Fortec Constructors v. The United States, 760 F.2d 1288 (Fed. Cir. 1985). · Go Syfert
Fortec Constructors v. The United States, 760 F.2d 1288 (Fed. Cir. 1985). Cases Citing This Book View Copy Cite
322 citation events (98 in the last 25 years) across 15 distinct courts.
Strongest positive: Korte Construction Company (asbca, 2024-05-06)
Treatment trajectory · 1986 → 2026 · click a year to view as-of
1986 2006 2026
Top citers, strongest first. 50 distinct citers. How cited ↗
discussed Cited as authority (verbatim quote) Korte Construction Company
A.S.B.C.A. · 2024 · quote attribution · 1 verbatim quote · confidence high
the existence of a patent ambiguity in the contract raises the duty of inquiry, regardless of the reasonableness of the contractor's interpretation
examined Cited as authority (verbatim quote) Swain County v. United States (2×) also: Cited as authority (rule)
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence high
this court must be guided by the well accepted and basic principle that an interpretation 8 that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (verbatim quote) Hendrickson v. United States (2×) also: Cited as authority (rule)
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence high
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts óf the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (verbatim quote) Langkamp v. United States (2×) also: Cited as authority (rule)
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence high
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (verbatim quote) Per Aarsleff A/S v. United States (3×) also: Cited "see, e.g."
Fed. Cl. · 2015 · signal: see also · quote attribution · 1 verbatim quote · confidence high
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (verbatim quote) John H. Dalton, Secretary of the Navy v. Cessna Aircraft Company (4×) also: Cited as authority (rule)
Fed. Cir. · 1996 · quote attribution · 2 verbatim quotes · confidence high
the existence of a patent ambiguity in the contract raises the duty of inquiry, regardless of the reasonableness of the contractor's interpretation.
examined Cited as authority (quoted) Vandesande v. United States (2×) also: Cited as authority (rule)
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence low
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (quoted) 27-35 Jackson Ave LLC v. United States
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence low
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
examined Cited as authority (quoted) Vandesande v. United States (2×) also: Cited as authority (rule)
Fed. Cl. · 2017 · quote attribution · 1 verbatim quote · confidence low
this court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.
cited Cited as authority (rule) American Tech Solutions, LLC v. United States
Fed. Cl. · 2025 · confidence medium
Cir. 1994); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
discussed Cited as authority (rule) Land O'lakes, Inc. v. United States
Fed. Cl. · 2022 · confidence medium
Cir. 1997) (citing Gould, Inc., 935 F.2d at 1274 ); McAbee Constr., Inc., 97 F.3d at 1434 , reh'g denied and en banc suggestion declined (1996); Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.
discussed Cited as authority (rule) Joan C. Pulkkila v. James M. Pulkkila
Wis. · 2020 · confidence medium
The canon applies to contracts like MSAs: "This court must be Dissenting from the court of appeals decision, then-Judge 6 Brian Hagedorn recognized that "the MSA's mandatory lien language does not make much sense if other remedies could be pursued instead of a lien." Pulkkila v. Pulkkila, No. 2018AP712-FT, unpublished slip op., ¶15 (Wis. Ct. App. Feb. 27, 2019) (Hagedorn, J., dissenting). 26 No. 2018AP712-FT.rgb guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of th…
cited Cited as authority (rule) CKY, Inc.
A.S.B.C.A. · 2020 · confidence medium
Cir. 1997) (quoting Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
discussed Cited as authority (rule) Omran Holding Group, Inc. v. United States
Fed. Cl. · 2017 · confidence medium
A contract term is ambiguous when “it is susceptible of two different yet reasonable interpretations, each of which is 'consistent with the contract language and with the other provisions of the contract.” Lockheed Martin, 108 F.3d at 322 . “[A]n interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.” Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.
discussed Cited as authority (rule) Premier Office Complex of Parma, LLC v. United States
Fed. Cl. · 2017 · confidence medium
This type of ambiguity in a government contract “raises the duty of inquiry, regardless of the reasonableness of the contractor’s interpretation.” Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
cited Cited as authority (rule) Access Personnel Services, Inc.
A.S.B.C.A. · 2017 · confidence medium
Cir. 2002); Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.
discussed Cited as authority (rule) Veterans Evaluation Services, Inc. v. United States
unknown court · 2017 · confidence medium
Cir. 1997) (“The existence of a patent ambiguity in a government contract ‘raises the duty of inquiry, regardless of the reasonableness of the contractor’s interpretation,’ [and] requires the contractor to inquire ... as to the trae meaning of the contract before submitting a bid.”) (quoting Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
cited Cited as authority (rule) James G. Davis Construction Corporation
A.S.B.C.A. · 2014 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
discussed Cited as authority (rule) Ensley, Inc. v. United States
Fed. Cl. · 2014 · confidence medium
PL's Resp. at 7 (citing Lockheed Martin IR Imaging Sys., Inc. v. West, 108 F.3d 319, 322 (Fed.Cir. 1997), McAbee Constr., Inc. v. United States, 97 F.3d 1431, 1434 (Fed.Cir. 1996), and Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir. 1985)).
cited Cited as authority (rule) System Planning Corp. v. United States
Fed. Cl. · 2012 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.
discussed Cited as authority (rule) Marquardt Co. v. United States (2×) also: Cited "see, e.g."
Fed. Cl. · 2011 · confidence medium
Fortec Constructors v. United States (Fortec), 760 F.2d 1288, 1292 (Fed.
discussed Cited as authority (rule) Villanueva v. Barcroft
N.D. Ohio · 2011 · confidence medium
Cl. 745, 784 (Fed.Cl.2000) (“When interpreting the language of a contract, a court must give a reasonable meaning to all parts of the contract and not render portions of the contract meaningless.”) (citing Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985)). b.
cited Cited as authority (rule) Allied Technology Group, Inc. v. United States
Fed. Cl. · 2010 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985).
cited Cited as authority (rule) Public Service Co. v. United States
Fed. Cl. · 2009 · confidence medium
“Contract interpretation is a matter of law_” Neal & Co. v. United States, 945 F.2d 385, 390 (Fed.Cir.1991) (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985)).
discussed Cited as authority (rule) Prati v. United States
Fed. Cl. · 2008 · confidence medium
Construing these sub-paragraphs in a coherent and consistent manner, see, e.g., Helvering v. Stockholms Enskilda Bank, 293 U.S. 84, 88-89 , 55 S.Ct. 50 , 79 L.Ed. 211 (1934); Fortec Constr. v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985), the court rightly maintained that the meaning of "such items” can refer only to those items actually settled or agreed upon.
cited Cited as authority (rule) Forest Glen Properties, LLC v. United States
Fed. Cl. · 2007 · confidence medium
Sanchez & Son, Inc. v. United States, 6 F.3d 1539, 1544 (Fed.Cir. 1993); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) HWA, Inc. v. United States
Fed. Cl. · 2007 · confidence medium
HWA also argues, though, that any interpretation of the solicitation criteria other than one that makes the socioeconomic factor the most important “necessarily renders the solicitation's] stated evaluation weighting formula meaningless,” and that this is not allowed under applicable Federal Circuit case law that upholds the principle that “an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless.” Pl.’s Mot. 27 (quoting Fottec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.19…
cited Cited as authority (rule) Precision Pine & Timber, Inc. v. United States
Fed. Cl. · 2007 · confidence medium
Textron Defense Sys. v. Widnall, 143 F.3d 1465, 1468 (Fed.Cir.1998); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) Alliant Techsystems Inc. v. United States
Fed. Cl. · 2007 · confidence medium
Bank v. United States, 245 F.3d 1342, 1346 (Fed.Cir.2001); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) Precision Pine & Timber, Inc. v. United States
Fed. Cl. · 2006 · confidence medium
Textron Defense Sys. v. Widnall, 143 F.3d 1465, 1468 (Fed.Cir.1998); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) Travelers Casualty & Surety of America v. United States
Fed. Cl. · 2006 · confidence medium
Bank v. United States, 245 F.3d 1342, 1346 (Fed.Cir.2001); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) Rotech Healthcare Inc. v. United States
Fed. Cl. · 2006 · confidence medium
Further, the court must “consider the solicitation as a whole, interpreting it in a manner that harmonizes and gives reasonable meaning to all of its provisions.” Banknote, 365 F.3d at 1353; Overstreet Electric, 59 Fed.Cl. at 112 (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985)).
discussed Cited as authority (rule) PHT Supply Corp. v. United States
Fed. Cl. · 2006 · confidence medium
Further, the court must “consider the solicitation as a whole, interpreting it in a manner that harmonizes and gives reasonable meaning to all of its provisions.” Banknote, 365 F.3d at 1353; Overstreet Elec., 59 Fed.Cl. at 112 (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985)).
cited Cited as authority (rule) Modeer v. United States
Fed. Cl. · 2005 · confidence medium
“Contract interpretation is a matter of law ....” Neal & Co. v. United States, 945 F.2d 385, 390 (Fed.Cir.1991) (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985)).
cited Cited as authority (rule) Frazier v. United States
Fed. Cl. · 2005 · confidence medium
Bank v. United States, 245 F.3d 1342, 1346 (Fed.Cir.2001); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985), and begins with the plain language of the agreement.
cited Cited as authority (rule) Tecom, Inc. v. United States
Fed. Cl. · 2005 · confidence medium
Bank v. United States, 245 F.3d 1342, 1346 (Fed.Cir.2001); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985); C.
discussed Cited as authority (rule) International Data Products Corp. v. United States
Fed. Cl. · 2005 · confidence medium
Kent v. Principi, 389 F.3d 1380, 1384 (Fed.Cir.2004) (citing Lane v. Principi, 339 F.3d 1331, 1339 (Fed.Cir.2003) (statutory interpretation is a question of law)); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985) (interpretation of a government contract is a question of law).
discussed Cited as authority (rule) Blackstone Consulting, Inc. v. United States
Fed. Cl. · 2005 · confidence medium
Cir.1997) (holding that where "contract ambiguities ... are judged so 'patent and glaring’ that it is unreasonable for a contractor not to discover and inquire about them" a contractor has a duty to inquire); Fortee Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985) ("The existence of a patent ambiguity in a contract raises the duty of inquiry, regardless of the reasonableness of the contractor's interpretation."). .
cited Cited as authority (rule) Jacobs Engineering Group, Inc. v. United States
Fed. Cl. · 2005 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) CW Government Travel, Inc. v. United States
Fed. Cl. · 2004 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985).
cited Cited as authority (rule) Precision Pine & Timber, Inc. v. United States
Fed. Cl. · 2004 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) CW Government Travel, Inc. v. United States
Fed. Cl. · 2004 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
cited Cited as authority (rule) Dismas Charities, Inc. v. United States
Fed. Cl. · 2004 · confidence medium
Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) Nvt Technologies, Inc. v. United States (2×)
Fed. Cir. · 2004 · confidence medium
Wickham Contracting Co. v. Fischer, 12 F.3d 1574, 1577 (Fed.Cir.1994); Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) Marketing & Management Information, Inc. v. United States
Fed. Cl. · 2003 · confidence medium
Where a patent ambiguity exists, it raises the “duty of inquiry regardless of the reasonableness of the contractor’s interpretation.” Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) Bechtel National, Inc. v. Roche
Fed. Cir. · 2003 · confidence medium
This court prefers to give “a reasonable meaning to all parts of the contract” rather than to “leave[ ] portions of the contract meaningless.” Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985).
cited Cited as authority (rule) Roy Case Construction Co. v. White
Fed. Cir. · 2002 · confidence medium
Cir.1998) (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.
discussed Cited as authority (rule) Olympia Properties, L.L.C. v. United States
Fed. Cl. · 2002 · confidence medium
See Lockheed Martin IR Imaging Sys., Inc. v. West, 108 F.3d at 322 (citing Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed.Cir.1991)); McAbee Constr., Inc. v. United States, 97 F.3d 1431, 1434 (Fed.Cir.), reh’g denied and en banc suggestion declined (1996); Fortec Constructors v. United States, 760 F.2d 1288, 1292 (Fed.Cir.1985) (citing United States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed.Cir.1983)); GPA-I LP v. United States, 46 Fed.Cl. 762, 769 (2000).
cited Cited as authority (rule) Sweet v. United States
Fed. Cl. · 2002 · confidence medium
For tec Constructors v. United States, 760 F.2d 1288, 1291 (Fed.Cir.1985).
discussed Cited as authority (rule) Metcalf Construction Co. v. United States (2×)
Fed. Cl. · 2002 · confidence medium
Reply at 4 (citing Fortec Constructors v. United States, 760 F.2d 1288, 1291-92 (Fed.Cir.1985)).
Retrieving the full opinion text from the archive…
FORTEC CONSTRUCTORS, Appellant,
v.
the UNITED STATES, Appellee
Appeal 84-1579.
Court of Appeals for the Federal Circuit.
Apr 30, 1985.
760 F.2d 1288
1985 U.S. App. LEXIS 14776
David W. Mockbee, Jones, Mockbee & Bass, Jackson, Miss., argued for appellant., George M. Beasley, III, Commercial Litigation Branch, Dept, of Justice, Washington, D.C., argued for appellee. With him on brief were Richard K. Willard, Acting Asst. Atty. Gen., David M. Cohen, Director, Sandra P. Spooner and Stephen J. McHale, Washington, D.C., David A. Tomlinson, Engineer Trial Atty., Dept, of the Army, of counsel,
Bissell, Bennett, Smith, Bis-Sell.
Cited by 231 opinions  |  Published
1 passages pin-cited by 3 cases
Pinpoint authority: #22,429 of 633,719
Citer courts: Federal Claims (3)
BISSELL, Circuit Judge.

Fortec Constructors appeals from the decision of the Armed Services Board of Contract Appeals (ASBCA or Board) sustaining a contracting officer’s final decision denying Fortec’s claim for an equitable adjustment. We affirm.

BACKGROUND

Fortec was awarded contract DACA6381-C-0041 by the United States Army Engineer District of Fort Worth on December 31, 1980. This contract called for the construction of a 32,000 square foot one-story medical clinic at Fort Sam Houston, San Antonio, Texas. The clinic structure rests on a concrete distribution rib slab foundation consisting of reinforced concrete beams, exterior grade beams and interior grade beams (distribution ribs).

The project commenced on February 3, 1981. After preparing the foundation area and placing the reinforcing steel (rebar) in the exterior grade and interior distribution rib trenches, Fortec began tying the rebar on June 3, 1981, for the first 25-foot concrete pour and continued to tie the rebar and pour the slab in 25-foot pours with the eighth and final pour on July 29, 1981. On July 28, 1981, a dispute arose about the manner of installing the rebar. Fortec had installed the rebar in the interior distribution ribs so that it butted up against the exterior grade beams without extending or lapping into them. The Corps area engineer informed Fortec that the rebar was improperly placed because the interior distribution rib rebar did not overlap the exterior grade beam rebar. On September 10, 1981, the Corps directed Fortec to immediately remove the concrete at the junction of the interior distribution ribs and exterior grade beams to determine if the rebar placement complied with contract documents. Thirty-five junctions were demol[*1290] ished; only two junctions met lapping requirements.

DRAWINGS AND SPECIFICATIONS

The contract drawings, sheet S-3, sequence number 55, sections 01 and 02 and details 19 and 20, see Fortec Constructors, 84-2 BCA ¶ 17,328, at 86,345 (1984), schematically illustrate the rebar in the distribution ribs intersecting the rebar in the exterior grade beams. Drawing sheet S-6, sequence number 58, provides two instructions of importance under the “Reinforcing Steel Notes,” specifically notes 3 and 4, which provide:

3. DETAILING OF CONCRETE REINFORCEMENT AND ACCESSORIES SHALL BE IN ACCORDANCE WITH ACI 315-74.
4. REINFORCING BARS MAY BE SPLICED ONLY AS SHOWN ON THE DRAWINGS EXCEPT THAT REINFORCING DESIGNATED AS ‘CONTINUOUS’ MAY BE CONTACT LAP SPLICED 36 BARS DIAMETERS. LAP SPLICES OF CONTINUOUS REINFORCING SHALL BE MADE OVER SUPPORTS FOR BOTTOM BARS AND FOR INTERMEDIATE BARS AND AT MIDSPAN FOR TOP BARS. AT EXTERIOR SUPPORTS, TOP BARS SHALL BE HOOKED DOWN AND BOTTOM BARS SHALL BE HOOKED UP.

Fortec, 84-2 BCA at 86,346.

American Concrete Institute (ACI) Standard 315-74, incorporated by reference in note 3, provides the details of concrete reinforcement. The schematic illustrating the reinforcement in ACI 315-74 is shown at figure 2-9 entitled “Typical Wall Details.” Two alternative structures are shown for double curtain reinforcement.

Typical intersection details for double curtain reinforcement

The detail on the left shows the rebar from the interior distribution rib stopping at the exterior grade beam. The detail on the right depicts the rebar from the interior distribution rib running into the exterior beam. No instruction was provided which would have enabled Fortec to select either of these two alternative reinforcement schemes.

ASBCA DECISION

The Board’s decision reported at 84-2 BCA H 17,328 found that the drawings, notes, and details were not a model of clarity. It held that a finding of ambiguity was not necessary in order to go outside the four corners of the contract to resolve the dispute as to whether Fortec complied with the terms of the contract. It found:

[Tjhat a concrete distribution rib type of foundation is commonly found in the area to provide ‘continuous reinforcement’ in foundations which have a tendency to deflect due to either the absorption or loss of moisture at the perimeter of buildings (findings 7, 8). Experts from both sides agreed without exception that in distribution rib type of founda[*1291] tions seen and found in the area, the interior rebars always lap or tie into exterior support (finding 9). We conclude from the foregoing that the Government has established a prima facie case that in the locality of the construction, there is a trade practice when installing a concrete distribution rib type of foundation to lap interior rebars from the distribution ribs into the exterior grade beams.

Fortee, 84-2 BCA at 86,351 (emphasis in original).

It also found that the hook configuration at the ends of the interior rebar should have indicated to an experienced contractor that the interior rebar was to be lapped over the exterior grade beam rebar. Fortee had installed the rebar in accordance with ACI 315-74 figure 2-9 details showing the interior distribution rib rebar stopping at the exterior grade beam. The Board held that Fortee was not entitled to an equitable adjustment for having been required to demolish and reconstruct the thirty-three noncomplying intersections between the interi- or and exterior grade beams.

OPINION

This court has jurisdiction under 28 U.S.C. § 1295(a)(10) (1982) to hear an appeal pursuant to 41 U.S.C. § 607(g)(1)(A) (1982). Our standard of review is governed by 41 U.S.C. § 609(b) (1982):

[A]ny contract provision, regulation, or rules of law to the contrary, the decision of the agency board on any question of law shall not be final or conclusive, but the decision on any question of fact shall be final and conclusive and shall not be set aside unless the decision is fraudulent, or arbitrary, or capricious, or so grossly erroneous as to necessarily imply bad faith, or if such decision is not supported by substantial evidence.

The interpretation of a contract is a question of law to be decided by the court and an administrative interpretation of a contract is not binding on the court. B.D. Click Company v. United States, 614 F.2d 748, 752, 222 Ct.Cl. 290 (1980). However, a Board’s interpretation of a contract will be given careful consideration and accorded great respect. George Hyman Construction Co. v. United States, 564 F.2d 939, 944, 215 Ct.Cl. 70 (1977).

Fortee contends that the Board’s reliance on trade practice to change the meaning of an unambiguous contract was contrary to law. It argues that the contract provisions permitted the butting of the interior distribution rib rebar to the exterior grade beams. The Board in its decision declined to hold that the contract was ambiguous despite resorting to evidence of trade practice to interpret the terms of the agreement. We hold as a matter of law that the contract was patently ambiguous. Our review of the record before this court shows that no direction was provided as to which of the two rebar schemes shown in ACI 315-74, figure 2-9, “Typical intersection details for double curtain reinforcement,” was required.

The existence of a patent ambiguity in the contract raises the duty of inquiry, regardless of the reasonableness of the contractor’s interpretation. Newsom v. United States, 676 F.2d 647, 649-50, 230 Ct.Cl. 301 (1982); FFR Building Specialties v. United States, 229 Ct.Cl. 538, 539-40 (1981). Fortee did not seek clarification of the rebar requirements; it instead exercised its own judgment. In deciding the correct meaning of a contract containing a patent ambiguity it is proper to consider the trade standards and practices of the relevant business community. Alfred A. Altimont, Inc. v. United States, 579 F.2d 622, 625, 217 Ct.Cl. 628 (1978). A contractor is charged with the knowledge of these standards. Id. The Board’s trade practice findings are not arbitrary, capricious, or grossly erroneous. Furthermore, Fortec’s own expert testified that rebar from the interior grade beam is normally tied into the exterior grade beam. Fortec, 84-2 BCA at 86,343.

Fortee further contends that the presence of a Corps of Engineers Quality Assurance representative at the project site charged with the responsibility of seeing that the plans and specifications were complied with constituted an acceptance of the alleged defects because of the representa[*1292] tive’s failure to notify Fortec of the defects. Clause 10 of the contract’s general provisions provides in part:

(a) All work ... shall be subject to inspection and test by the Government at all reasonable times and at all places prior to acceptance. Any such inspection and test is for the sole benefit of the Government and shall not relieve the Contractor of the responsibility of providing quality control measures to assure that the work strictly complies with the contract requirements. No inspection or test by the Government,shall be construed as constituting or implying acceptance. [Emphasis added.]

To agree with Fortec’s contention would render clause 10 meaningless. This court must be guided by the well accepted and basic principle that an interpretation that gives a reasonable meaning to all parts of the contract will be preferred to one that leaves portions of the contract meaningless. United States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed.Cir.1983). Therefore, Fortec’s contention is rejected for being inconsistent with contract clause 10. The Corps quality assurance inspections did not constitute an acceptance of the work.

Fortec’s claim for equitable adjustment was properly denied.

AFFIRMED.