33 C.F.R. § 322.4 (2026)
Activities not requiring permits
Edition and currency
Other sources
Courts have cited this section in 11 opinions since 1979. The most litigated part is subsection (a) (1 case).
(a) Activities that were commenced or completed shoreward of established Federal harbor lines before May 27, 1970 (see 33 CFR 320.4(o)) do not require section 10 permits; however, if those activities involve the discharge of dredged or fill material into waters of the United States after October 18, 1972, a section 404 permit is required. (See 33 CFR part 323.)
(b) Pursuant to section 154 of the Water Resource Development Act of 1976 (Pub. L. 94-587), Department of the Army permits are not required under section 10 to construct wharves and piers in any waterbody, located entirely within one state, that is a navigable water of the United States solely on the basis of its historical use to transport interstate commerce.
- The case’s holding
- A party that illegally alters a wetland must restore it to its pre-violation condition regardless of regulatory ambiguity.
- Later courts cite it for
- “an equitable relationship to the degree and kind of wrong it is intended to remedy.” · 2 citing courts
- Later courts cite it for
- “clear water is not within the definition of a pollutant under the cwa.” · 2 citing courts
- Where it cites § 322.4
- “This regulation was first promulgated in 1977 as 33 C.F.R. § 322.4 (g), and the Corps indicated that this provision only applied to Section 10 of the Rivers and Harbor Act, although it acknowledged that certain activities might be "regulated under other authorities of the…”
- Where it cites § 322.4
- “18-20) In particular, 33 C.F.R. § 322.4 (a) provides: “[activities that were commenced or completed shoreward of established Fed *1047 eral harbor lines before May 27, 1970 .”
- Later courts cite it for
- “where congress expressly provides for government enforcement of a statute by way of injunction, and the government has satisfied the statutory conditions of the statute, irreparable harm to the public is presumed.” · 2 citing courts
- Where it cites § 322.4
- “33 CFR §§ 322.4 (1979) exempts certain structures and work from the requirements of 33 USC § 403 , including: "(c) The repair, rehabilitation, or replacement of any previously authorized, currently serviceable, structure or of any currently serviceable structure constructed…”
- Where it cites § 322.4
- “17 Rising Waters? — Dam Not “Currently Serviceable” The second point which DeFeliee challenges concerns the Corps’ interpretation of the phrase “currently serviceable” in the regulation as it applies to an exemption to the permit requirements found in 33 CFR § 322.4 (c). (See…”
- Later courts cite it for
- “tidal waters by their very nature form a continuous water body with interstate waterways.” · 2 citing courts
- Where it cites § 322.4
- “Instead, Gulf has contended that its failure to comply with the statute is excused by the grandfather clause contained in 33 C.F.R. § 322.4 (g) (1981). The regulation provides that no section 10 permit is required for “structures or work completed before 18 December 1968 or in…”
- Where it cites § 322.4
- “Because Congress affirmatively authorized the Tracy Pumping Plant, a Corps permit is not required for its present operational level. Therefore, we do not reach the question of whether an environmental impact statement is required for the Tracy Plant.”
- Later courts cite it for
- “the legislative history of the rivers and harbors act of 1899 does not reflect a congressional intent either to afford a private remedy or to deny one.” · 1 citing court
- Where it cites § 322.4
- “See 33 C.F.R. § 322.4 (g) (1977). No such exemption existed under the Clean Water Act.”
- Where it cites § 322.4
- “33 CFR §§ 322.4 (c) and (g) provide: "The following structures or work are hereby permitted for purposes of Section 10 and do not require separate Department of the Army permits: *807 "(c) The repair, rehabilitation, or replacement of any previously authorized, currently…”
- Where it cites § 322.4
- “33 CFR 322.4(a), I have determined that the South Island ferry is a permitted structure since the cable was installed prior to 18 December 1968 and there was no evidence available to the Corps to indicate it posed a hazard to navigation before the recent accidents.”
- The case’s holding
- The United States has no general duty to ensure navigable waters are safe or to provide warning devices under the Suits in Admiralty Act.
- Later courts cite it for
- “laurit-zen has been sufficiently undermined by subsequent supreme court decisions that it should no longer be followed.” · 2 citing courts
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 1979. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 9 courts in all.
(a)1 case
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.