N.Y. Town Law § 282 (2026)
Court review
Edition and currency
Other sources
Courts have cited this section in 56 opinions since 1985.
§ 282. Court review. Any person or persons, jointly or severally aggrieved by any decision of the planning board concerning such plat or the changing of the zoning regulations of such land, or any officer, department, board or bureau of the town, may have the decision reviewed by a special term of the supreme court in the manner provided by article seventy-eight of the civil practice law and rules provided the proceeding is commenced within thirty days after the filing of the decision in the office of the town clerk. Commencement of the proceeding shall stay proceedings upon the decision appealed from. If, upon the hearing, it shall appear to the court that testimony is necessary for the proper disposition of the matter, it may take evidence or appoint a referee to take such evidence as it may direct and report the same to the court with his findings of fact and conclusions of law, which shall constitute a part of the proceedings upon which the determination of the court shall be made. The court may reverse or affirm, wholly or partly, or may modify the decision brought up for review. Costs shall not be allowed against the planning board, unless it shall appear to the court that it acted with gross negligence or in bad faith or with malice in making the decision appealed from. All issues in any proceeding under this section shall have preference over all other civil actions and proceedings.
- Where it cites § 282
- “Timeliness of Proceedings Against The Board As against the Board, the petition was correctly dismissed as untimely under Town Law § 282.”
- Where it cites § 282
- “They also alleged that the Board's decision to condition final site plan approval on their acceptance of the conservation restriction was arbitrary and capricious, and sought attorneys' fees pursuant to Town Law § 282.”
- Later courts cite it for
- “the contested resolution falls short of eliminating all economically viable uses of the encumbered property, the court looks to several factors to determine whether a taking occurred, including 'the resolution's economic effect on the landowner, the extent to which the resolution interferes with reasonable investment-backed expectations, and the character of the government action” · 3 citing courts
- Where it cites § 282
- “The Planning Board moved to dismiss the petition upon objections in point of law that the petitioner’s challenge to certain of the conditions of final subdivision approval was time barred pursuant to Town Law § 282 and that the Planning Board did not act illegally or in an…”
- Later courts cite it for
- “so long as there is a reasonable relationship between the problem sought to be alleviated and the application concerning the property” · 2 citing courts
- Where it cites § 282
- “Town Law § 276 establishes a two-stage (preliminary and final) subdivision plat approval procedure. Town Law § 282 states that "[a]ny person * * * aggrieved by any decision of the planning board concerning such plat * * * may have the decision [judicially] reviewed * * *…”
- Where it cites § 282
- “*803 Regardless of how the petitioners characterize this proceeding, they are, in effect, seeking to review the Planning Board’s determination dated June 19, 2008, and filed June 20, 2008, which is subject to a 30-day statute of limitations (see Town Law § 282). The petitioners’…”
- Later courts cite it for
- “the extraordinary remedy of mandamus is available in limited circumstances only to compel the performance of a purely ministerial act which does not involve the exercise of official discretion or judgment, and only when a clear legal right to the relief has been demonstrated” · 4 citing courts
- Where it cites § 282
- “The petitioner’s claims with respect to the propriety of the review by the Planning Board of the Town of Southampton (hereinafter the Planning Board) of the subdivision application pursuant to the State Environmental Quality Review Act (hereinafter SEQRA) were not time barred by…”
- Where it cites § 282
- “, 59 NY2d 385, 392; People v Graham, 55 NY2d 144, 152), but also the fact that subdivision (b) of that section makes the number of permitted dwelling units a matter of “the planning board’s judgment,” which may be overturned only if illegal, arbitrary or an abuse of discretion…”
- The case’s holding
- The issuance of a permit for a use allowed by a zoning ordinance may not be denied because the proposed use violates a private restrictive covenant or easement.
- Later courts cite it for
- “the use that may be made of land under a zoning ordinance and the use of the same land under an easement or restrictive covenant are, as a general rule, separate and distinct matters, the ordinance being a legislative enactment and the easement or covenant a matter of private agreement” · 8 citing courts
- Where it cites § 282
- “Thus, as the statute of limitations for a section 1983 action is three years, this action is not time barred as against the Planning Board and its members pursuant to Town Law § 282 (see 423 S.”
- Where it cites § 282
- “At the outset, we reject respondents’ contention that the court erred in deciding this proceeding on the merits (see Town Law § 282). Turning to the merits, Town Law § 267-b (1) provides that, in reviewing an administrative officer’s determination, the ZBA: “may reverse or…”
- Later courts cite it for
- “is limited to whether the administrative action is arbitrary and capricious or lacks a rational basis” · 3 citing courts
- Where it cites § 282
- “The Supreme Court properly dismissed as time barred that portion of the complaint challenging the subdivision approvals on the grounds of defective notice of hearing and failure to conduct an environmental review. Town Law § 282 provides that an aggrieved party may seek judicial…”
- Where it cites § 282
- “Respondents then moved to dismiss the petition/complaint arguing, inter alia, that the petition/ complaint was time barred by the 30-day Statute of Limitations set forth in Town Law § 282.”
- Where it cites § 282
- “Because the Board’s SEQRA review was completed as of May 16, 1990, the date of the filing of the preliminary plat approval, the 30-day Statute of Limitations contained in Town Law § 282 began to run at that time (see, Matter of Long Is.”
- Later courts cite it for
- “resolution of questions of conflict of interest requires a case-by-case examination of the relevant facts and circumstances” · 7 citing courts
- Where it cites § 282
- “The respondents and Highview separately moved to dismiss the petition on the grounds that the petitioners’ challenge to the SEQRA findings statement and the resolution was time-barred pursuant to Town Law § 282 and that the petitioners lacked standing to bring the proceeding.”
- Where it cites § 282
- “v Williams, 131 AD2d 205, 207-208 ), his challenge is time barred under the 30-day limitation period set forth by Town Law §§282 and 274-a (3) which displace the four-month limitation period of CPLR 217.”
- Where it cites § 282
- “The statute of limitations defense has no merit as respondents admit in their answer that petitioners timely commenced this proceeding by the filing of a notice of petition and petition in the Ulster County Clerk’s office within the 30-day statute of limitations found in Town…”
- Where it cites § 282
- “In a determination dated June 8, 2010, and stamped “received” June 9, 2010, the Zoning Board of Appeals of the Town of East Hampton (hereinafter the ZBA) granted the application of Vinayak Singh for an area variance. Under Town Law § 282, the petitioner, Singh’s neighbor, had 30…”
- Where it cites § 282
- “, N.Y. Town Law § 282 (McKinney 1987); Mass.”
- Where it cites § 282
- “Town Law § 282 provides in pertinent part that, "[a]ny person * * * aggrieved by any decision of the planning board concerning such plat * * * may have the decision reviewed by a special term of the supreme court in the manner provided by article seventy-eight of the civil…”
- Where it cites § 282
- “Notwithstanding, this proceeding was not commenced until November 17, 2000, over 22 months after the subdivision plat was approved, nearly a year after the road itself was constructed and nearly five months after the Planning Board meeting at which their objections were voiced.…”
- Where it cites § 282
- “The 30-day statute of limitations for challenging the subdivision proposal on State Environmental Quality Review Act ([SEQRA] ECL art 8) grounds will not be triggered until the Planning Board files the preliminary plat approval (see Town Law § 282; Matter of Long Is. Pine…”
Show all 56 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 4 cases in 1990. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: text as retrieved May 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.