Oklahoma Statutes homeSearch Oklahoma
Okla. Stat.Title 42 — Liens

Okla. Stat. tit. 42, § 143 (2026)

Lien by or through subcontractor

Edition and currency
laws through the 2025 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2025 session (checked Sept. 2026) cited 1953–2019 30citing cases
At a glance

Courts have cited this section in 30 opinions since 1953.

Any person who shall furnish any such material or lease or rent equipment used on said land or perform such labor as a subcontractor, or as an artisan or day laborer in the employ of the contractor, may obtain a lien upon such land, or improvements, or both, from the same time, in the same manner, and to the same extent as the original contractor, for the amount due for such material, equipment and labor, as well as any applicable profit and overhead costs due to the person; and any artisan or day laborer in the employ of, and any person furnishing material or equipment used on said land to, such subcontractor may obtain a lien upon such land, or improvements, or both, for the same time, in the same manner, and to the same extent as the subcontractor, for the amount due for such material, equipment used on said land and labor, as well as any applicable profit and overhead costs due to the person, by filing with the county clerk of the county in which the land is situated, within ninety (90) days after the date upon which material or equipment used on said land was last furnished or labor last performed under such subcontract, a statement, verified by affidavit, setting forth the amount due from the contractor to the claimant, and the items thereof, as nearly as practicable, the name of the owner, the name of the contractor, the name of the claimant, and a legal description of the property upon which a lien is claimed. Immediately upon the filing of such statement the county clerk shall enter a record of the same against the tract index and in the journal provided for in the preceding section, and in the manner therein specified. Provided further, that the owner of any land affected by such lien shall not thereby become liable to any claimant for any greater amount than he contracted to pay the original contractor. The risk of all payments made to the original contractor shall be upon such owner until the expiration of the ninety (90) days herein specified, and no owner shall be liable to an action by such contractor until the expiration of said ninety (90) days, and such owner may pay such subcontractor the amount due him from such contractor for such labor, equipment used on said land and material, and the amount so paid shall be held and deemed a payment of said amount to the original contractor.

R.L. 1910, § 3864. Amended by Laws 1957, p. 417, § 1, emerg. eff. May 29, 1957; Laws 1977, c. 207, § 8, eff. Oct. 1, 1977; Laws 1978, c. 133, § 4, eff. Oct. 1, 1978; Laws 1980, c. 216, § 3, emerg. eff. May 30, 1980; Laws 2013, c. 78, § 2, eff. Nov. 1, 2013.

The 20 cases that cite Okla. Stat. tit. 42, § 143 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENKnapp v. Arko Interstate Elec. Co., 448 P.2d 996 (Okla. 1968).
cites § 143 13×cited by 10 cases
Where it cites § 143
“This appeal is concerned with a judgment of the District Court of Muskogee County establishing liens claimed under the provisions of 42 O.S.1961, § 143 against certain real property located in that county.”
2
GREENMcGlumphy v. Jetero Const. Co., 593 P.2d 76 (Okla. 1978).
cites § 143 3×cited by 11 cases
Where it cites § 143
“Lasater adopts the same positions as Jetero and Travelers except as to Lasater’s recovery; there contending, breach does not bar recovery for unpaid, but performed work.”
3
GREENMurphy Oil USA Inc v. Trivental Inc, 438 F.3d 1008 (10th Cir. 2006).
cites § 143 1×cited by 23 cases
Where it cites § 143
“From all appearances, Mustang complied with Okla. Stat. tit. 42, § 143 's notice and perfection procedures, and the lien claim was timely filed.”
4
GREENLiberty Plan Co. v. Francis T. Smith Lumber Co., 360 P.2d 500 (Okla. 1961).
cites § 143 2×cited by 39 cases
Where it cites § 143
“Since plaintiff asserts its material-man’s lien as a subcontractor, notice in writing to the owner was required under the provisions of 42 O.S.Supp.1957 § 143. Notice by registered mail is sufficient to satisfy this statutory requirement.”
The case’s holding
A materialman's lien is not defeated by failing to attach an itemized statement, which may be supplied by amendment before or during trial; variance is harmless absent prejudice.
Later courts cite it for
“by an appropriate amendment such itemized statement is supplied either before or during trial.” · 1 citing court
5
GREENWelling v. Am. Roofing & Sheet Metal Co., 617 P.2d 206 (Okla. 1980).
cites § 143 1×cited by 39 cases
Where it cites § 143
“42 O.S.1971, § 143. The court further found, however, that the defendant was really a contractor to the $2,700 re-roofing portion, and established a lien for that amount, as the statement was filed within the 120 days allowed a contractor, 42 O.”
The case’s holding
A person is a sub-contractor if they enter into an express or implied contract to perform work for a person who has already contracted for that performance.
6
GREENCashway Lumber Co. v. Langston, 479 P.2d 582 (Okla. 1970).
cites § 143 3×cited by 13 cases
Where it cites § 143
“We hold that Joe Brown Company is entitled to obtain a lien, 42 O.S.1961, § 143, and reverse No. 42,582.”
7
GREENFirst Nat'l Bank of Pauls Valley v. Crudup, 656 P.2d 914 (Okla. 1982).
cites § 143 1×cited by 33 cases
Where it cites § 143
“A foreclosure suit is prematurely brought if commenced before the statutory period in 42 O.S.1971 § 143. Smith v. Findley, Okl.”
8
GREENJones v. Purcell Investments, LLC, 2010 OK CIV APP 15, 231 P.3d 706.
cites § 143 1×cited by 13 cases
Where it cites § 143
“Thus, 42 O.S. § 143 allows the subcontractors to file their lien claims up to 90 days after the job is completed.”
9
cites § 143 4×cited by 7 cases
Where it cites § 143
“Defendants contend the lien claims were not timely filed as required by 42 O.S.1961, § 143. Defendants’ theory for reversal appears to be bottomed on their analysis of the facts, which defendants construe as follows: Spartan Petroleum Corporation entered a written contract with…”
10
GREENDuncan v. Neal (In re Neal), 324 B.R. 365 (Bankr. W.D. Okla. 2005).
cites § 143 1×cited by 11 cases
Where it cites § 143
“Under Oklahoma law, one who furnishes material or labor to a contractor may obtain a lien by filing a sworn statement of lien in the county clerk’s office within 90 days after the material or labor was furnished.”
Later courts cite it for
“the tenth circuit has taken a very narrow view of the concept of fiduciary duty under this section.” · 5 citing courts
11
GREENAnchor Concrete Co. v. Victor Sav. & Loan Ass'n, 664 P.2d 396 (Okla. 1983).
cites § 143 1×cited by 12 cases
Where it cites § 143
“Finally, Subcontractor’s argument against the award of attorney’s fees to Owner rests on Subcontractor’s conviction that since it would prevail on appeal, the attorney’s fees awarded in the court below could not stand.”
12
GREENAm.-First Title & Trust Co. v. Ewing, 403 P.2d 488 (Okla. 1965).
cites § 143 1×cited by 33 cases
Where it cites § 143
“Under the above circumstances, a sub-contractor’s rights, although statutory (See Title 42 O.S.1961, § 143), do not accrue by virtue of his performing labor or furnishing materials under a contract with the owner, but by virtue of a contract with the general contractor whose…”
13
GREENGibson v. Dunham, 346 P.2d 327 (Okla. 1959).
cites § 143 2×cited by 7 cases
Where it cites § 143
“As such he was entitled to a lien as a sub-contractor for materials furnished to the contractor under the provisions of 42 O.S.1951 § 143. It is also well settled that, under 42 O.”
14
GREENShawver & Son, Inc. v. Tefertiller, 772 P.2d 396 (Okla. 1989).
cites § 143 1×cited by 7 cases
Where it cites § 143
“The United States Bankruptcy Court for the Western District of Oklahoma has certified a question of law wherein the pivotal issue is whether the perfection of a mechanic’s and materialmen’s lien pursuant to 42 O.S.1981 § 143 is required to assert a claim upon construction trust…”
15
GREENMatter of Mahan & Rowsey, Inc., 27 B.R. 883 (Bankr. W.D. Okla. 1983).
cites § 143 1×cited by 5 cases
Where it cites § 143
“First, it attempts to distinguish Forry as a decision interpreting only 42 O.S.1981 § 143, dealing with sub-contractors’ obligations for perfecting liens rather than interpreting § 144, the section in issue.”
16
GREENGaddis-Walker Elec. Co. v. Phillips Petroleum Co., 526 P.2d 964 (Okla. Civ. App. 1974).
cites § 143 1×cited by 9 cases
Where it cites § 143
“1971 § 143 reads: “Any person who shall furnish any such material or perform such labor as a subcontractor, or as an artisan or day laborer in the employ of the contractor, may obtain a lien upon such land, or improvements, or both, from the same time, in the same manner, and to…”
17
GREENOklahoma Hardware Co. v. Townsend, 494 P.2d 326 (Okla. 1972).
cites § 143 3×cited by 2 cases
Where it cites § 143
“The trial court found that Townsends, the purchasers of the property, were the “owners” within our lien laws; that the materi-alman, plaintiff in error, failed to give written notice to the “owners” as required by 42 O.S.1961, § 143; and that the property was not subject to the…”
18
GREENMobile Components, Inc. v. Layon, 623 P.2d 591 (Okla. 1980).
cites § 143 1×cited by 3 cases
Where it cites § 143
“The mischief which may be wrought by frivolous, malicious, or fraudulent lien claimants is graphically illustrated by an article which appeared in The Daily Oklahoman in 1979.”
19
GREENCyclone Drilling & Workover, Inc. v. Woods, 671 P.2d 688 (Okla. Civ. App. 1983).
cites § 143 1×cited by 2 cases
Where it cites § 143
“1981 § 142, or ninety days if the contract is with a contractor, 42 O.S.1981 § 143, to file lien statements.”
20
GREENCushing Country Club v. Boardman Co., 381 P.2d 856 (Okla. 1963).
cites § 143 1×cited by 4 cases
Where it cites § 143
“” The statute under which a subcontractor’s lien is obtained is 42 O.S.1961 § 143. The pertinent language with which we are concerned here is: “ * * * by filing with the clerk of the district court * * * within ninety (90) days after the date upon which material was last…”

Show all 30 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195219852019

One bar per 2 years. Tallest: 4 cases in 1958–1959. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Okla.22Okla. Civ. App.4Bankr. W.D. Okla.210th Cir.1W.D. Okla.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 30 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2025 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Oklahoma Statutes Home  |  Search Oklahoma  |  Search cases for this section  |  syfert.com