N.Y. General Construction Law § 20 (2026)
Day, computation
Edition and currency
Other sources
Courts have cited this section in 166 opinions since 1985, 54 of them in the last five years.
§ 20. Day, computation. A number of days specified as a period from a certain day within which or after or before which an act is authorized or required to be done means such number of calendar days exclusive of the calendar day from which the reckoning is made. If such period is a period of two days, Saturday, Sunday or a public holiday must be excluded from the reckoning if it is an intervening day between the day from which the reckoning is made and the last day of the period. In computing any specified period of time from a specified event, the day upon which the event happens is deemed the day from which the reckoning is made. The day from which any specified period of time is reckoned shall be excluded in making the reckoning.
- Where it cites § 20
- “If such period is a period of two days, Saturday, Sunday or a public holiday must be excluded from the reckoning if it is in an intervening day between the day from which the reckoning is made and the last day of the period.”
- Where it cites § 20
- “, October 8, 2000), that date fell on a Sunday and the following Monday was a public holiday; the effective date of the Act was therefore postponed under General Construction Law §§ 20 and 25-a until Tuesday, October 10, 2000—two days after the incident at the synagogue.”
- Later courts cite it for
- “in whole or in substantial part because of a belief or perception regarding the race” · 2 citing courts
- Where it cites § 20
- “dy’s reckoning, application of a 30-day period from the service of the answer with counterclaim, plus a five-day extension to account for the service of the answer with counterclaim by mail (see CPLR 2103 [b] [2]), established the last date for timely service of a reply as June…”
- The case’s holding
- A court must dismiss a claim as abandoned if a default judgment is not sought within one year of the default unless sufficient cause is shown.
- Later courts cite it for
- “if the plaintiff fails to take proceedings for the entry of judgment within one year after the default, the court shall not enter judgment but shall dismiss the complaint as abandoned, without costs, upon its own initiative or on motion, unless sufficient cause is shown why the complaint should not be dismissed.” · 35 citing courts
- Where it cites § 20
- “They argue, however, that this time period should be measured as 40 days because the court should have excluded the last day, January 24, from its calculation since they could have hypothetically stated ready for trial on that date.”
- Later courts cite it for
- “new york courts have consistently held that, when computing a period of days, the first day is excluded but the last day is included” · 2 citing courts
- Where it cites § 20
- “The borrower's submissions established, prima facie, that recovery is time-barred for any unpaid installments that were due prior to November 10, 2009—to wit, from the installment due on April 1, 2009, up to and including the installment due on November 1, 2009 ( see CPLR…”
- The case’s holding
- The voluntary discontinuance of a foreclosure action does not constitute an affirmative act of revoking a prior acceleration of debt without clear and unambiguous evidence of de-acceleration.
- Later courts cite it for
- “repeatedly held that a lender's mere act of discontinuing an action, without more, does not constitute, in and of itself, an affirmative act of revoking an earlier acceleration of the debt” · 4 citing courts
- Where it cites § 20
- “It was therefore appropriate for the court below to apply General Construction Law § 20 which states: "In computing any specified period of time from a specified event, the day upon which the event happens is deemed the day from which the reckoning is made.”
- Holding on this section
- The day an event occurs is excluded from the computation of a statutory period under General Construction Law section 20.
- Where it cites § 20
- “Here, the record demonstrates that the defendants were served with the summons and complaint pursuant to CPLR 308(2), and that proof of such service was filed with the Nassau County Clerk's Office on March 25, 2016 ( see CPLR 308[2]; see also General Construction Law § 20). The…”
- Later courts cite it for
- “furthermore, where an action is subject to a mandatory settlement conference ( see cplr 3408), the one-year deadline imposed by cplr 3215(c) is tolled while settlement conferences are pending” · 2 citing courts
- Where it cites § 20
- “30, the day which begins the running of the “speedy trial clock” is excluded from the reckoning of days (People v Stiles, 70 NY2d 765, 767 ; see, General Construction Law § 20). 3 . In fact, defendant himself before the trial court requested that only 8 days of the relevant…”
- The case’s holding
- A criminal action commences when a defendant first appears in response to a desk appearance ticket, and a notice of readiness tolls the speedy trial clock during an adjournment.
- Later courts cite it for
- “a notice of readiness is the kind of record commitment to proceed which satisfies the people's duty to be ready for trial, and serves to toll the 'speedy trial clock” · 4 citing courts
- Where it cites § 20
- “10 (2) (see General Construction Law § 20; People v Prunier, 100 AD3d at 1270-1271).”
- Later courts cite it for
- “general construction law 25-a applies to extend the 90-day readiness period established under cpl 30.30 (1) (b) for defendants charged with certain misdemeanors” · 2 citing courts
- Where it cites § 20
- “At minimum, all time from the day after defendant's May 8, 2023, arraignment ( see General Construction Law § 20; People v Stiles, 70 NY2d 765, 767 [1987]) to, and including, the September 18, 2023, service and filing of the silent SCoC ( see General Construction Law § 20;…”
- Later courts cite it for
- “with all automatic discovery the people's discovery obligation is clear; they must 'make a diligent, good faith effort to . . . cause discovery to be made available . . . where it exists but is not within the prosecutor's possession.' whether the means, mechanisms or methodologies by which the people make discovery available to the defense are 'sufficient to satisfy cpl article 245 is fundamentally case-specific, as with any question of reasonableness, and will turn on the circumstances presented” · 2 citing courts
- Where it cites § 20
- “Even if the letter was delivered on April 12, 2000, the complaint was filed on May 12, 2000, a day short of the requisite 30-day period alloted to the Town to investigate and adjust the plaintiffs claim (see General Construction Law § 20). The complaint must be dismissed based…”
- Later courts cite it for
- “a plaintiff must not only plead in the complaint that he or she served a notice of claim but that the notice was served at least 30 days prior to commencement of the action and in that time the defendants neglected or refused to adjust or satisfy the claim” · 2 citing courts
- Where it cites § 20
- ““In calculating the 14-day time period, the date the misbehavior report is written is excluded” (Matter of Freeman v Selsky, 270 AD2d 547, 547-548 [2000]; see Matter of Harris v Goord, 268 AD2d 933, 934 [2000]; see generally General Construction Law § 20). Here, the second MBR…”
- Later courts cite it for
- “petitioner failed to exhaust his administrative remedies with respect to that contention, and this court has no discretionary authority to reach that contention” · 3 citing courts
- Where it cites § 20
- “Accordingly, any causes of action asserted by the plaintiff in her individual capacity must be dismissed as time-barred to the extent that they are based on acts occurring prior to November 6, 2004, since the notice of claim dated February 4, 2005, was not timely served with…”
- Where it cites § 20
- “The Supreme Court granted the motions, finding that the plaintiff’s affidavit of merit was sufficient but that she failed to proffer a justifiable excuse for the failure to comply with the 90-day notice.”
- Where it cites § 20
- “1 [a]), although the day from which the reckoning is made is excluded from the calculation (see General Construction Law § 20). As the record establishes that the incident occurred, the misbehavior report was prepared and petitioner was confined on September 11, 2014, and the…”
- Where it cites § 20
- “As such, the 24-month approval period began on April 2, 2015 ( see General Construction Law § 20; People v Stiles , 70 NY2d 765, 767 ), and, without any extensions, would have expired on April 1, 2017 ( see General Construction Law §§ 25-a, 30).”
- Where it cites § 20
- “[FN1] In calculating whether service was accomplished within the statutory 90-day period, general principles of statutory construction require excluding the date of injury and beginning the count on the following day ( see General Construction Law § 20; Turner v City of New York…”
- Where it cites § 20
- “Inasmuch as that day is not considered when calculating the length of his penalty, he was appropriately released after 30 days on September 14, 2007 (see General Construction Law § 20; see generally Matter of Vasquez v Goord, 14 AD3d 903, 904 [2005]).”
- Where it cites § 20
- “Respondents filed the certificate of election on September 29, 2000, and thus the 10-day period began to run on September 30, 2000 (see, General Construction Law § 20). Because the 10-day period expired on October 9, 2000, which was Columbus Day, the last date on which…”
- Later courts cite it for
- “too speculative to warrant the conclusion that the court abused its discretion in refusing to recuse itself here” · 5 citing courts
- Where it cites § 20
- “1 [a]), “although the day from which the reckoning is made is excluded from the calculation” (Matter of Garrow v Annucci, 141 AD3d 1046, 1047 [2016], citing General Construction Law § 20). As the record establishes that the incident occurred, the misbehavior report was prepared…”
Show all 166 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 19 cases in 2024. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 19 courts in all.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: text as retrieved May 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.