Utah Code § 14-2-1 (2026)
Definitions -- Payment bond required -- Right of action -- Attorney fees
Edition and currency
Other sources
Courts have cited this section in 32 opinions since 1955, 1 of them in the last five years. The most litigated part is subsection (3) (1 case).
Amended by Chapter 330, 2012 General Session
- Where it cites § 14-2-1
- “T11 The private bond statute allows a cause of action against the bond if one is obtained, see Utah Code Ann. § 14-2-1 (4) (2005), and directly against the owner if no bond has been purchased, see id.”
- The case’s holding
- Trust funds have standing to assert mechanics' lien and private bond claims for unpaid fringe benefits, and state statutes of general application are not preempted by ERISA.
- Later courts cite it for
- “this court reviews a trial court's legal conclusions and ultimate grant or denial of summary judgment for correctness, and views the facts and all reasonable inferences drawn therefrom in the light most favorable to the nonmoving party.” · 5 citing courts
- Where it cites § 14-2-1
- “Bailey also challenges the trial court's award of only $1,800 in damages pursuant to Utah Code Ann. §§ 14-2-1 and -2 (1986), [1] for Call's failure to obtain a bond.”
- Later courts cite it for
- “due regard shall be given to the opportunity of the trial court to judge the credibility of the 866 witnesses.” · 2 citing courts
- Where it cites § 14-2-1
- “We turn next to whether the district court erred in allowing recovery to several of the plaintiffs who asserted claims based on Utah's private bond statutes, Utah Code §§ 14-2-1 and 14-2-2, as an alternative theory for recovery of the unpaid amounts due the subcontractors when…”
- The case’s holding
- Equipment rental charges are not lienable under the mechanic's lien statute because leased equipment is not consumed or incorporated into the construction project.
- Later courts cite it for
- “furnishing materials to be used in the construction” · 2 citing courts
- Where it cites § 14-2-1
- “A cause of action was also asserted against Hercules for failure to obtain a payment bond as required by Utah Code Ann. §§ 14-2-1 et seq. (1986) (hereafter, the Payment Bond Statute).”
- Where it cites § 14-2-1
- “THE CONTRACTOR’S BOND STATUTE Graco asserts on its cross-appeal that the contractor’s bond statute, Utah Code Ann. § 14-2-1 (1973) (amended 1985), as it existed at the time this dispute arose, applied to the rental services provided by a subcontractor on an oil well and required…”
- Where it cites § 14-2-1
- “Its complaint alleged, in pertinent part, that Bueh-ner had furnished defendant CS & G Masonry, a subcontractor, materials to be used in constructing a building owned by the remaining defendants, that Buehner had not been paid for the materials, and that because the defendant…”
- The case’s holding
- An appellate court may affirm a trial court decision on any proper ground regardless of the specific reason assigned by the lower court.
- Later courts cite it for
- “may affirm trial court decisions on any proper ground(s), despite the trial court's having assigned another reason for its ruling” · 8 citing courts
- Where it cites § 14-2-1
- “Buchanan, Robert King and DeVerl Byington, finding they had failed to file or obtain a bond as required by Utah Code Ann. § 14-2-1 . On December 27,1984, Kenneth Clarke, a law partner of Mr.”
- Where it cites § 14-2-1
- “, Utah Code Ann. § 14-2-1 (5) (attorney fees in action upon bond in private contract); § 14-2-2(3) (attorney fees in action for failure to obtain bond in private contract); § 34-27-1 (attorney fees in suits for wages); § 38-1-18 (attorney fees in suits enforcing mechanic's…”
- The case’s holding
- A party is entitled to attorney fees only if authorized by statute or contract, and the right to seek such fees is not waived if requested before final judgment.
- Later courts cite it for
- “the general rule in utah is that, subject to certain exceptions, a party is entitled to attorney fees only if authorized by statute or by contract.” · 3 citing courts
- Where it cites § 14-2-1
- “In its motion, Supplier contended that because Developer failed to require Larry Price Construction, the project contractor, to obtain a payment bond under Utah Code Ann. § 14-2-1 to — 5 (1999) (the Payment Bond Statute), Developer was liable for the rent for the equipment plus…”
- Where it cites § 14-2-1
- “These defendants did not obtain from Berg a bond in a sum equal to the contract price to assure payment for materials furnished under the contract as provided in § 14-2-1, U.C.A. 1953. Berg entered into a subcontract with General Plumbing & Heating, Inc.”
- Where it cites § 14-2-1
- “, at the instance of Tel-Tech, wrote a bond to insure payment for materials and labor furnished to CVDA's plant as required by Utah Code Ann. § 14-2-1 (1953). ACP made Industrial Indemnity a defendant to this action and sought to recover upon the bond, together with a reasonable…”
- Later courts cite it for
- “no indication from the record ... that the trial judge failed to adequately deliberate and consider the merits of the case.” · 2 citing courts
- Where it cites § 14-2-1
- “, 1953, §§ 14-2-1 and 1A-2-2. Those statutes provide, respectively, as follows: The owner of any interest in land entering into a contract, involving $2,000 or more, for the construction, addition to, or alteration or repair of, any building, structure or improvement upon land…”
- Later courts cite it for
- “because the counterclaim was unsuccessful, the hours spent in the prosecution thereof are noncompensable.” · 2 citing courts
- Where it cites § 14-2-1
- “97 which Skyline failed to pay over to Koch, because Penney failed to furnish a bond as required by Section 14-2-1, U.C.A.1953. In opposition to the foregoing, defendant Penney contends that in order to reduce the expense of the total contract by $11,000 bonding costs, an…”
- Where it cites § 14-2-1
- “We are called on to construe and apply sections 14-2-1 and 14-2-2. Those sections provide: *152 “14-2-1.”
- Where it cites § 14-2-1
- “The matter was before the Supreme Court under Section 14-2-1, Utah Code Annotated 1953, which makes a land owner personally liable for work done and material furnished when he does not require a bond from the contractor, etc.”
- Later courts cite it for
- “is intended and designed to prevent the owner of land from taking the benefits of improvements placed on his property without paying for the labor and material that went into them.” · 1 citing court
- Where it cites § 14-2-1
- “CROCKETT, Justice: Plaintiff Holbrook Company sued the three named defendants, alleging they were a partnership dba The Exchange, for the value of work and materials furnished in remodeling the building at 39 Exchange Place in Salt Lake City: one count is in quantum meruit and…”
- Later courts cite it for
- “it only takes one sworn statement under oath to dispute the averments on the other side of the controversy and create an issue of fact.” · 4 citing courts
- Where it cites § 14-2-1
- “” The portions of the statutes upon which this action is based are: Section 14-2-1, U.C.A.1953: “The owner of any interest in land entering into a contract, involving $500 or more, for the construction, * * * of, any building, structure or improvement upon land shall, before any…”
- Later courts cite it for
- “there be an annexation to the land, or to some part of the realty; or a fixture appurtenant to it, and this must have been done with the intention of making it a permanent part thereof.” · 2 citing courts
- Where it cites § 14-2-1
- “at 1078 (citing Utah Code Ann. § 14-2-1 (Supp.1985)). In view of the common purpose,of the private contractor’s bond and the mechanic’s lien statutes, we compared their provisions as suggested in an earlier decision, King Brothers, Inc.”
- Where it cites § 14-2-1
- “The other two counts pleaded failure to procure a bond under Section 14-2-1, U.C.A., 1953, and alleged damages under the contract to render services in the amount of the unpaid balance.”
- Where it cites § 14-2-1
- “Utah Code Ann. § 14-2-1 (1987) requires that property owners who contract for construction work exceeding $2,000 shall obtain from the general contractor a payment bond assuring subcontractors and suppliers will be paid even if the general contractor defaults.”
- Later courts cite it for
- “is to preclude landowners from having their lands improved by others, without becoming personally responsible for the reasonable value of materials and labor.” · 2 citing courts
Show all 32 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per 2 years. Tallest: 6 cases in 1988–1989. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
(3)1 case
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: laws through the 2026 General Session (checked Sept. 2026). Syfert holds no earlier or later version of this section.