Michigan Compiled Laws
Mich. Comp. Laws § 460.563 (2026)
Transmission as essential service; act as controlling.
✓ current as of July 2026
Find cases:
SyfertCases citing this section
MI-LEGlegislature.mi.gov
JustiaChapter on Justia
CornellLII Search
CasesGoogle Scholar
ELECTRIC TRANSMISSION LINE CERTIFICATION ACT
Act 30 of 1995
460.563 Transmission as essential service; act as controlling.
Sec. 3.
(1) Transmission of electricity is an essential service.
(2) This act shall control in any conflict between this act and any other law of this state.
History: 1995, Act 30, Imd. Eff. May 17, 1995 ;-- Am. 2004, Act 198, Imd. Eff. July 12, 2004
Notes of Decisions
Cited in 2
cases, 2012–2014 · leading case: In Re Application of Michigan Elec. Transmission Co, 309 Mich. App. 1 (Mich. Ct. App. 2014).
In Re Application of Michigan Elec. Transmission Co, 309 Mich. App. 1 (Mich. Ct. App. 2014). “The PSC found that under MCL 460.563 and MCL 460.570, the grant of a CPCN to METC preempted Oshtemo’s ordinance.”
In re Int'l Transmission Co., 298 Mich. App. 338 (Mich. Ct. App. 2012). “” MCL 460.563(2). If the language of MCL 460.”
Mich. Comp. Laws § 460.563(2): 2 cases
In Re Application of Michigan Elec. Transmission Co, 309 Mich. App. 1 (Mich. Ct. App. 2014). “The PSC found that under MCL 460.563 and MCL 460.570, the grant of a CPCN to METC preempted Oshtemo’s ordinance.”
In re Int'l Transmission Co., 298 Mich. App. 338 (Mich. Ct. App. 2012). “” MCL 460.563(2). If the language of MCL 460.”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.