Ohio Revised Code homeSearch Ohio
Ohio Rev. CodeChapter 4906

Ohio Rev. Code § 4906.01 (2026)

Power siting definitions

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) ACTIVE · 5 IN 5Y cited 1995–2026 14citing cases
At a glance

Courts have cited this section in 14 opinions since 1995, 5 of them in the last five years. The most litigated part is subsection (B)(1) (4 cases).

As used in Chapter 4906. of the Revised Code:

(A) "Person" means an individual, corporation, business trust, association, estate, trust, or partnership or any officer, board, commission, department, division, or bureau of the state or a political subdivision of the state, or any other entity.

(B)(1) "Major utility facility" means:

(a) Electric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more;

(b) An electric transmission line and associated facilities of a design capacity of one hundred kilovolts or more;

(c) A gas pipeline that is greater than five hundred feet in length, and its associated facilities, is more than nine inches in outside diameter and is designed for transporting gas at a maximum allowable operating pressure in excess of one hundred twenty-five pounds per square inch.

(2) "Major utility facility" does not include any of the following:

(a) Gas transmission lines over which an agency of the United States has exclusive jurisdiction;

(b) Any solid waste facilities as defined in section 6123.01 of the Revised Code;

(c) Electric distributing lines and associated facilities as defined by the power siting board;

(d) Any manufacturing facility that creates byproducts that may be used in the generation of electricity as defined by the power siting board;

(e) Gathering lines, gas gathering pipelines, and processing plant gas stub pipelines as those terms are defined in section 4905.90 of the Revised Code and associated facilities;

(f) Any gas processing plant as defined in section 4905.90 of the Revised Code;

(g) Natural gas liquids finished product pipelines;

(h) Pipelines from a gas processing plant as defined in section 4905.90 of the Revised Code to a natural gas liquids fractionation plant, including a raw natural gas liquids pipeline, or to an interstate or intrastate gas pipeline;

(i) Any natural gas liquids fractionation plant;

(j) A production operation as defined in section 1509.01 of the Revised Code, including all pipelines upstream of any gathering lines;

(k) Any compressor stations used by the following:

(i) A gathering line, a gas gathering pipeline, a processing plant gas stub pipeline, or a gas processing plant as those terms are defined in section 4905.90 of the Revised Code;

(ii) A natural gas liquids finished product pipeline, a natural gas liquids fractionation plant, or any pipeline upstream of a natural gas liquids fractionation plant; or

(iii) A production operation as defined in section 1509.01 of the Revised Code.

(C) "Commence to construct" means any clearing of land, excavation, or other action that would adversely affect the natural environment of the site or route of a major utility facility, but does not include surveying changes needed for temporary use of sites or routes for nonutility purposes, or uses in securing geological data, including necessary borings to ascertain foundation conditions.

(D) "Certificate" means a certificate of environmental compatibility and public need issued by the power siting board under section 4906.10 of the Revised Code or a construction certificate issued by the board under rules adopted under divisions (E) to (H) of section 4906.03 of the Revised Code.

(E) "Gas" means natural gas, flammable gas, or gas that is toxic or corrosive.

(F) "Natural gas liquids finished product pipeline" means a pipeline that carries finished product natural gas liquids to the inlet of an interstate or intrastate finished product natural gas liquid transmission pipeline, rail loading facility, or other petrochemical or refinery facility.

(G) "Large solar facility" means an electric generating plant that consists of solar panels and associated facilities with a single interconnection to the electrical grid that is a major utility facility.

(H) "Large wind farm" means an electric generating plant that consists of wind turbines and associated facilities with a single interconnection to the electrical grid that is a major utility facility.

(I) "Natural gas liquids fractionation plant" means a facility that takes a feed of raw natural gas liquids and produces finished product natural gas liquids.

(J) "Raw natural gas" means hydrocarbons that are produced in a gaseous state from gas wells and that generally include methane, ethane, propane, butanes, pentanes, hexanes, heptanes, octanes, nonanes, and decanes, plus other naturally occurring impurities like water, carbon dioxide, hydrogen sulfide, nitrogen, oxygen, and helium.

(K) "Raw natural gas liquids" means naturally occurring hydrocarbons contained in raw natural gas that are extracted in a gas processing plant and liquefied and generally include mixtures of ethane, propane, butanes, and natural gasoline.

(L) "Finished product natural gas liquids" means an individual finished product produced by a natural gas liquids fractionation plant as a liquid that meets the specifications for commercial products as defined by the gas processors association. Those products include ethane, propane, iso-butane, normal butane, and natural gasoline.

(M) "Advanced transmission technologies" means software or hardware technologies that increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission system, including grid-enhancing technologies such as dynamic line rating, advanced power flow controllers, and topology optimization; advanced conductors; and other technologies designed to reduce transmission congestion, or increase the capacity, efficiency, reliability, or safety of an existing or new electric transmission system.

(N) "Advanced conductor" means a conductor with a direct current electrical resistance that is at least ten per cent lower than existing conductors of a similar diameter on the electric transmission system while simultaneously increasing the energy carrying capacity by at least seventy-five per cent.

Last updated May 22, 2025 at 12:27 PM

The 14 cases that cite Ohio Rev. Code § 4906.01 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENIn re Application of Champaign Wind, L.L.C., 2016-Ohio-1513, 58 N.E.3d 1142.
cites § 4906.01 4×cited by 16 cases
Where it cites § 4906.01
“A majority of the county’s and neighbors’ arguments relate to procedural or evidentiary errors they allege the board committed during both discovery and the adjudicatory hearing.”
The case’s holding
An administrative board decision regarding questions of fact is not reversed if the record contains sufficient probative evidence showing the decision is not manifestly against the weight of the evidence.
Later courts cite it for
“only when our review of the record reveals that the order is unlawful or unreasonable.” · 3 citing courts
2
GREENIn re Application of Middletown Coke Co., 2010-Ohio-5725, 939 N.E.2d 1210.
cites § 4906.01 12×subsections: (B)(1) 12×cited by 3 cases
Where it cites § 4906.01
“Under R.C. 4906.01(B)(1), a “major utility facility” includes “[e]lectric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more.”
3
GREENBiglin v. S (In re Black Fork Wind Energy, L. L.C.), 124 N.E.3d 787 (Ohio 2018).
cites § 4906.01 2×cited by 12 cases
Where it cites § 4906.01
“3 {¶ 13} Most importantly for purposes of this case, to commence the amendment process, a litigant must first file an application with the board that is "in such form and contain[s] such information as the board prescribes.”
Later courts cite it for
“we have long held that 'constitutional questions will not be decided until the necessity for a decision arises on the record before the court.” · 2 citing courts
4
GREENIn re Application of Buckeye Wind, L.L.C., 2012-Ohio-878, 131 Ohio St. 3d 449.
cites § 4906.01 2×subsections: (B)(1) 2×cited by 15 cases
Where it cites § 4906.01
“The wind farm’s expected generation capacity exceeded 126 megawatts, qualifying it under R.C. 4906.01(B)(1) as a “major utility facility” that required the approval of the board.”
The case’s holding
The Power Siting Board may grant a major utility facility certificate subject to whatever terms, conditions, or modifications of construction, operation, or maintenance it considers appropriate.
Later courts cite it for
“upon such terms, conditions, or modifications of the construction, operation, or maintenance of the major utility facility as the board considers appropriate.” · 1 citing court
5
GREENIn re Application of Black Fork Wind Energy, L.L.C., 2013-Ohio-5478, 3 N.E.3d 173.
cites § 4906.01 1×cited by 60 cases
Where it cites § 4906.01
“In addition to the turbines, Black Fork’s project includes access roads, electrical collection lines, a *44 construction-staging area, a concrete-batch plant, a substation, and an operation and maintenance facility.”
The case’s holding
A party forfeits a due process claim regarding the denial of cross-examination if it fails to subpoena witnesses or object to their absence during an administrative hearing.
Later courts cite it for
“with effectively zero air emissions and waste generation.” · 2 citing courts
cites § 4906.01 2×cited by 6 cases
Where it cites § 4906.01
“Code 4906-5- 10(B), 2008-2009 Ohio Monthly Record 2-4257, effective June 19, 2009.3 {¶ 13} Most importantly for purposes of this case, to commence the amendment process, a litigant must first file an application with the board that is “in such form and contain[s] such…”
7
GREENIn re Application of Alamo Solar I, L.L.C., 2023-Ohio-3778, 235 N.E.3d 372.
cites § 4906.01 1×subsections: (B)(1)(a)cited by 11 cases
Where it cites § 4906.01
“R.C. 4906.01(B)(1)(a) and 4906.04. {¶ 6} In 2019, joint stipulations and recommendations were filed in each case.”
The case’s holding
A court independently interprets an agency's regulation, applying clear text as written and giving the agency's reading only persuasive weight when the regulation is ambiguous.
Later courts cite it for
“if the text of a regulation is clear, then we apply it as written and stop right there. but if we determine that the text is ambiguous, we may consider the board's interpretation only for its persuasive power.” · 2 citing courts
8
GREENSunoco Pipeline L.P. v. Teter, 2016-Ohio-7073.
cites § 4906.01 1×subsections: (I)cited by 7 cases
Where it cites § 4906.01
“R.C. 4906.01(I). {¶35} Furthermore, Liquid Petroleum Gas, also known as LPG, is defined in the Fire Code of the Ohio Administrative Code.”
9
GREENState ex rel. Ohio Edison Co. v. Parrott, 654 N.E.2d 106 (Ohio 1995).
cites § 4906.01 1×subsections: (B)(2)cited by 15 cases
Where it cites § 4906.01
“R.C. 4906.01(B)(2) and *708 (D), 4906.04, and 4906.”
Later courts cite it for
“where there is a patent and unambiguous lack of subject matter jurisdiction.” · 2 citing courts
10
NEUTRALIn re Application of 6011 Greenwich Windpark, L.L.C., 2019-Ohio-2406, 134 N.E.3d 1157.
cites § 4906.01 2×subsections: (B)(1) (D)cited by 6 cases
Where it cites § 4906.01
“FACTS AND PROCEDURAL BACKGROUND {¶ 3} The Power Siting Board has exclusive authority to issue a certificate of environmental compatibility and public need for construction, operation, and maintenance of a “major utility facility,” R.C. 4906.01(B)(1), such as a wind- powered…”
cites § 4906.01 2×subsections: (B)(1)(c) 2×cited by 1 case
Where it cites § 4906.01
“See R.C. 4906.01(B)(1)(c) and 4906.04. {¶ 5} R.”
12
GREENIn re Application of Harvey Solar I, L.L.C., 2025-Ohio-1503, 267 N.E.3d 649.
cites § 4906.01 1×cited by 1 case
Where it cites § 4906.01
“The Power Siting Board Approves the Harvey Solar Project {¶ 5} Before construction begins on a facility that will generate at least 50 megawatts of power, the Power Siting Board must issue a “certificate of environmental compatibility and public need,” R.C. 4906.01. R.C.…”
Later courts cite it for
“it is well-settled that the board is not required to resolve every issue before issuing a certificate.” · 1 citing court
cites § 4906.01 1×subsections: (B)(1)(a)cited by 0 cases
Where it cites § 4906.01
“” R.C. 4906.01(B)(1)(a). 2 January Term, 2025 an applicant seeking a certificate of environmental compatibility and public need to construct a major utility facility must file with the board chairperson an application containing “[s]uch .”
14
NEUTRALIn re Application of Oak Run Solar Proj., L.L.C., 2026-Ohio-1849, 279 N.E.3d 599.
cites § 4906.01 2×subsections: (B)(1)cited by 0 cases
Where it cites § 4906.01
“The board found, and there is no dispute, that Oak Run’s proposed solar farm is a “major utility facility,” as defined in R.C. 4906.01. But the term “facility” also encompasses “all associated facilities,” which is defined by rule as “rights-of-way, land, permanent access roads,…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199520102026

One bar per year. Tallest: 2 cases in 2016. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ohio13Ohio Ct. App.1
By subsection
(B)(1)4 cases
In re Application of Middletown Coke Co., 2010-Ohio-5725, 939 N.E.2d 1210.“Under R.C. 4906.01(B)(1), a “major utility facility” includes “[e]lectric generating plant and associated facilities designed for, or capable of, operation at a capacity of fifty megawatts or more.”
In re Application of Buckeye Wind, L.L.C., 2012-Ohio-878, 131 Ohio St. 3d 449.“The wind farm’s expected generation capacity exceeded 126 megawatts, qualifying it under R.C. 4906.01(B)(1) as a “major utility facility” that required the approval of the board.”
In re Application of 6011 Greenwich Windpark, L.L.C., 2019-Ohio-2406, 134 N.E.3d 1157.“FACTS AND PROCEDURAL BACKGROUND {¶ 3} The Power Siting Board has exclusive authority to issue a certificate of environmental compatibility and public need for construction, operation, and maintenance of a “major utility facility,” R.C. 4906.01(B)(1), such as a wind- powered…”
In re Application of Oak Run Solar Proj., L.L.C., 2026-Ohio-1849, 279 N.E.3d 599.“The board found, and there is no dispute, that Oak Run’s proposed solar farm is a “major utility facility,” as defined in R.C. 4906.01. But the term “facility” also encompasses “all associated facilities,” which is defined by rule as “rights-of-way, land, permanent access roads,…”
(B)(1)(a)2 cases
In re Application of Alamo Solar I, L.L.C., 2023-Ohio-3778, 235 N.E.3d 372.“R.C. 4906.01(B)(1)(a) and 4906.04. {¶ 6} In 2019, joint stipulations and recommendations were filed in each case.”
In re Application of S. Branch Solar, L.L.C., 2025-Ohio-5679.“” R.C. 4906.01(B)(1)(a). 2 January Term, 2025 an applicant seeking a certificate of environmental compatibility and public need to construct a major utility facility must file with the board chairperson an application containing “[s]uch .”
(B)(1)(c)1 case
In re Letter of Notification Application of Columbia Gas of Ohio, Inc., 2024-Ohio-4747, 248 N.E.3d 235.“See R.C. 4906.01(B)(1)(c) and 4906.04. {¶ 5} R.”
(B)(2)1 case
State ex rel. Ohio Edison Co. v. Parrott, 654 N.E.2d 106 (Ohio 1995).“R.C. 4906.01(B)(2) and *708 (D), 4906.04, and 4906.”
(D)1 case
(I)1 case
Sunoco Pipeline L.P. v. Teter, 2016-Ohio-7073.“R.C. 4906.01(I). {¶35} Furthermore, Liquid Petroleum Gas, also known as LPG, is defined in the Fire Code of the Ohio Administrative Code.”
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Ohio Revised Code Home  |  Search Ohio  |  Search cases for this section  |  syfert.com