U.S.C. homeSearch U.S. Code
U.S. CodeTitle 16Chapter 12B— Bonneville Project

16 U.S.C. § 832 (2026)

Completion and maintenance of project; generation of electricity

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1951–2015 56citing cases
At a glance

Courts have cited this section in 56 opinions since 1951.

For the purpose of improving navigation on the Columbia River, and for other purposes incidental thereto, the dam, locks, power plant, and appurtenant works under construction on August 20, 1937, at Bonneville, Oregon and North Bonneville, Washington (called Bonneville project in this chapter), shall be completed, maintained, and operated under the direction of the Secretary of the Army and the supervision of the Chief of Engineers, subject to the provisions of this chapter relating to the powers and duties of the Bonneville power administrator provided for in section 832a(a) of this title (called the administrator in this chapter) respecting the transmission and sale of electric energy generated at said project. The Secretary of the Army shall provide, construct, operate, maintain, and improve at Bonneville project such machinery, equipment, and facilities for the generation of electric energy as the administrator may deem necessary to develop such electric energy as rapidly as markets may be found therefor. The electric energy thus generated and not required for the operation of the dam and locks at such project and the navigation facilities employed in connection therewith shall be delivered to the administrator, for disposition as provided in this chapter.

(Aug. 20, 1937, ch. 720, § 1, 50 Stat. 731; July 26, 1947, ch. 343, title II, § 205(a), 61 Stat. 501.)
The 20 cases that cite 16 U.S.C. § 832 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENS. California Edison v. United States, 58 Fed. Cl. 313 (Fed. Cl. 2003).
cites § 832 3×cited by 39 cases
Where it cites § 832
“Four separate acts constitute the principal components of this framework: the Bonneville Project Act of 1937, as amended, 16 U.S.C. §§ 832 -832m; the Pacific *315 Northwest Consumer Power Preference Act of 1964, as amended, 16 U.”
The case’s holding
Contract interpretation is a question of law that a court may resolve on a motion to dismiss, beginning with the written agreement's language and giving plain meaning to clear terms.
Later courts cite it for
“contract interpretation is a matter of law and thus may be addressed by the court in resolving a motion to dismiss.” · 8 citing courts
2
GREENPuget Sound Power & Light Co. v. United States, 23 Cl. Ct. 46 (Ct. Cl. 1991).
cites § 832 6×cited by 16 cases
Where it cites § 832
“16 U.S.C. §§ 832 et seq. (1988) 1 and 42 U.”
Later courts cite it for
“thereby waiving the government's traditional immunity, must be explicit and strictly construed.” · 3 citing courts
cites § 832 2×cited by 148 cases
Where it cites § 832
“731 , 16 U. S. C. § 832 et seq. (Project Act), the Bonneville Power Administration (BPA) has marketed low-cost hydroelectric power generated by a series of dams along the Columbia River.”
The case’s holding
An agency administrator's interpretation of its governing statute is entitled to great weight (reasoning that the interpretation is to be given great weight).
Later courts cite it for
“because the exchange program essentially requires bpa to trade its cheap power for more expensive power, it is obviously a money-losing pro- gram for bpa.” · 4 citing courts
4
GREENCity of Burbank v. United States, 273 F.3d 1370 (Fed. Cir. 2001).
cites § 832 3×cited by 15 cases
Where it cites § 832
“See 16 U.S.C. §§ 832 -832m (2000). Whenever the BPA generates sufficient electric energy to satisfy the demand of its primary service area, any electric energy above this amount is defined as surplus.”
Later courts cite it for
“bpa markets, transmits, purchases, exchanges, and sells electric energy in the wholesale market.” · 3 citing courts
5
GREENSpence v. Smyth, 686 P.2d 597 (Wyo. 1984).
cites § 832 6×cited by 7 cases
Where it cites § 832
“16 U.S.C. § 832 et seq. BPA supplies power to, among others, Lower Valley Power & Light Company (LV), which is a rural electric distribution cooperative serving Lincoln, Sublette and Teton Counties in Wyoming and two Idaho counties.”
6
REDCalifornia v. NRG Energy Inc., 391 F.3d 1011 (9th Cir. 2004).
cites § 832 2×cited by 18 cases
Vacated in part by Powerex Corp. v. Reliant Energy Services, Inc. (2007): the U.S. Supreme Court's own opinion in this case ("We therefore vacate in part the judgment of the Ninth Circuit and remand the case with instructions to…
The case’s holding
Federal agencies may remove state claims alleging conspiracy to fix wholesale electricity prices, and section 1447(d) does not bar appellate review of substantive immunity and sovereign-status rulings.
Later courts cite it for
“had jurisdiction to review the underlying merits of the district court's substantive rulings on immunity and sovereign status,” · 3 citing courts
7
GREENPortland Gen. Elec. Co. v. Bonneville Power Admin., 501 F.3d 1009 (9th Cir. 2007).
cites § 832 1×cited by 62 cases
Where it cites § 832
“See Bonneville Project Act, 16 U.S.C. §§ 832 -832m (2000). BPA was tasked with marketing the power generated by federally owned dams on the Columbia River.”
The case’s holding
An agency's general authority to enter into settlement agreements is limited by its specific statutory obligations and requirements governing the subject matter of the settlement.
Later courts cite it for
“as a general rule, we will not review challenges to agency action raised for the first time on appeal.” · 4 citing courts
8
GREENBonneville Power Admin. v. Mirant Corp., 440 F.3d 238 (5th Cir. 2006).
cites § 832 1×cited by 49 cases
Where it cites § 832
“See generally Bonneville Project Act of 1937, 16 U.S.C. § 832 . Originally, BPA marketed the energy produced for the benefit of the public, particularly domestic and rural customers, giving preference and priority to public bodies and cooperatives.”
The case’s holding
The bankruptcy code exception to ipso facto clauses requires an actual inquiry into applicable law rather than a hypothetical one.
Later courts cite it for
“flexibility to the bankruptcy courts.” · 5 citing courts
9
GREENSierra Club v. Donald P. Hodel, 544 F.2d 1036 (9th Cir. 1976).
cites § 832 2×cited by 22 cases
Where it cites § 832
“The Bonneville Power Administration (BPA) is a federal agency created pursuant to the Act of August 20, 1937, 16 U.S.C. § 832 et seq. BPA is under the jurisdiction of the Department of the Interior.”
Later courts cite it for
“remote and conjectural consequences,” · 2 citing courts
10
cites § 832 1×cited by 35 cases
Where it cites § 832
“§ 839c(a) (stating that all power sales conducted pursuant to section 5 of the NWPA are “subject at all times to the preference and priority provisions of the Bonneville Project Act of 1937 ( 16 U.S.C. § 832 and following) and, in particular, sections 4 and 5 thereof [16 U.”
The case’s holding
A petitioner's legally protected interest need not be statutorily created; economic injury from utility price increases passed through customer contracts can establish concrete, particularized Article III standing.
Later courts cite it for
“a petitioner's 'legally protected interest' need not be a statutorily created interest,” · 4 citing courts
11
GREENUnited States v. City of Fulton, 475 U.S. 657 (1986).
cites § 832 1×cited by 56 cases
Where it cites § 832
“731 , codified as amended at 16 U. S. C. §§ 832 -832L The relevant provisions of the two statutes are essentially identical, however, and the Commission and Secretary have treated them interchangeably.”
The case’s holding
Courts apply deferential review to an agency's formulation and implementation of hydroelectric power rates (upholding agency interpretation of the Flood Control Act of 1944).
Later courts cite it for
“protect consumers by ensuring that power is sold 'at the low- est possible rates . . . consistent with sound business princi- ples.” · 4 citing courts
12
GREENPac. Nw. Generating Coop. v. Dept. of Energy, 580 F.3d 792 (9th Cir. 2009).
cites § 832 1×cited by 21 cases
Where it cites § 832
“The Bonneville Project Act of 1937 (“Project Act”), 16 U.S.C. § 832 -832j, cre *799 ated BPA as the authority responsible for the “sale and disposition” of the electric energy generated by the federal hydroelectric projects in the Pacific Northwest.”
The case’s holding
An agency must offer the statutory cost-based rate to direct service industrial customers before selling power at a lower negotiated rate.
Later courts cite it for
“at a rate below what bpa is statutorily required to offer (i.e., the ip rate), and below what it could receive on the open market” · 2 citing courts
13
GREENDalles Irrigation Dist. v. United States, 71 Fed. Cl. 344 (Fed. Cl. 2006).
cites § 832 1×cited by 17 cases
Where it cites § 832
“66, 69 (2005) (citing 16 U.S.C. §§ 832 , 832a(b)). . The method looked both backward and forward to calculate the rates.”
Later courts cite it for
“every claim of which the united states court of federal claims has jurisdiction shall be barred unless the petition thereon is filed within six years after such claim first accrues.” · 3 citing courts
14
GREENNat. Resources Def. Council, Inc. v. Hodel, 435 F. Supp. 590 (D. Or. 1977).
cites § 832 2×cited by 10 cases
Where it cites § 832
“FACTS The Bonneville Power Administration was created in 1937 by the Bonneville Project Act, 16 U.S.C. §§ 832 et seq., to market electricity generated at the Bonneville Dam on the Columbia River and to develop a transmission system for delivery of the electricity generated at…”
15
cites § 832 2×cited by 5 cases
Where it cites § 832
“2007); see 16 U.S.C. §§ 832 -832m. “Congress has since expanded BPA’s mandate to include marketing authority over nearly all the electric power generated by federal facilities in the Pacific Northwest.”
16
GREENDalles Irrigation Dist. v. United States, 82 Fed. Cl. 346 (Fed. Cl. 2008).
cites § 832 1×cited by 10 cases
Where it cites § 832
“731 -33 (codified at 16 U.S.C. §§ 832 , 832a, as amended). BPA is the power marketing agency for Pacific Northwest federal hydroelectric power system, see Federal Columbia River Transmission System Act, Pub.”
Later courts cite it for
“the express terms of the . . . contract are illuminated by the authorizing legislation . . . and, to a lesser extent, by other background legislation.” · 1 citing court
17
GREENCent. Lincoln Peoples' Util. Dist. v. Johnson, 735 F.2d 1101 (9th Cir. 1984).
cites § 832 3×cited by 17 cases
Where it cites § 832
“BPA is the federal marketing agent for power generated by federal dams constructed and operated by the Bureau of Reclamation and the Army Corps of Engineers in the Pacific Northwest, pursuant to the Bonneville Project Act of 1937, 16 U.S.C. §§ 832 et seq. (1982). BPA also…”
The case’s holding
Non-constitutional challenges to wholesale power rates are not reviewable until the Federal Energy Regulatory Commission confirms and approves the rate determinations.
Later courts cite it for
“substantial evidence in the rulemaking record” · 4 citing courts
18
GREENFlorida Power & Light Co. v. United States, 64 Fed. Cl. 37 (Fed. Cl. 2005).
cites § 832 1×cited by 9 cases
Where it cites § 832
“§ 839f(e)(5) provides in relevant part: "Suits to challenge the constitutionality of this chapter, or any action thereunder, final actions *40 and decisions taken pursuant to this chapter by the Administrator or the Council, or the implementation of such final actions, whether…”
19
GREENPac. Nw. Generating Coop. v. Brown, 822 F. Supp. 1479 (D. Or. 1993).
cites § 832 1×cited by 18 cases
Where it cites § 832
“PPC is a preference customer under 16 U.S.C. § 832 , and its member utilities provide approximately 43% of the BPA’s total annual revenues under long term power contracts.”
The case’s holding
Generalized claims of agency failure within the habitat sector are not ripe for adjudication when unparticularized allegations make it impossible to determine the duration of the alleged injury.
Later courts cite it for
“because these plaintiffs have relied upon generalized claims of esa violations by defendants within the habitat sector, it is impossible at this time to tell if the generalized failures are of such a short duration that they may evade review.” · 4 citing courts
20
GREENS. California Edison v. United States, 69 Fed. Cl. 66 (Fed. Cl. 2005).
cites § 832 2×cited by 3 cases
Where it cites § 832
“See 16 U.S.C. § 832 ; Def.’s Mot. at 4. BPA is obligated to give a preference and priority to the power needs of utilities in the Pacific Northwest.”

Show all 56 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195019822015

One bar per 2 years. Tallest: 7 cases in 2006–2007. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
9th Cir.30Fed. Cl.9Ct. Cl.4W.D. Wash.3OLC2D. Or.2SCOTUS25th Cir.1

The 8 courts with the most citing cases, of 11 courts in all.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 56 citing cases (list view) →

Enactment and amendments
(Aug. 20, 1937, ch. 720, § 1, 50 Stat. 731; July 26, 1947, ch. 343, title II, § 205(a), 61 Stat. 501.)
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com