Connecticut General Statutes homeSearch Connecticut
Conn. Gen. Stat.Title 49 — Mortgages and LiensChapter 847 — Liens

Conn. Gen. Stat. § 49-36 (2025)

Liens limited; apportionment; payments to original contractor

Edition and currency
laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026) cited 1960–2021 21citing cases
At a glance

Courts have cited this section in 21 opinions since 1960, 1 of them in the last five years.

(a) No mechanic's lien may attach to any building or its appurtenances, or to the land on which the same stands, or any lot, or any plot of land, in favor of any person, to a greater amount in the whole than the price which the owner agreed to pay for the building and its appurtenances or the development of any such lot, or the development of any such plot of land.

(b) When there are several claimants and the amount of their united claims exceeds that price, the claimants, other than the original contractor, shall be first paid in full, if the amount of that price is sufficient for that purpose; but, if not, it shall be apportioned among the claimants having the liens, other than the original contractor, in proportion to the amount of the debts due them respectively; and the court having jurisdiction thereof, on application of any person interested, may direct the manner in which the claims shall be paid.

(c) In determining the amount to which any lien or liens may attach upon any land or building, or lot or plot of land, the owner of the land or building or lot or plot of land shall be allowed whatever payments he has made, in good faith, to the original contractor or contractors, before receiving notice of the lien or liens. No payments made in advance of the time stipulated in the original contract may be considered as made in good faith, unless notice of intention to make the payment has been given in writing to each person known to have furnished materials or rendered services at least five days before the payment is made.

(1949 Rev., S. 7220; P.A. 74-310, S. 4; P.A. 79-602, S. 92.)

History: P.A. 74-310 applied provisions with respect to lots, plots of land and development of such land; P.A. 79-602 divided section into Subsecs., substituted “may” for “shall” and “the”, etc. for “such” and made other slight changes in wording.

Owner is to be allowed for bona fide payments to original contractor before notice, though made in advance. 27 C. 578. Owner cannot waive defect in notice of intent so as to make lien valid as against others claiming liens. 42 C. 541. Owner not allowed for payments made after notice to him by subcontractor, although he had, before such notice, verbally guaranteed contractor's debts, in performance of which guaranty he made such payments. 43 C. 14. Limitation of amount of liens generally. 73 C. 519. Effect of abandonment of work by contractor. Id., 452; 82 C. 244; 87 C. 686; 89 C. 254. Effect of alteration in original contract; of payment made before notice of lien; of payment made in advance of time agreed on. 74 C. 493; 81 C. 502; 89 C. 254; 131 C. 643. Payment of subcontractor by contractor will not defeat lien of one to whom former has sublet part of work. 76 C. 107. Subcontractor has no greater rights than his principal. 81 C. 632; 82 C. 244; 96 C. 225. Effect of direct payments by mortgagee holding advance payment mortgage to contractor, at request of mortgagor. 82 C. 244. Effect of contract providing for payments as work progresses under which weekly payments are made and contract price is fully paid. 84 C. 487. What constitutes “notice” of subcontractor's lien. Id.; 91 C. 712. What constitutes knowledge in provision for advance payments. 89 C. 262. Right of subcontractors where one gives notice, owner thereafter makes payments on contract, and then others give notice. 92 C. 482. Duty of owner as to withholding payments after receiving notice. Id., 485. No priority between subcontractors under same original contractor. 99 C. 343; 108 C. 243. Cited. 109 C. 364; Id., 554; 113 C. 10; 115 C. 199. Finding of fraud between owner and principal contractor. 111 C. 132. Priority of materialmen over contractor not removed by assumption by owner to pay them. 116 C. 277. In action to foreclose lien of subcontractor, original contractor a necessary party. 118 C. 614. Payments made in advance of the time when they are due under the contract and without notice to the lienor are ineffective as to him in reducing the amount due on the contract. 143 C. 146. Cited. 147 C. 351; 168 C. 371; 169 C. 76; 180 C. 501; 181 C. 592; 182 C. 568. Challenge by general contractor to constitutionality of mechanic's lien statutes discussed. 185 C. 583.

Cited. 27 CA 199; 39 CA 122. Defendant, despite having paid general contractor the original contract price in full, still owed general contractor for “extras” and therefore a lienable fund existed and subcontractor's lien was not invalid. 136 CA 184. When the general contractor is not in default, unless there were payments made in bad faith, the lienable fund is the amount still owed by the property owner to the general contractor at the time the property owner receives the notice of the lien pursuant to Sec. 49-34, regardless of whether it continues to make payments to the nondefaulted general contractor. 196 CA 430.

Cited. 15 CS 360; 23 CS 380.

Cited. 2 Conn. Cir. Ct. 620. Only payments made to original contractor in good faith before notice of subcontractor's lien are allowed owner. 6 Conn. Cir. Ct. 512.

The 20 cases that cite Conn. Gen. Stat. § 49-36 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENRene Dry Wall Co. v. Strawberry Hill Assocs., 438 A.2d 774 (Conn. 1980).
cites § 49-36 11×cited by 51 cases
Where it cites § 49-36
“General Statutes § 49-36. Although § 49-36 does require pro rata allocation of proceeds among unpaid subcontractors, that provision does not come into play until it is determined that there are net proceeds available for distribution, taking into account the diminutions from the…”
The case’s holding
An owner is protected from a subcontractor's mechanic's lien if the owner acts in good faith and reasonably when making progress payments to a defaulting general contractor.
Later courts cite it for
“if . . . a general contractor receives progress payments that are not turned over to those who have done the work represented by the progress payments, and ultimately defaults entirely, the owner making such payments and completing such a job is protected as long as the owner acts in good faith and reasonably. . . .” · 3 citing courts
2
GREENW. G. Glenney Co. v. Bianco, 604 A.2d 1345 (Conn. App. Ct. 1992).
cites § 49-36 10×cited by 40 cases
Where it cites § 49-36
“The defendants claim that the trial court improperly (1) rendered judgment without joining the general contractor as a party to this action, (2) found that the defendants prevented the general contractor from completing performance, and (3) refused to apportion the debt owed by…”
The case’s holding
Nonjoinder of a party is not a jurisdictional issue because statutory provisions explicitly provide that the failure to join a party does not defeat an action.
Later courts cite it for
“a party is defined as indispensable if its interest in the case is such that a final judgment cannot be entered without either affecting the party's interest or leaving the case in such condition that its final resolution may be inconsistent with equity and good conscience.” · 4 citing courts
3
GREENSeaman v. Climate Control Corp., 436 A.2d 271 (Conn. 1980).
cites § 49-36 6×cited by 71 cases
Where it cites § 49-36
“General Statutes § 49-36. These general observations help to clarify what is not at issue in this case.”
The case’s holding
A second-tier subcontractor is subrogated to the rights of the general contractor rather than the first-tier subcontractor for purposes of establishing a mechanic's lien.
Later courts cite it for
“had the legislature wished to limit, . . the rights of second tier subcontractors to obtain liens against the owner, it would have been easy enough for the supreme court of nevada 14 (0) 1947a legislature to link the subcontractor's claim to the person with whom such subcontractor shall have contracted.” · 4 citing courts
4
GREENFCM Grp., Inc. v. Miller, 17 A.3d 40 (Conn. 2011).
cites § 49-36 4×cited by 39 cases
Where it cites § 49-36
“18 General Statutes § 49-36 provides in relevant part: “(a) No mechanic’s lien may attach to any building or its appurtenances, or to the land on which the same stands, or any lot, or any plot of land, in favor of any person, to a greater amount in the whole than the price which…”
The case’s holding
A person who is not a party to a contract is not bound by its terms and cannot be held liable for its breach.
Later courts cite it for
“parties to a contract cannot thereby impose any liability on one who, under its terms, is a stranger to the contract, and, in any event, in order to bind a third person contractually, an expression of assent by such person is necessary. ... in other words, a person who is not a party to a contract (i.e., is not named in the contract and has not executed it) is not bound by its terms.” · 2 citing courts
5
GREENJohnson v. De Toledo, 763 A.2d 28 (Conn. App. Ct. 2000).
cites § 49-36 7×cited by 16 cases
Where it cites § 49-36
“In response, the homeowners assert that because Basli was to construct the patio and the retaining wall under the original contract, they are entitled to a $17,500 credit.”
6
GREENGen. Elec. Supply Co. v. S. New England Tel. Co., 441 A.2d 581 (Conn. 1981).
cites § 49-36 5×cited by 27 cases
Where it cites § 49-36
“They maintain instead that the general contractor is adversely affected by the imposition of a lien on the property of the owner, because the result of notice of a lien is invariably to freeze assets to which the general contractor would otherwise be entitled. Section 49-36 of…”
7
GREENThompson & Peck, Inc. v. Div. Drywall, Inc., 696 A.2d 326 (Conn. 1997).
cites § 49-36 3×cited by 70 cases
Where it cites § 49-36
“ng and appurtenances or lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then on the plot of land and the claim takes precedence over any other encumbrance originating after the…”
The case’s holding
Unpaid insurance premiums are not lienable as materials or services under the mechanic's lien statute because they do not physically enhance the property.
8
GREENSpearhead Constr. Corp. v. Bianco, 665 A.2d 86 (Conn. App. Ct. 1995).
cites § 49-36 4×cited by 30 cases
Where it cites § 49-36
“” The defendants sought to reduce the Glenney claim by application of the apportionment statute, General Statutes § 49-36 (b). 2 Their *127 argument was that the sum of Glenney’s claim for $55,185.”
The case’s holding
The allowance of prejudgment interest depends on whether the detention of money is wrongful under the circumstances and is determined in view of the demands of justice.
Later courts cite it for
“under 37-3a , an allowance of prejudgment interest turns on whether the detention of the money is or is not wrongful under the circumstances. . . and that the ultimate determination is one to be made in view of the demands of justice rather than through the application of any arbitrary rule.” · 4 citing courts
9
GREENGill v. Diorio, 720 A.2d 526 (Conn. App. Ct. 1998).
cites § 49-36 6×cited by 13 cases
Where it cites § 49-36
“The owners and tenant claimed, therefore, that Aqua did not have standing to allege its claims pursuant to General Statutes § 49-36 (c). 6 Aqua opposed the motion *144 to dismiss arguing that the trial court, as a court of general jurisdiction, had subject matter jurisdiction…”
10
GREENPROBUILD EAST, LLC v. Poffenberger, 45 A.3d 654 (Conn. App. Ct. 2012).
cites § 49-36 5×cited by 6 cases
Where it cites § 49-36
“” 5 General Statutes § 49-36 provides in relevant part: “(a) No mechanic’s lien may attach to any building or its appurtenances, or to the land on which the same stands, or any lot, or any plot of land, in favor of any person, to *192 a greater amount in the whole than the price…”
11
GREENRusso Roofing, Inc. v. Rottman, 863 A.2d 713 (Conn. App. Ct. 2005).
cites § 49-36 2×cited by 8 cases
Where it cites § 49-36
“2 General Statutes § 49-36 (a) provides: “No mechanic’s lien may attach to any building or its appurtenances, or to the land on which the same stands, or any lot, or any plot of land, in favor of any person, to a greater amount in the whole than the price which the owner agreed…”
12
GREENO & G Indus., Inc. v. Am. Home Assurance Co., 254 A.3d 955 (Conn. App. Ct. 2021).
cites § 49-36 2×cited by 3 cases
Where it cites § 49-36
“’’ With respect to the seventh special defense, which alleged that the plaintiff’s substitute bond claim was barred because neither the owner, Morganti, nor the defendant owed the plaintiff for the materials supplied, the court found for the plaintiff because the parties had…”
13
GREENNew England Sav. Bank v. Meadow Lakes Realty Co., 706 A.2d 465 (Conn. 1998).
cites § 49-36 1×cited by 18 cases
Where it cites § 49-36
“” General Statutes § 49-33 (b) provides: “The claim is a lien on the land, building and appurtenances or lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then on the plot of land and the…”
14
GREENAstoria Fed. Mortg. Corp. v. Genesis Ltd. P'ship, 143 A.3d 1121 (Conn. App. Ct. 2016).
cites § 49-36 1×cited by 4 cases
Where it cites § 49-36
“"(b) The claim is a lien on the land, building and appurtenances or lot or in the event that the materials were furnished or services were rendered in the site development or subdivision of any plot of land, then on the plot of land and the claim takes precedence over any other…”
15
GREENBrook Hollow Assocs. v. J. E. Greene, Inc., 389 F. Supp. 1322 (D. Conn. 1975).
cites § 49-36 2×cited by 8 cases
Where it cites § 49-36
““§ 49-36. Liens limited; apportionment; payments to original contractor No such lien shall attach to any building or its appurtenances, or to the land on which the same stands, in favor of any person, to a greater amount in the whole than the price which the owner agreed to pay…”
16
GREENChris Constr. Co. v. May Centers, Inc., 581 A.2d 748 (Conn. App. Ct. 1990).
cites § 49-36 1×cited by 6 cases
Where it cites § 49-36
“e than the amount by which the contract price between the owner and the person through whom the subcontractor claims exceeds the reasonable cost, either estimated or actual, as the case may be, of satisfactory completion of the contract plus any damages resulting from such…”
17
GREENBiller v. Harris, 161 A.2d 187 (Conn. 1960).
cites § 49-36 1×cited by 14 cases
Where it cites § 49-36
“The notice of intent to file a lien is, however, required only of a subcontractor; if he complies with the terms of the statutes 49-34, 49-35, 49-36), he “acquires the right to find in the property owner’s hands such an amount, within the limits of what is due to the original…”
18
NEUTRALProf'l Elec. Contractors of Connecticut, Inc. v. Stamford Hosp., 230 A.3d 773 (Conn. App. Ct. 2020).
cites § 49-36 16×cited by 0 cases
Where it cites § 49-36
“No mechanic’s lien may exceed the price which the owner has agreed to pay for the building being erected or improved, and the owner is entitled, furthermore, to credit for payments made in good faith to the original contractor before receipt of notice of such a lien or liens.…”
cites § 49-36 1×cited by 99 cases
Vacated: 37 citing opinions add another limit ("vacated (caution)").
Where it cites § 49-36
“Section 49-36 provides that the amount of the lien on any building or its appurtenances cannot exceed the amount agreed upon in the contract for such building and its appurtenances, and § 49-37 provides that the owner of the real estate subject to the lien may apply to the…”
The case’s holding
Mechanic's lien statutes violate due process if they allow for the perfection of a lien without providing notice or a meaningful opportunity to be heard.
Later courts cite it for
“it is fundamental that property cannot be taken without procedural due process as guaranteed by the fourteenth amendment to the constitution of the united states and article first, 10, of the constitution of connecticut.” · 3 citing courts
cites § 49-36 2×cited by 0 cases
Where it cites § 49-36
“General Statutes § 49-36.”). The rulings in jurisdictions providing mechanic’s lien protection apparently similar to that of Connecticut are uniform that where the subcontractor had the opportunity to obtain a mechanic’s lien, but failed to do so, the subcontractor was not…”

Show all 21 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
196019902021

One bar per year. Tallest: 2 cases in 1975. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Conn. App. Ct.11Conn.8Bankr. D. Conn.1D. Conn.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 21 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Connecticut General Statutes Home  |  Search Connecticut  |  Search cases for this section  |  syfert.com