Skip to main content
C.F.R.Title 20Chapter VI—Office of Workers' Compensation Programs, Department of LaborSubchapter B—Federal Coal Mine Health and Safety Act of 1969, As AmendedPart 725—Claims for Benefits Under Part C of Title IV of the Federal Mine Safety and Health Act, As AmendedSubpart E—Adjudication of Claims by the District Director

20 C.F.R. § 725.418 (2026)

Proposed decision and order

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 ACTIVE · 6 IN 5Y cited 1987–2026 19citing cases
At a glance

Courts have cited this section in 19 opinions since 1987, 6 of them in the last five years.

(a) Within 20 days after the termination of all informal conference proceedings, or, if no informal conference is held, at the conclusion of the period permitted by § 725.410(b) for the submission of evidence, the district director will issue a proposed decision and order. A proposed decision and order is a document, issued by the district director after the evidentiary development of the claim is completed and all contested issues, if any, are joined, which purports to resolve a claim on the basis of the evidence submitted to or obtained by the district director. A proposed decision and order will be considered a final adjudication of a claim only as provided in § 725.419. A proposed decision and order may be issued by the district director at any time during the adjudication of any claim if:

(1) Issuance is authorized or required by this part;

(2) The district director determines that its issuance will expedite the adjudication of the claim; or

(3) The district director determines that the claimant is a survivor who is entitled to benefits under 30 U.S.C. 932(l). In such cases, the district director may designate the responsible operator in the proposed decision and order regardless of whether the requirements of paragraph (d) of this section have been met. Any operator identified as liable for benefits under this paragraph may challenge the finding of liability by timely requesting revision of the proposed decision and order and specifically indicating disagreement with that finding. See 20 CFR 725.419(a) and (b). In such cases, the district director must allow all parties 30 days within which to submit liability evidence. At the end of this period, the district director must issue a new proposed decision and order.

(b) A proposed decision and order must contain findings of fact and conclusions of law. It must be served on all parties to the claim by certified mail.

(c) The proposed decision and order must contain a notice of the right of any interested party to request a formal hearing before the Office of Administrative Law Judges. If the proposed decision and order is a denial of benefits, and the claimant has previously filed a request for a hearing, the proposed decision and order must notify the claimant that the case will be referred for a hearing pursuant to the previous request unless the claimant notifies the district director that he no longer desires a hearing. If the proposed decision and order is an award of benefits, and the designated responsible operator has previously filed a request for a hearing, the proposed decision and order must notify the operator that the case will be referred for a hearing pursuant to the previous request unless the operator notifies the district director that it no longer desires a hearing.

(d) The proposed decision and order must reflect the district director's final designation of the responsible operator liable for the payment of benefits. Except as provided in paragraph (a)(3) of this section, no operator may be finally designated as the responsible operator unless it has received notification of its potential liability pursuant to § 725.407, and the opportunity to submit additional evidence pursuant to § 725.410. The district director must dismiss, as parties to the claim, all other potentially liable operators that received notification pursuant to § 725.407 and that were not previously dismissed pursuant to § 725.410(a)(3).

[78 FR 59118, Sept. 25, 2013]
The 17 cases that cite 20 C.F.R. § 725.418 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENIsland Creek Coal Co. v. Melyndia Bryan, 937 F.3d 738 (6th Cir. 2019).
cites § 725.418 1×cited by 102 cases
Where it cites § 725.418
“20 C.F.R. § 725.418 (a). From that order, a miner or operator may request a hearing before an administrative law judge.”
The case’s holding
Agency regulations requiring petitions for review to identify specific issues impose an issue exhaustion requirement even in the absence of an express statutory mandate.
Later courts cite it for
“courts have described an implied requirement to raise issues with an agency as a 'judge-made,' 'prudential,' or 'common law' duty to exhaust,” · 116 citing courts
cites § 725.418 2×cited by 6 cases
Where it cites § 725.418
“20 C.F.R. § 725.418 (d). When it issues the PDO, the district director must "dismiss, as parties to the claim, all other potentially liable operators.”
3
GREENMabel Samons v. Nat'l Mines Corp., 25 F.4th 455 (6th Cir. 2022).
cites § 725.418 1×cited by 14 cases
Where it cites § 725.418
“§ 919 (d); 20 C.F.R. §§ 725.418 , 725.451. A losing party may then appeal that judge’s decision to the Benefits Review Board.”
Later courts cite it for
“encapsulates a simple idea: courts generally decline to redecide issues that they have already decided.” · 5 citing courts
4
GREENApogee Coal Co. v. OWCP, 112 F.4th 343 (6th Cir. 2024).
cites § 725.418 1×cited by 3 cases
Where it cites § 725.418
“A carrier’s due process rights in the BLBA context are protected in part by 20 C.F.R. § 725.418 , which states that “no operator may be finally designated as the responsible operator unless it has received notification of its potential liability pursuant to § 725.407, and the opportunity to submit additional evidence pursuant to § 725.410.””
5
GREENSaginaw Mining Co. v. Mazzulli, 818 F.2d 1278 (6th Cir. 1987).
cites § 725.418 2×cited by 34 cases
Where it cites § 725.418
“We can only conclude that paragraph (a) of the regulation was intended to apply in those relatively rare circumstances where the proposed decision and order, see 20 C.F.R. § 725.418 , of the deputy commissioner was not opposed by either party within 30 days and therefore became…”
The case’s holding
A black lung claimant seeking modification of an administrative law judge's decision must file the request with a deputy commissioner, not with the judge, and the initial modification stages involve no hearing.
Later courts cite it for
“a claimant for benefits under the blba must file with a deputy commissioner, rather than an alj, a request for modification of an alj decision.” · 2 citing courts
6
GREENIsland Fork Constr. v. Jimmy Bowling, 872 F.3d 754 (6th Cir. 2017).
cites § 725.418 1×cited by 2 cases
Where it cites § 725.418
“The District Director, a Department of Labor employee responsible for processing claims, 20 C.F.R. § 725.418 (d), issued a Notice of Claim that-proposed designating Island Fork as the responsible operator.”
7
GREENCornett v. Benham Coal, Inc., 227 F.3d 569 (6th Cir. 2000).
cites § 725.418 1×cited by 34 cases
Where it cites § 725.418
“Benham Coal claims that because the Director is an "adjudicator” under the BLBA but only a "mediator” (without the ability to bind the parties) under the LHWCA, the Director cannot now contradict the position of the district director. See Benham’s Motion to Strike at 10, 11, 16.”
The case’s holding
A black lung claimant need not prove coal dust was the only cause of his respiratory impairment, and a physician may rely on non-qualifying pulmonary test results in reaching a reasonable opinion.
Later courts cite it for
“this legal definition of pneumoconiosis . . . encompasses a wider range of afflictions than does the more restrictive medical definition of pneumoconiosis.” · 3 citing courts
cites § 725.418 1×cited by 5 cases
Where it cites § 725.418
“20 C.F.R. § 725.418 . The decision of the Deputy Commissioner becomes final if there is no objection within thirty days.”
9
GREENElmer Robbins v. Cyprus Cumberland Coal Co. Dir., 146 F.3d 425 (6th Cir. 1998).
cites § 725.418 1×cited by 4 cases
Where it cites § 725.418
“The district director then issues a proposed decision- on the claim, see 20 C.F.R. § 725.418 , which the parties can then accept, request revision, or reject and request a hearing before an ALJ.”
10
NO FLAGRockwood Cas. Ins. v. Dir., OWCP, No. 18-9520 (10th Cir. Mar. 5, 2019).
cites § 725.418 2×
Where it cites § 725.418
“20 C.F.R. § 725.418 (d). When it issues the PDO, the district director must “dismiss, as parties to the claim, all other potentially liable operators.”
11
NO FLAGHobet Mining, Inc. v. DOWCP, No. 23-2157 (4th Cir. Oct. 1, 2025).
cites § 725.418 2×
Where it cites § 725.418
“20 C.F.R. § 725.418 . The proposed decision and order must “reflect the district director’s final designation of the responsible operator liable for the payment of benefits.”
12
NO FLAGSextet Mining Corp. v. Mary Whitfield, 604 F. App'x 442 (6th Cir. 2015).
cites § 725.418 2×unpublished
Where it cites § 725.418
“418(d) provided in relevant part: The proposed decision and order must reflect the district director’s final designation of the responsible operator hable for the payment of benefits.”
13
NO FLAGScalia v. Chevron Mining, Inc., No. 4:20-cv-00010 (W.D. Ky. June 21, 2021).
cites § 725.418 1×
Where it cites § 725.418
“) (citing 20 C.F.R. §§ 725.418 (a), 725.419(a), 725.502(a)(2)).”
14
NO FLAGThree H Coal Co. v. DOWCP, No. 23-1486 (4th Cir. Jan. 21, 2025).
cites § 725.418 1×unpublished
Where it cites § 725.418
“” 20 C.F.R. § 725.418 (d). The “responsible operator” designated by the district director may request a revision of the proposed decision or request a hearing before an ALJ.”
15
NO FLAGHunter, No. 4:25-cv-00020 (W.D. Ky. Feb. 19, 2026).
cites § 725.418 1×
Where it cites § 725.418
“401 ; 20 C.F.R. § 725.418 (a). The proposed decision and order is “considered a final adjudication of a claim” only if no party requests a revision or a hearing within 30 days.”
16
NO FLAGSprague v. Dir., Off. of Workers' Comp. Programs, 310 F. App'x 890 (7th Cir. 2009).
cites § 725.418 1×unpublished
Where it cites § 725.418
“The ALJ considered a plethora of medical documents: ten readings of three X-rays done by six different doctors; five readings by five doctors of a single CT scan; and doctors’ reports from both parties interpreting the X-rays, CT scan, medical history, occupational history,…”
17
NO FLAGTolliver v. DOWCP, No. 97-2141 (4th Cir. Jan. 26, 1999).
cites § 725.418 1×unpublished
Where it cites § 725.418
“416, issue a proposed decision and order deciding the claim, see 20 C.F.R. §§ 725.418 , or issue an initial determination (which he did), see 20 C.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198720062026

One bar per year. Tallest: 3 cases in 2009. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
6th Cir.84th Cir.37th Cir.310th Cir.2W.D. Ky.211th Cir.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.