
16
cites § 803 3×cited by 126 cases
Where it cites § 803
“16 U. S. C. §803 (a) (1982 ed.). Congress’ subsequent amendments to those provisions expressly direct that FERC consider a project’s effect on fish and wildlife as well as “power and development purposes.”
The case’s holding
Courts must accord deference to longstanding agency decisions that interpret statutes underlying complex regulatory regimes.
Later courts cite it for
“a broad federal role in the development and licensing of hydroelectric power.” · 9 citing courts
cites § 803 4×cited by 276 cases
Where it cites § 803
“But, despite its general and all-inclusive terms, § 21 does not apply to nor authorize condemnation of lands or interests in lands owned by the United States, because § 10 (e) of the Act, 16 U. S. C. § 803 (e), expressly provides that "the licensee shall pay to the United States…”
The case’s holding
A general statute applying to all persons includes Indian tribes and their property interests held in fee simple.
Later courts cite it for
“a general statute in terms applying to all persons includes indians and their property interests.” · 41 citing courts
cites § 803 4×cited by 18 cases
Where it cites § 803
“See 16 U.S.C. §§ 803 (j), 811. Wisconsin Power and Light Company (“WP&L”) petitions for review of Commission orders placing conditions on its license as a result of the Secretary’s prescription.”
cites § 803 3×cited by 31 cases
Where it cites § 803
“] By directing FERC to consider the recommendations of state wildlife and other regulatory agencies while providing FERC with final authority to establish license conditions (including those with terms inconsistent with the States’ recommendations), Congress has amended the FPA…”
The case’s holding
State water quality requirements incorporated into federal licensing analysis become federal requirements for purposes of preemption analysis.
cites § 803 4×cited by 140 cases
Where it cites § 803
“842 , 16 U. S. C. § 803 (a). Thus, congressional approval of a comprehensive plan can be read, as we think it should in this case, simply as saying that a plan such as that here, recommended by the Corps of Engineers for the fullest realization of the potential benefits in the…”
The case’s holding
A government official has standing to challenge a licensing action if the action impacts the official's statutory duties regarding the conservation of natural resources.
Later courts cite it for
“complicated specialty of federal jurisdiction, the solution of whose problems is in any event more or less determined by the specific circumstances of individual situations. . . .” · 9 citing courts

Show all 256 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
192819762025

One bar per 2 years. Tallest: 13 cases in 1996–1997. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.699th Cir.37SCOTUS162d Cir.154th Cir.12N.Y. App. Div.75th Cir.6Cal. Ct. App.6

The 8 courts with the most citing cases, of 63 courts in all.

By subsection
(a)3 cases
Georgia Power Co. v. Fed. Power Comm'n, 152 F.2d 908 (5th Cir. 1946).
Rocky Mountain Power Co. v. Fed. Power Comm'n, 409 F.2d 1122 (D.C. Cir. 1969).
(c)4 cases
Skokomish Indian v. Tacoma Pub. Utils., 410 F.3d 506 (9th Cir. 2005).
Allen v. United States, 572 F. Supp. 3d 411 (E.D. Mich. 2021).
(d)1 case
Alabama Power Co. v. Fed. Power Comm'n, 482 F.2d 1208 (5th Cir. 1973).
(i)2 cases
United States v. S. Power Co., 31 F.2d 852 (4th Cir. 1929).

Show all 256 citing cases (list view) →

Enactment and amendments
(June 10, 1920, ch. 285, pt. I, § 10, 41 Stat. 1068; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 206, 212, 49 Stat. 842, 847; Pub. L. 87–647, Sept. 7, 1962, 76 Stat. 447; Pub. L. 90–451, § 4, Aug. 3, 1968, 82 Stat. 617; Pub. L. 99–495, §§ 3(b), (c), 9(a), 13, Oct. 16, 1986, 100 Stat. 1243, 1244, 1252, 1257; Pub. L. 99–546, title IV, § 401, Oct. 27, 1986, 100 Stat. 3056; Pub. L. 102–486, title XVII, § 1701(a), Oct. 24, 1992, 106 Stat. 3008.)
Amendment years (notes): 1992, 1986, 1968, 1962, 1935
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com