Topic: the party asserting a breach of contract has the burden of … · Go Syfert
← All topics

Topic #7703

3 canonical passages across 3 cases, quoted by 47 opinions in total. These passages cluster together because the same opinions keep quoting them side by side — they state parts of one doctrine. The anchor passage is from Alan Custom Homes, Inc v. Krol.

#Case FlagCanonical passage Citers
1 Alan Custom Homes, Inc v. Krol Anchor
michctapp · 2003
green “the party asserting a breach of contract has the burden of proving its damages with reasonable certainty, and may recover only those damages that are the direct, natural, and proximate result of the breach.” 36
2 Corl v. Huron Castings, Inc.
mich · 1996
green “the remedy for breach of contract is to place the nonbreaching party in as good a position as if the contract had been fully performed.” 8
3 Home Insurance v. Commercial & Industrial Security Services, Inc.
michctapp · 1974
neutral “uncertainty as to the fact of the amount of damage caused by the breach of contract is fatal.” 3

A red or yellow flag on a member means the underlying case has negative treatment — for those, check the case page before relying on the passage.

← Caselaw search · Hot / Trending / Newly red · Brief Check