Viking Communities Corp. v. Peeler Const. Co., 367 So. 2d 737 (Fla. 4th DCA 1979). · Go Syfert
Viking Communities Corp. v. Peeler Const. Co., 367 So. 2d 737 (Fla. 4th DCA 1979). Cases Citing This Book View Copy Cite
“since a contract is essential to any mechanic's lien, we look first to the enforceability of the basic contractual obligation”
17 citation events (5 in the last 25 years) across 5 distinct courts.
Strongest positive: Premier Finishes, Inc. v. Maggirias (fladistctapp, 2013-11-15) · Strongest negative: Grant v. Wester (fladistctapp, 1996-09-30)
Top citers, strongest first. 9 distinct citers. How cited ↗
discussed Cited "but see" Grant v. Wester (2×) also: Cited as authority (rule)
Fla. Dist. Ct. App. · 1996 · signal: but see · quote attribution · 1 verbatim quote · confidence high
damages are generally determined by the amount in excess of the contract price.
discussed Cited as authority (verbatim quote) Premier Finishes, Inc. v. Maggirias
Fla. Dist. Ct. App. · 2013 · quote attribution · 1 verbatim quote · confidence high
a contract is essential to any eontractor's lien.
discussed Cited as authority (verbatim quote) Cds & Assocs. v. 1711 Donna Road Assocs.
Fla. Dist. Ct. App. · 1999 · quote attribution · 1 verbatim quote · confidence high
since a contract is essential to any mechanic's lien, we look first to the enforceability of the basic contractual obligation
cited Cited as authority (rule) Niehaus v. Big Ben's Tree Service, Inc.
Fla. Dist. Ct. App. · 2008 · confidence medium
Co., 367 So.2d 737, 739 (Fla. 4th DCA 1979) (stating "a contract is essential to any mechanic's lien").
cited Cited as authority (rule) Hasse Contracting Co. v. KBK Financial, Inc.
N.M. Ct. App. · 1998 · confidence medium
Co., 367 So.2d 737, 739 (Fla.Dist.Ct.App.1979) (technical breach without damage is consistent with substantial performance). 27.
discussed Cited as authority (rule) Stunkel v. Gazebo Landscaping Design, Inc.
Fla. · 1995 · confidence medium
Co., 367 So.2d 737, 739 (Fla. 4th DCA 1979); § 713.06(1), Fla. Stat. (1991) ("[A] subcontractor ... has a lien on the real property improved for any money that is owed to him for labor, services, or materials furnished in accordance with his contract." (emphasis added)).
discussed Cited "see" Michnal v. Palm Coast Development, Inc.
Fla. Dist. Ct. App. · 2003 · signal: see · confidence high
See Viking Communications Corp. v. Peeler Const. Co., 367 So.2d 737 (Fla. 4th DCA 1979)(since a contract is essential to any mechanic's [contractor's] lien, the court must look first to the enforceability of the basic contractual obligation); § 713.02(7), Fla. Stat. (1997).
discussed Cited "see, e.g." Braverman v. Van Bower, Inc.
Fla. Dist. Ct. App. · 1991 · signal: see also · confidence low
See also Viking Communities Corp. v. Peeler Construction Co., 367 So.2d 737 (Fla. 4th DCA 1979) (basic contractual obligation must be fulfilled before contractor entitled to mechanic's lien; compliance with both contract and mechanic's lien statute necessary for recovery on mechanic's lien).
cited Cited "see, e.g." Atkinson & Mullen Travel, Inc. v. SunCoast Airlines, Inc. (In Re SunCoast Airlines, Inc.)
Bankr. S.D. Florida · 1989 · signal: see, e.g. · confidence medium
See, e.g., Viking Communities Corp. v. Peeler Construction Co., 367 So.2d 737, 739 (Fla. 4th DCA 1979) (doctrine of substantial performance is recognized in Florida).
Retrieving the full opinion text from the archive…
VIKING COMMUNITIES CORP., Now Known As Communities Financial Corporation, Appellant,
v.
PEELER CONSTRUCTION CO. and Star Construction Co. of Ft. Pierce, Inc., Appellees.
77-1569.
District Court of Appeal of Florida, Fourth District.
Feb 21, 1979.
367 So. 2d 737
Beranek.
Cited by 14 opinions  |  Published

[*738] Leonard Jaffe, Miami, and Gerald Mager, of Abrams, Anton, Robbins, Resnick, Schneider & Mager, Hollywood, for appellant.

Devitt J. Adams, Fort Pierce, for appellee Star Construction Co. of Ft. Pierce, Inc.

BERANEK, Judge.

Viking Communities, plaintiff below, here appeals a final judgment entered in favor of Star Construction on a counterclaim in a third-party action.

Star Construction contracted with Viking to perform certain excavations on Viking's construction project. Payment was based on a unit price for the volume of material excavated. The contract estimated the volume of excavation and established a dollar amount which was not to be exceeded. The contract also provided for progress payments from Viking to Star. Work commenced and problems arose. The subsequent events are disputed, but several facts are apparent. The estimated volume of excavation was too low. Star fell behind schedule in completing the project and Viking withheld a progress payment. Star eventually ceased work altogether and Viking completed the work through another subcontractor. Star filed a complaint seeking recovery on two counts; foreclosure of a mechanic's lien and quantum meruit.

The case was tried by the Court resulting in a final judgment in favor of Star for the full amount claimed but denying the mechanic's lien. The trial court found that Star had breached the contract in failing to perform within the prescribed time but that no damages to Viking had occurred. The Court denied foreclosure of the mechanic's lien based upon the equitable theory of "unclean hands" as applied against Star. The Court entered judgment for the full amount claimed by Star under the breached contract but did so on the theory of quantum meruit. Viking here appeals that judgment and Star cross appeals denial of the mechanic's lien.

[*739] Since a contract is essential to any mechanic's lien, we look first to the enforceability of the basic contractual obligation. 22 Fla.Jur., Mechanic's Lien § 19. The doctrine of substantial performance prevails in this State and a contractor who substantially performs and is in good faith is entitled to enforce the contract even if performance has been less than complete. Ocean Ridge Development Corp. v. Quality Plastering, Inc., 247 So.2d 72 (Fla. 4th DCA 1971). Where a contractor breaches a construction contract, the damages are generally determined by the amount in excess of the contract price which the owner reasonably expends to complete the project. Assuming good faith substantial performance, recovery under the contract should be diminished by this amount. Melnick v. Reynolds Metals, 230 So.2d 490 (Fla. 4th DCA 1970), Bryan v. Owsley Lumber Co., 201 So.2d 246 (Fla. 1st DCA 1967). Where a contractor complies with all provisions of Chapter 713, Florida Statutes, and has substantially performed the contract, he is entitled to a mechanic's lien. See Poranski v. Millings, 82 So.2d 675 (Fla. 1955), and American Motor Inns of Florida, Inc. v. Bell Electric, 260 So.2d 276 (Fla. 4th DCA 1972).

Here, the trial court found a breach by the contractor, Star, but no damages to the owner. Nevertheless the mechanic's lien was denied because the court characterized Star as having "unclean hands." The judgment makes no mention of substantial performance but the record indicates Star did substantially perform and a technical breach without damage is certainly consistent with substantial performance. A technical breach of contract alone may or may not result in unclean hands but under the circumstances here presented it should not have been the basis for denying the mechanic's lien. The Court erred in failing to grant to Star a mechanic's lien.

The final judgment granting full damages under the breached contract on a quantum meruit theory is the subject of Viking's appeal. If the contractor is entitled to prevail on the mechanic's lien aspect of the case, he is not also entitled to a full contract price recovery on the quantum meruit theory. We are, therefore, convinced that the Court misconceived the effect of the evidence and the judgment based on quantum meruit is also reversed. The matter is remanded for further proceedings consistent with this opinion.

REVERSED AND REMANDED.

DOWNEY, C.J., and LETTS, J., concur.