Massachusetts General Laws

Mass. Gen. Laws ch. 30, § 39G (2026)

Completion of public works; semi-final and final estimates; payments; extra work; disputed items

✓ current as of July 2026
Find cases: SyfertCases citing this section MAmalegislature.gov (official) JustiaChapter on Justia CornellLII Search CasesGoogle Scholar

Section 39G. Upon substantial completion of the work required by a contract with the commonwealth, or any agency or political subdivision thereof, for the construction, reconstruction, alteration, remodeling, repair or improvement of public ways, including bridges and other highway structures, sewers and, water mains, airports and other public works, the contractor shall present in writing to the awarding authority its certification that the work has been substantially completed. Within twenty-one days thereafter, the awarding authority shall present to the contractor either a written declaration that the work has been substantially completed or an itemized list of incomplete or unsatisfactory work items required by the contract sufficient to demonstrate that the work has not been substantially completed. The awarding authority may include with such list a notice setting forth a reasonable time, which shall not in any event be prior to the contract completion date, within which the contractor must achieve substantial completion of the work. In the event that the awarding authority fails to respond, by presentation of a written declaration or itemized list as aforesaid, to the contractor's certification within the twenty-one day period, the contractor's certification shall take effect as the awarding authority's declaration that the work has been substantially completed.

Within sixty-five days after the effective date of a declaration of a substantial completion, the awarding authority shall prepare and forthwith send to the contractor for acceptance a substantial completion estimate for the quantity and price of the work done and all but one per cent retainage, if held by the awarding authority, on that work, including the quantity, price and all but one per cent retainage, if held by the awarding authority, for the undisputed part of each work item and extra work item in dispute but excluding the disputed part thereof, less the estimated cost of completing all incomplete and unsatisfactory work items and less the total periodic payments made to date for the work. The awarding authority also shall deduct from the substantial completion estimate an amount equal to the sum of all demands for direct payment filed by subcontractors and not yet paid to subcontractors or deposited in joint accounts pursuant to section thirty-nine F, but no contract subject to said section thirty-nine F shall contain any other provision authorizing the awarding authority to deduct any amount by virtue of claims asserted against the contract by subcontractors, material suppliers or others.

If the awarding authority fails to prepare and send to the contractor any substantial completion estimate required by this section on or before the date herein above set forth, the awarding authority shall pay to the contractor interest on the amount which would have been due to the contractor pursuant to such substantial completion estimate at the rate of three percentage points above the rediscount rate then charged by the Federal Reserve Bank of Boston from such date to the date on which the awarding authority sends that substantial completion estimate to the contractor for acceptance or to the date of payment therefor, whichever occurs first. The awarding authority shall include the amount of such interest in the substantial completion estimate.

Within fifteen days after the effective date of the declaration of substantial completion, the awarding authority shall send to the contractor by certified mail, return receipt requested, a complete list of all incomplete or unsatisfactory work items, and, unless delayed by causes beyond his control, the contractor shall complete all such work items within forty-five days after the receipt of such list or before the then contract completion date, whichever is later. If the contractor fails to complete such work within such time, the awarding authority may, subsequent to seven days' written notice to the contractor by certified mail, return receipt requested, terminate the contract and complete the incomplete or unsatisfactory work items and charge the cost of same to the contractor.

Within thirty days after receipt by the awarding authority of a notice from the contractor stating that all of the work required by the contract has been completed, the awarding authority shall prepare and forthwith send to the contractor for acceptance a final estimate for the quantity and price of the work done and all retainage, if held by the awarding authority, on that work less all payments made to date, unless the awarding authority's inspection shows that work items required by the contract remain incomplete or unsatisfactory, or that documentation required by the contract has not been completed. If the awarding authority fails to prepare and send to the contractor the final estimate within thirty days after receipt of notice of completion, the awarding authority shall pay to the contractor interest on the amount which would have been due to the contractor pursuant to such final estimate at the rate hereinabove provided from the thirtieth day after such completion until the date on which the awarding authority sends the final estimate to the contractor for acceptance or the date of payment therefor, whichever occurs first, provided that the awarding authority's inspection shows that no work items required by the contract remain incomplete or unsatisfactory. Interest shall not be paid hereunder on amounts for which interest is required to be paid in connection with the substantial completion estimate as hereinabove provided. The awarding authority shall include the amount of the interest required to be paid hereunder in the final estimate.

The awarding authority shall pay the amount due pursuant to any substantial completion or final estimate within thirty-five days after receipt of written acceptance for such estimate from the contractor and shall pay interest on the amount due pursuant to such estimate at the rate hereinabove provided from that thirty-fifth day to the date of payment. Within 15 days, 30 days in the case of the commonwealth, after receipt from the contractor, at the place designated by the awarding authority, if such place is so designated, of a periodic estimate requesting payment of the amount due for the preceding periodic estimate period, the awarding authority shall make a periodic payment to the contractor for the work performed during the preceding periodic estimate period and for the materials not incorporated in the work but delivered and suitably stored at the site, or at some location agreed upon in writing, to which the contractor has title or to which a subcontractor has title and has authorized the contractor to transfer title to the awarding authority, upon certification by the contractor that he is the lawful owner and that the materials are free from all encumbrances. The awarding authority shall include with each such payment interest on the amount due pursuant to such periodic estimate at the rate herein above provided from the due date. In the case of periodic payments, the contracting authority may deduct from its payment a retention based on its estimate of the fair value of its claims against the contractor, a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, and a retention to secure satisfactory performance of the contractual work not exceeding five per cent of the approved amount of any periodic payment, and the same right to retention shall apply to bonded subcontractors entitled to direct payment under section thirty-nine F of chapter thirty; provided, that a five per cent value of all items that are planted in the ground shall be deducted from the periodic payments until final acceptance.

No periodic, substantial completion or final estimate or acceptance or payment thereof shall bar a contractor from reserving all rights to dispute the quantity and amount of, or the failure of the awarding authority to approve a quantity and amount of, all or part of any work item or extra work item.

Substantial completion, for the purposes of this section, shall mean either that the work required by the contract has been completed except for work having a contract price of less than one per cent of the then adjusted total contract price, or substantially all of the work has been completed and opened to public use except for minor incomplete or unsatisfactory work items that do not materially impair the usefulness of the work required by the contract.

Notes of Decisions
Cited in 17 cases (1 in the last 5 years), 1963–2023 · leading case: Reynolds Bros. v. Town of Norwood, 414 Mass. 295 (Mass. 1993).
Sort: Relevance Newest Treatment
Reynolds Bros. v. Town of Norwood, 414 Mass. 295 (Mass. 1993). · cites it 7× “Reynolds claims that, under G. L. c. 30, § 39G (1990 ed.), it is entitled to interest on amounts paid to it by the defendant town, Norwood, for construction work at Norwood Municipal Airport.”
D. Federico Co. v. New Bedford Redevelopment Auth., 399 N.E.2d 1103 (Mass. App. Ct. 1980). · cites it 5× “While “Estimate #18” provides only for payment on account of the balance of the line item for preparation of site and miscellaneous work, thus having a characteristic of a closing requisition, the estimate fails significantly to conform to G. L. c. 30, § 39G, in that it…”
Massachusetts High. Dep't v. Perini Corp., 947 N.E.2d 62 (Mass. App. Ct. 2011). · cites it 5× “The judge confirmed orders 11A and 16 to the extent they required CA/T to pay postaward interest, but imposed a different interest rate, the rate established by G. L. c. 30, § 39G, and ruled that the award of compound interest was contrary to the controlling statute.”
J. A. Sullivan Corp. v. Commonwealth, 494 N.E.2d 374 (Mass. 1986). “See G. L. c. 30, § 39G (1984 ed.). In relying on Fay, Spofford & Thorndike, Inc.”
Acme Plastering Co. v. Boston Hous. Auth., 490 N.E.2d 445 (Mass. App. Ct. 1986). · cites it 2× “at 145 (construing substantially similar provisions of G. L. c. 30, § 39G). The provision for final payment, less retentions, upon substantial completion of the work and “possession for occupancy” by the awarding authority strikes an obvious equitable balance.”
D. Federico Co. v. New Bedford Redevelopment Auth. (In re D. Federico Co.), 25 B.R. 822 (D. Mass. 1982). · cites it 2× “FD1 gave the varying interest rates under Mass.Gen.Laws ch. 30 § 39G. On May 17,1982, well after the Court had made its findings in the liability trial, which defined and limited the issues to be heard in the damages trial; after several pre-trial hearings and after the trial on…”
Long Island Painting Corp. v. Beacon Constr. Co., 188 N.E.2d 857 (Mass. 1963). · cites it 2× “on its appeal, is this: G. L. c. 30, § 39G, requires that M. D. C.”
Petricca Constr. Co. v. Commonwealth, 432 N.E.2d 545 (Mass. App. Ct. 1982). “There was no authorization either by statute (G. L. c. 30, § 39G, as amended by St. 1976, c.”
Indus. Eng'g & Metal Fabricators, Inc. v. Fontaine Bros., 319 N.E.2d 726 (Mass. App. Ct. 1974). “306, 323 [1969], decided under G. L. c. 30, § 39G), there is nothing in the present record to suggest that either Industrial’s claim against Fontaine or Fontaine’s claim against the city was ever submitted as or as a part of either of the types of “periodic estimate”…”
D. Federico Co. v. New Bedford Redevelopment Auth. (In Re D. Federico Co.), 16 B.R. 282 (Bankr. D. Mass. 1981). “Similarly, the Massachusetts Appeals Court reached the same conclusion: [A] public agency cannot thwart the policy of G.L. c. 30, § 39G, by the simple expedient of failing to obtain, or withholding, a stamp of approval.”
J.C. Higgins Co. v. Bond Bros., 791 N.E.2d 367 (Mass. App. Ct. 2003). “The amounts Bond claimed were disputed under its contract with MCCA, and we have held in an analogous context that disputed amounts under a public works contract accrue interest under G.”
Reynolds Bros. v. Town of Norwood, 584 N.E.2d 1142 (Mass. App. Ct. 1992). · cites it 9× “However, the plaintiff brought this action in the Superior Court claiming that it is due an additional sum of money for interest because of the town’s failure to make timely payments under the contract pursuant to G. L. c. 30, § 39G. The defendants denied liability on the…”
Show all 17 citing cases →
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.