Skip to main content
U.S. CodeTitle 16Chapter 12B— Bonneville Project

16 U.S.C. § 832f (2026)

Elements in determining rates

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1980–1989 8citing cases
At a glance

Courts have cited this section in 8 opinions since 1980.

It is the intent of Congress that rate schedules for the sale of electric energy which is or may be generated at the Bonneville project in excess of the amount required for operating the dam, locks, and appurtenant works at said project shall be determined with due regard to and predicated upon the fact that such electric energy is developed from water power created as an incident to the construction of the dam in the Columbia River at the Bonneville project for the purposes set forth in section 832 of this title. Rate schedules shall be drawn having regard to the recovery (upon the basis of the application of such rate schedules to the capacity of the electric facilities of Bonneville project) of the cost of producing and transmitting such electric energy, including the amortization of the capital investment over a reasonable period of years. Rate schedules shall be based upon an allocation of costs made by the Secretary of Energy. In computing the cost of electric energy developed from water power created as an incident to and a byproduct of the construction of the Bonneville project, the Secretary of Energy may allocate to the costs of electric facilities such a share of the cost of facilities having joint value for the production of electric energy and other purposes as the power development may fairly bear as compared with such other purposes.

(Aug. 20, 1937, ch. 720, § 7, 50 Stat. 735; Pub. L. 95–91, title III, § 301(b), Aug. 4, 1977, 91 Stat. 578.)
The 8 cases that cite 16 U.S.C. § 832f most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 832f 1×cited by 38 cases
Where it cites § 832f
“See 16 U.S.C. § 832f (BPA rate schedules designed to recover BPA costs) H.”
The case’s holding
An agency's interpretation of its enabling statutes is valid if it is reasonable, even if it is not the only possible interpretation.
Later courts cite it for
“bpa is required to allocate use of federally-owned transmission facilities in a manner which accords preference first to transmission of federal power and then to transmission of other northwest-generated power.” · 2 citing courts
2
GREENPac. Power & Light Co. v. Duncan, 499 F. Supp. 672 (D. Or. 1980).
cites § 832f 2×cited by 9 cases
Where it cites § 832f
“, ¶ 1 , but the interim rates do not become final until confirmed and approved by the FERC, id. HH1, 2. In addition, the Secretary delegated his authority to the FERC “to exercise the cost allocation authority contained in Section 7 of the Bonneville Project Act [16 U.”
3
GREENCent. Lincoln Peoples' Util. Dist. v. Johnson, 735 F.2d 1101 (9th Cir. 1984).
cites § 832f 2×cited by 17 cases
The case’s holding
Non-constitutional challenges to wholesale power rates are not reviewable until the Federal Energy Regulatory Commission confirms and approves the rate determinations.
Later courts cite it for
“substantial evidence in the rulemaking record” · 4 citing courts
4
GREENAluminum Co. of Am. v. Bonneville Power Admin., 903 F.2d 585 (9th Cir. 1989).
cites § 832f 1×cited by 13 cases
Later courts cite it for
“the 'widespread use' requirement provides bpa with . . . so much discretion that there is no law to apply.” · 4 citing courts
5
GREENCP Nat'l Corp. v. Jura, 876 F.2d 745 (9th Cir. 1989).
cites § 832f 1×cited by 5 cases
Where it cites § 832f
“See also Bonneville Project Act of 1937, 16 U.S.C. § 832f (1982) (“[rjate schedules shall be drawn having regard to the recovery .”
6
GREENUtil. Reform Proj. v. Bonneville Power Admin., 869 F.2d 437 (9th Cir. 1989).
cites § 832f 1×cited by 4 cases
Where it cites § 832f
“” 16 U.S.C. § 832f. These procedures would not serve the purpose for which they were designed if they were required to be applied to this exchange.”
Later courts cite it for
“the unrestricted language of the statute gives the administrator expansive authority to settle contract claims.” · 3 citing courts
7
GREENAluminum Co. of Am. v. Bonneville Power Admin., 891 F.2d 748 (9th Cir. 1989).
cites § 832f 1×cited by 3 cases
Summary
No passage or summary on file for this case yet.
cites § 832f 1×cited by 2 cases
Where it cites § 832f
“3 This need to consider the interests of preserving competition, however, does not override BPA’s statutory obligations, repeatedly expressed in 16 U.S.C. §§ 832f, 838g, and 839e(a)(l), to be fiscally self-supporting.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198019841989

One bar per year. Tallest: 4 cases in 1989. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
9th Cir.7D. Or.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments
(Aug. 20, 1937, ch. 720, § 7, 50 Stat. 735; Pub. L. 95–91, title III, § 301(b), Aug. 4, 1977, 91 Stat. 578.)
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.