Florida Administrative Code

Fla. Admin. Code R. 40B-3.201 (2026)

Permit Fees

✓ current as of September 2026
Find cases: SyfertCases citing this section FLRulesflrules.org (official) ChapterChapter 40B-3 CornellLII Search CasesGoogle Scholar

(1) Failure of an applicant to pay the fees established herein is grounds for the denial of the permit application.

(2) Any portion of the fees enumerated in this rule in excess of $100 shall be waived for well permits issued on behalf of a municipality or county government qualified under Section 218.075, F.S.

(3) Fees for permits to construct or repair wells required by this Chapter shall be as listed in Table 1 below, and shall apply to each well constructed or repaired. No fee shall be required for a permit to abandon or modify a well; or for wells constructed or repaired for the District.

(4) Water well contractor licensing fees are enumerated in Rule 62-531.340, F.A.C.

TABLE 1 SCHEDULE OF WATER WELL PERMIT FEES

Public Water Supply Wells not in a Chapter 62-524, F.A.C., Delineated Area Construction

$275

Repair

$140

Transfer of an application to another licensed water well contractor

$10

Chapter 62-524, F.A.C., Delineated Area Wells

Domestic Self-Supply well construction

$275

Repair

$140

Public Supply Wells

$500

Transfer of an application to another licensed water well contractor

$10

All other wells

Construction

$40

Repair

$10

Transfer of an application to another licensed water well contractor

$10

Rulemaking Authority 373.044, 373.109, 373.113, 373.171, 373.323(8), 373.324(4), 373.337 FS. Law Implemented 218.075, 373.109, 373.308, 373.309, 373.313 FS. History–New 4-15-81, Amended 9-15-81, 1-31-83, 7-1-85, 6-16-88, 6-22-99, 10-18-22, Technical Change 11-14-25, 4-9-26.

Effective: 4/9/2026.