NRS
40.647 Claimant required to allow inspection of and reasonable
opportunity to repair defect; claimant or claimant’s expert required to be
present at inspection; effect of noncompliance.
1. After notice of a constructional defect
is given pursuant to NRS 40.645, before
a claimant may commence an action or amend a complaint to add a cause of action
for a constructional defect against a contractor, subcontractor, supplier or
design professional, the claimant must:
(a) Allow an inspection of the alleged
constructional defect to be conducted pursuant to NRS 40.6462;
(b) Be present or have a representative of the
claimant present at an inspection conducted pursuant to NRS 40.6462 and, to the extent possible,
reasonably identify the proximate locations of the defects, damages or injuries
specified in the notice; and
(c) Allow the contractor, subcontractor, supplier
or design professional a reasonable opportunity to repair the constructional
defect or cause the defect to be repaired if an election to repair is made
pursuant to NRS 40.6472.
2. If a claimant commences an action
without complying with subsection 1 or NRS
40.645, the court shall:
(a) Dismiss the action without prejudice and
compel the claimant to comply with those provisions before filing another
action; or
(b) If dismissal of the action would prevent the
claimant from filing another action because the action would be procedurally
barred by the statute of limitations or statute of repose, the court shall stay
the proceeding pending compliance with those provisions by the claimant.
(Added to NRS by 2003,
2039; A 2015,
13; 2019,
2260)
Notes of Decisions
D.R. Horton, Inc. v. Eighth Jud. Dist. Court, 168 P.3d 731 (Nev. 2007).
· cites it 3× “Horton further argues that the inadequacy of First Light’s notice frustrates its opportunity to repair under NRS 40.647. In its answer, First Light contends that its notice is sufficient and that D.”
Waterfall Homeowners Ass'n v. Viega, Inc., 283 F.R.D. 571 (D. Nev. 2012).
· cites it 7× “647(1), a court must dismiss the case without prejudice and compel the plaintiff to file such a notice before filing another action. See Nev.Rev.”
Cincinnati Ins. v. AMSCO Windows, 921 F. Supp. 2d 1226 (D. Utah 2013).
“See Nev. Rev. Stat § 40.647 ("If a claimant commences an action without” meeting Chapter 40's procedural requirements, the "the court shall dismiss the action.”
Byrne Vs. Sunridge Builders, Inc., 2020 NV 69 (Nev. 2020).
· cites it 6× “See NRS 40.647(1). If a claimant fails to comply with the prelitigation process before filing his or her lawsuit, the court must dismiss the action without prejudice.”
Barrett v. Eighth Jud. Dist. Ct., 2014 NV 65 (Nev. 2014).
· cites it 10× “646; NRS 40.647. A claimant "may" give notice to a subcontractor, supplier, or design professional, if the contractor is unavailable, but the claimant is not required to do so.”
— Nev. Rev. Stat. § 40.647(1) — 5 cases
D.R. Horton, Inc. v. Eighth Jud. Dist. Court, 168 P.3d 731 (Nev. 2007).
“Horton further argues that the inadequacy of First Light’s notice frustrates its opportunity to repair under NRS 40.647. In its answer, First Light contends that its notice is sufficient and that D.”
Waterfall Homeowners Ass'n v. Viega, Inc., 283 F.R.D. 571 (D. Nev. 2012).
“647(1), a court must dismiss the case without prejudice and compel the plaintiff to file such a notice before filing another action. See Nev.Rev.”
Byrne Vs. Sunridge Builders, Inc., 2020 NV 69 (Nev. 2020).
“See NRS 40.647(1). If a claimant fails to comply with the prelitigation process before filing his or her lawsuit, the court must dismiss the action without prejudice.”
Barrett v. Eighth Jud. Dist. Ct., 2014 NV 65 (Nev. 2014).
“646; NRS 40.647. A claimant "may" give notice to a subcontractor, supplier, or design professional, if the contractor is unavailable, but the claimant is not required to do so.”
— Nev. Rev. Stat. § 40.647(2) — 3 cases
D.R. Horton, Inc. v. Eighth Jud. Dist. Court, 168 P.3d 731 (Nev. 2007).
“Horton further argues that the inadequacy of First Light’s notice frustrates its opportunity to repair under NRS 40.647. In its answer, First Light contends that its notice is sufficient and that D.”
Barrett v. Eighth Jud. Dist. Ct., 2014 NV 65 (Nev. 2014).
“646; NRS 40.647. A claimant "may" give notice to a subcontractor, supplier, or design professional, if the contractor is unavailable, but the claimant is not required to do so.”
— Nev. Rev. Stat. § 40.647(2)(a) — 2 cases
Waterfall Homeowners Ass'n v. Viega, Inc., 283 F.R.D. 571 (D. Nev. 2012).
“647(1), a court must dismiss the case without prejudice and compel the plaintiff to file such a notice before filing another action. See Nev.Rev.”
Byrne Vs. Sunridge Builders, Inc., 2020 NV 69 (Nev. 2020).
“See NRS 40.647(1). If a claimant fails to comply with the prelitigation process before filing his or her lawsuit, the court must dismiss the action without prejudice.”
— Nev. Rev. Stat. § 40.647(2)(b) — 10 cases
Waterfall Homeowners Ass'n v. Viega, Inc., 283 F.R.D. 571 (D. Nev. 2012).
“647(1), a court must dismiss the case without prejudice and compel the plaintiff to file such a notice before filing another action. See Nev.Rev.”
Byrne Vs. Sunridge Builders, Inc., 2020 NV 69 (Nev. 2020).
“See NRS 40.647(1). If a claimant fails to comply with the prelitigation process before filing his or her lawsuit, the court must dismiss the action without prejudice.”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.