U.S. CodeTitle 16Chapter 12— Federal Regulation and Development of PowerSubchapter I— Regulation of the Development of Water Power and Resources

16 U.S.C. § 796 (2026)

Definitions

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1929–2025 263citing cases
At a glance

Courts have cited this section in 263 opinions since 1929, 16 of them in the last five years. The most litigated part is subsection (8) (2 cases).

The words defined in this section shall have the following meanings for purposes of this chapter, to wit:(1) “public lands” means such lands and interest in lands owned by the United States as are subject to private appropriation and disposal under public land laws. It shall not include “reservations”, as hereinafter defined;(2) “reservations” means national forests, tribal lands embraced within Indian reservations, military reservations, and other lands and interests in lands owned by the United States, and withdrawn, reserved, or withheld from private appropriation and disposal under the public land laws; also lands and interests in lands acquired and held for any public purposes; but shall not include national monuments or national parks;(3) “corporation” means any corporation, joint-stock company, partnership, association, business trust, organized group of persons, whether incorporated or not, or a receiver or receivers, trustee or trustees of any of the foregoing. It shall not include “municipalities” as hereinafter defined;(4) “person” means an individual or a corporation;(5) “licensee” means any person, State, or municipality licensed under the provisions of section 797 of this title, and any assignee or successor in interest thereof;(6) “State” means a State admitted to the Union, the District of Columbia, and any organized Territory of the United States;(7) “municipality” means a city, county, irrigation district, drainage district, or other political subdivision or agency of a State competent under the laws thereof to carry on the business of developing, transmitting, utilizing, or distributing power;(8) “navigable waters” means those parts of streams or other bodies of water over which Congress has jurisdiction under its authority to regulate commerce with foreign nations and among the several States, and which either in their natural or improved condition notwithstanding interruptions between the navigable parts of such streams or waters by falls, shallows, or rapids compelling land carriage, are used or suitable for use for the transportation of persons or property in interstate or foreign commerce, including therein all such interrupting falls, shallows, or rapids, together with such other parts of streams as shall have been authorized by Congress for improvement by the United States or shall have been recommended to Congress for such improvement after investigation under its authority;(9) “municipal purposes” means and includes all purposes within municipal powers as defined by the constitution or laws of the State or by the charter of the municipality;(10) “Government dam” means a dam or other work constructed or owned by the United States for Government purposes with or without contribution from others;(11) “project” means complete unit of improvement or development, consisting of a power house, all water conduits, all dams and appurtenant works and structures (including navigation structures) which are a part of said unit, and all storage, diverting, or forebay reservoirs directly connected therewith, the primary line or lines transmitting power therefrom to the point of junction with the distribution system or with the interconnected primary transmission system, all miscellaneous structures used and useful in connection with said unit or any part thereof, and all water-rights, rights-of-way, ditches, dams, reservoirs, lands, or interest in lands the use and occupancy of which are necessary or appropriate in the maintenance and operation of such unit;(12) “project works” means the physical structures of a project;(13) “net investment” in a project means the actual legitimate original cost thereof as defined and interpreted in the “classification of investment in road and equipment of steam roads, issue of 1914, Interstate Commerce Commission”, plus similar costs of additions thereto and betterments thereof, minus the sum of the following items properly allocated thereto, if and to the extent that such items have been accumulated during the period of the license from earnings in excess of a fair return on such investment: (a) Unappropriated surplus, (b) aggregate credit balances of current depreciation accounts, and (c) aggregate appropriations of surplus or income held in amortization, sinking fund, or similar reserves, or expended for additions or betterments or used for the purposes for which such reserves were created. The term “cost” shall include, insofar as applicable, the elements thereof prescribed in said classification, but shall not include expenditures from funds obtained through donations by States, municipalities, individuals, or others, and said classification of investment of the Interstate Commerce Commission shall insofar as applicable be published and promulgated as a part of the rules and regulations of the Commission;(14) “Commission” and “Commissioner” means the Federal Power Commission, and a member thereof, respectively;(15) “State commission” means the regulatory body of the State or municipality having jurisdiction to regulate rates and charges for the sale of electric energy to consumers within the State or municipality;(16) “security” means any note, stock, treasury stock, bond, debenture, or other evidence of interest in or indebtedness of a corporation subject to the provisions of this chapter;(17)(A) “small power production facility” means a facility which is an eligible solar, wind, waste, or geothermal facility, or a facility which—(i) produces electric energy solely by the use, as a primary energy source, of biomass, waste, renewable resources, geothermal resources, or any combination thereof; and(ii) has a power production capacity which, together with any other facilities located at the same site (as determined by the Commission), is not greater than 80 megawatts;(B) “primary energy source” means the fuel or fuels used for the generation of electric energy, except that such term does not include, as determined under rules prescribed by the Commission, in consultation with the Secretary of Energy—(i) the minimum amounts of fuel required for ignition, startup, testing, flame stabilization, and control uses, and(ii) the minimum amounts of fuel required to alleviate or prevent—(I) unanticipated equipment outages, and(II) emergencies, directly affecting the public health, safety, or welfare, which would result from electric power outages;(C) “qualifying small power production facility” means a small power production facility that the Commission determines, by rule, meets such requirements (including requirements respecting fuel use, fuel efficiency, and reliability) as the Commission may, by rule, prescribe;(D) “qualifying small power producer” means the owner or operator of a qualifying small power production facility;(E) “eligible solar, wind, waste or geothermal facility” means a facility which produces electric energy solely by the use, as a primary energy source, of solar energy, wind energy, waste resources or geothermal resources; but only if—(i) either of the following is submitted to the Commission not later than December 31, 1994:(I) an application for certification of the facility as a qualifying small power production facility; or(II) notice that the facility meets the requirements for qualification; and(ii) construction of such facility commences not later than December 31, 1999, or, if not, reasonable diligence is exercised toward the completion of such facility taking into account all factors relevant to construction of the facility.11 So in original. The period probably should be a semicolon.(18)(A) “cogeneration facility” means a facility which produces—(i) electric energy, and(ii) steam or forms of useful energy (such as heat) which are used for industrial, commercial, heating, or cooling purposes;(B) “qualifying cogeneration facility” means a cogeneration facility that the Commission determines, by rule, meets such requirements (including requirements respecting minimum size, fuel use, and fuel efficiency) as the Commission may, by rule, prescribe;(C) “qualifying cogenerator” means the owner or operator of a qualifying cogeneration facility;(19) “Federal power marketing agency” means any agency or instrumentality of the United States (other than the Tennessee Valley Authority) which sells electric energy;(20) “evidentiary hearings” and “evidentiary proceeding” mean a proceeding conducted as provided in sections 554, 556, and 557 of title 5;(21) “State regulatory authority” has the same meaning as the term “State commission”, except that in the case of an electric utility with respect to which the Tennessee Valley Authority has ratemaking authority (as defined in section 2602 of this title), such term means the Tennessee Valley Authority;(22)Electric utility.—(A) The term “electric utility” means a person or Federal or State agency (including an entity described in section 824(f) of this title) that sells electric energy.1(B) The term “electric utility” includes the Tennessee Valley Authority and each Federal power marketing administration.1(23)Transmitting utility.—The term “transmitting utility” means an entity (including an entity described in section 824(f) of this title) that owns, operates, or controls facilities used for the transmission of electric energy—(A) in interstate commerce;(B) for the sale of electric energy at wholesale.1(24)Wholesale transmission services.—The term “wholesale transmission services” means the transmission of electric energy sold, or to be sold, at wholesale in interstate commerce.1(25)Exempt wholesale generator.—The term “exempt wholesale generator” shall have the meaning provided by section 79z–5a 22 See References in Text note below. of title 15.1(26)Electric cooperative.—The term “electric cooperative” means a cooperatively owned electric utility.1(27) RTO.—The term “Regional Transmission Organization” or “RTO” means an entity of sufficient regional scope approved by the Commission—(A) to exercise operational or functional control of facilities used for the transmission of electric energy in interstate commerce; and(B) to ensure nondiscriminatory access to the facilities.1(28) ISO.—The term “Independent System Operator” or “ISO” means an entity approved by the Commission—(A) to exercise operational or functional control of facilities used for the transmission of electric energy in interstate commerce; and(B) to ensure nondiscriminatory access to the facilities.33 So in original. The period probably should be “; and”.(29)Transmission organization.—The term “Transmission Organization” means a Regional Transmission Organization, Independent System Operator, independent transmission provider, or other transmission organization finally approved by the Commission for the operation of transmission facilities.(June 10, 1920, ch. 285, pt. I, § 3, 41 Stat. 1063; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 201, 212, 49 Stat. 838, 847; Pub. L. 95–617, title II, § 201, Nov. 9, 1978, 92 Stat. 3134; Pub. L. 96–294, title VI, § 643(a)(1), June 30, 1980, 94 Stat. 770; Pub. L. 101–575, § 3, Nov. 15, 1990, 104 Stat. 2834; Pub. L. 102–46, May 17, 1991, 105 Stat. 249; Pub. L. 102–486, title VII, § 726, Oct. 24, 1992, 106 Stat. 2921; Pub. L. 109–58, title XII, §§ 1253(b), 1291(b), Aug. 8, 2005, 119 Stat. 970, 984.)Editorial NotesReferences in Text

Section 79z–5a of title 15, referred to in par. (25), was repealed by Pub. L. 109–58, title XII, § 1263, Aug. 8, 2005, 119 Stat. 974.

Amendments

2005—Par. (17)(C). Pub. L. 109–58, § 1253(b)(1), amended subpar. (C) generally. Prior to amendment, subpar. (C) read as follows: “ ‘qualifying small power production facility’ means a small power production facility—

“(i) which the Commission determines, by rule, meets such requirements (including requirements respecting fuel use, fuel efficiency, and reliability) as the Commission may, by rule, prescribe; and

“(ii) which is owned by a person not primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities);”.

Par. (18)(B). Pub. L. 109–58, § 1253(b)(2), amended subpar. (B) generally. Prior to amendment, subpar. (B) read as follows: “ ‘qualifying cogeneration facility’ means a cogeneration facility which—

“(i) the Commission determines, by rule, meets such requirements (including requirements respecting minimum size, fuel use, and fuel efficiency) as the Commission may, by rule, prescribe; and

“(ii) is owned by a person not primarily engaged in the generation or sale of electric power (other than electric power solely from cogeneration facilities or small power production facilities);”.

Pars. (22), (23). Pub. L. 109–58, § 1291(b)(1), added pars. (22) and (23) and struck out former pars. (22) and (23) which read as follows:

“(22) ‘electric utility’ means any person or State agency (including any municipality) which sells electric energy; such term includes the Tennessee Valley Authority, but does not include any Federal power marketing agency.

“(23) Transmitting utility.—The term ‘transmitting utility’ means any electric utility, qualifying cogeneration facility, qualifying small power production facility, or Federal power marketing agency which owns or operates electric power transmission facilities which are used for the sale of electric energy at wholesale.”

Pars. (26) to (29). Pub. L. 109–58, § 1291(b)(2), added pars. (26) to (29).

1992—Par. (22). Pub. L. 102–486, § 726(b), inserted “(including any municipality)” after “State agency”.

Pars. (23) to (25). Pub. L. 102–486, § 726(a), added pars. (23) to (25).

1991—Par. (17)(E). Pub. L. 102–46 struck out “, and which would otherwise not qualify as a small power production facility because of the power production capacity limitation contained in subparagraph (A)(ii)” after “geothermal resources” in introductory provisions.

1990—Par. (17)(A). Pub. L. 101–575, § 3(a), inserted “a facility which is an eligible solar, wind, waste, or geothermal facility, or”.

Par. (17)(E). Pub. L. 101–575, § 3(b), added subpar. (E).

1980—Par. (17)(A)(i). Pub. L. 96–294 added applicability to geothermal resources.

1978—Pars. (17) to (22). Pub. L. 95–617 added pars. (17) to (22).

1935—Act Aug. 26, 1935, § 201, amended definitions of “reservations” and “corporations”, and inserted definitions of “person”, “licensee”, “commission”, “commissioner”, “State commission” and “security”.

Statutory Notes and Related SubsidiariesFERC Regulations

Pub. L. 101–575, § 4, Nov. 15, 1990, 104 Stat. 2834, provided that: “Unless the Federal Energy Regulatory Commission otherwise specifies, by rule after enactment of this Act [Nov. 15, 1990], any eligible solar, wind, waste, or geothermal facility (as defined in section 3(17)(E) of the Federal Power Act as amended by this Act [16 U.S.C. 796(17)(E)]), which is a qualifying small power production facility (as defined in subparagraph (C) of section 3(17) of the Federal Power Act as amended by this Act)—“(1) shall be considered a qualifying small power production facility for purposes of part 292 of title 18, Code of Federal Regulations, notwithstanding any size limitations contained in such part, and“(2) shall not be subject to the size limitation contained in section 292.601(b) of such part.”

State Authorities; Construction

Pub. L. 102–486, title VII, § 731, Oct. 24, 1992, 106 Stat. 2921, provided that: “Nothing in this title [enacting sections 824l, 824m, and 825o–1 of this title and former sections 79z–5a and 79z–5b of Title 15, Commerce and Trade, and amending this section, sections 824, 824j, 824k, 825n, 825o, and 2621 of this title, and provisions formerly set out as a note under former section 79k of Title 15] or in any amendment made by this title shall be construed as affecting or intending to affect, or in any way to interfere with, the authority of any State or local government relating to environmental protection or the siting of facilities.”

Termination of Federal Power Commission; Transfer of Functions

The Federal Power Commission was terminated, and its functions, personnel, property, funds, etc., were transferred to the Secretary of Energy (except for certain functions which were transferred to the Federal Energy Regulatory Commission) by sections 7151(b), 7171(a), 7172(a), 7291, and 7293 of Title 42, The Public Health and Welfare.

Abolition of Interstate Commerce Commission and Transfer of Functions

Interstate Commerce Commission abolished and functions of Commission transferred, except as otherwise provided in Pub. L. 104–88, to Surface Transportation Board effective Jan. 1, 1996, by section 1302 of Title 49, Transportation, and section 101 of Pub. L. 104–88, set out as a note under section 1301 of Title 49. References to Interstate Commerce Commission deemed to refer to Surface Transportation Board, a member or employee of the Board, or Secretary of Transportation, as appropriate, see section 205 of Pub. L. 104–88, set out as a note under section 1301 of Title 49.

The 20 cases that cite 16 U.S.C. § 796 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 796 11×cited by 39 cases
Where it cites § 796
“3117 codified at 16 U.S.C. §§ 796 (17)-(18), 824a-3, 824i, 824k (1994), was one of five statutes enacted in 1978 as part of the National Energy Act, in response to the nation’s fuel shortage.”
cites § 796 6×cited by 37 cases
Where it cites § 796
“[2] See the provisions of 16 U.S.C. § 796 , which state in pertinent part: "The words defined in this section shall have the following meanings for purposes of this chapter, to wit: (18)(A) `cogeneration facility' means a facility which produces — (i) electric energy, and (ii)…”
The case’s holding
A presumption of correctness accompanies a regulatory commission's findings in matters it frequently adjudicates and in which it possesses specialized expertise.
Later courts cite it for
“a presumption of correctness accompanies the commission's findings in matters it frequently adjudicates and in which it possesses expertise.” · 3 citing courts
3
GREENMohamad v. Palestinian Auth., 566 U.S. 449 (2012).
cites § 796 2×cited by 377 cases
Where it cites § 796
“§717a (“ ‘Person’ includes an individual or a corporation”); 16 U. S. C. §796 (“ ‘[P]erson’ means an individual or a corporation”); 8 U.”
The case’s holding
The term individual in the Torture Victim Protection Act refers only to natural persons rather than corporations or other legal entities.
Later courts cite it for
“we generally seek to respect congress' decision to use different terms to describe different categories of people or things.” · 11 citing courts
cites § 796 6×cited by 276 cases
Where it cites § 796
“By § 3 (2) of the Federal Power Act, 16 U. S. C. § 796 (2), Congress has provided: "SEC.”
The case’s holding
A general statute applying to all persons includes Indian tribes and their property interests held in fee simple.
Later courts cite it for
“a general statute in terms applying to all persons includes indians and their property interests.” · 41 citing courts
5
GREENSolar Energy Indus. Ass'n v. FERC, 59 F.4th 1287 (D.C. Cir. 2023).
cites § 796 9×cited by 4 cases
Where it cites § 796
“But 7 the statute does not state whether the relevant capacity is that of the individual subcomponent generating DC power, i.”
Later courts cite it for
“to send . . . to an intended target or destination.” · 2 citing courts
cites § 796 3×cited by 227 cases
Where it cites § 796
“By definition a small power production facility has a production capacity of no more than 80 megawatts, 16 U. S. C. § 796 (17)(A)(ii) (1976 ed., Supp.”
The case’s holding
A court will uphold an agency decision even if it is not the only reasonable outcome (explaining that the agency's decision need not be the only reasonable one).
Later courts cite it for
“a qualifying facility and a utility may negotiate a contract setting a price that is lower than a full avoided cost rate.” · 3 citing courts
cites § 796 3×cited by 57 cases
Where it cites § 796
“which either in their natural or improved condition notwithstanding interruptions between the navigable parts of such streams or waters by falls, shallows, or rapids compelling land carriage, are used or suitable for use for the transportation of persons or property in…”
The case’s holding
An organization lacks Article III standing if it alleges only the expenditure of resources on advocacy rather than a perceptible impairment of its ability to provide services.
Later courts cite it for
“an organization must allege that the defendant's conduct perceptibly impaired the organization's ability to provide services.” · 11 citing courts
8
GREENCity of Tacoma v. Taxpayers of Tacoma, 357 U.S. 320 (1958).
cites § 796 4×cited by 318 cases
Where it cites § 796
“1063 , 16 U. S. C. § 796 (7). By a Washington statute all cities and towns of that State are made legally competent to "construct, condemn and purchase, purchase, acquire, add to, maintain, and operate works, plants, and facilities for the purpose of furnishing the city or town…”
The case’s holding
A final judgment in a proceeding where the state represents the public interest bars subsequent collateral attacks by citizens regarding the same subject matter.
Later courts cite it for
“prescribed the specific, complete and exclusive mode for judicial review of the commission's orders.” · 12 citing courts
cites § 796 2×cited by 445 cases
Where it cites § 796
“16 U. S. C. § 796 (18)(A). A "small power production facility" is one that has a production capacity of no more than 80 megawatts and uses biomass, waste, or renewable resources (such as wind, water, or solar energy) to produce electric power.”
The case’s holding
Congress may use its commerce power to preempt state regulation of private utilities and condition state involvement in a pre-emptible field on compliance with federal standards.
Later courts cite it for
“regulation of land use is perhaps the quintessential state activity.” · 15 citing courts
cites § 796 2×cited by 390 cases
Where it cites § 796
“Congress directed FERC to promulgate rules and regulations governing the terms of such purchases and sales, and state agencies such as the Pennsylvania Public *411 Utility Commission (“PUC”) are empowered to regulate the facilities and approve the contracts covered by PURPA.”
The case’s holding
A supplier cannot establish antitrust injury by alleging that a purchaser's refusal to buy products prevents competition in a market where the supplier is contractually or legally prohibited from competing.
Later courts cite it for
“unsupported conclusions and unwarranted inferences,” · 31 citing courts
11
REDChemehuevi Tribe of Indians v. Fed. Power Comm'n, 489 F.2d 1207 (D.C. Cir. 1973).
cites § 796 10×cited by 25 cases
Vacated by the U.S. Supreme Court in this case: Chemehuevi Tribe of Indians v. Federal Power Commission (1975).
Where it cites § 796
“§ 797 (e) (1970), 6 because the utilities are constructing and operating “project works,” see 16 U.S.C. §§ 796 (11), (12) (1970), 7 for the development, transmission, and utilization of electric power across and along “navigable waters,” see 16 U.”
Later courts cite it for
“nonfederal construction and operation of water power projects on navigable waters, public lands, or reservations.” · 2 citing courts
12
GREENConsol. Edison Co. v. Pub. Serv. Comm'n, 472 N.E.2d 981 (N.Y. 1984).
cites § 796 4×cited by 51 cases
Where it cites § 796
“A “cogeneration facility” is one that produces both electric energy and steam or some other form of useful energy, such as heat (see 16 USC § 796 [18] [A]). A “small power production facility” is one that produces electric power from biomass, waste, renewable resources such as…”
The case’s holding
The Federal Power Act preempts state regulation of purely state qualifying facilities, but PURPA does not prevent states from requiring utilities to purchase power from federal qualifying facilities.
Later courts cite it for
“not eligible for this federally authorized exemption because they are not covered by purpa.” · 2 citing courts
13
GREENUnited States v. S. California Edison Co., 300 F. Supp. 2d 964 (E.D. Cal. 2004).
cites § 796 2×cited by 74 cases
Where it cites § 796
“” 16 U.S.C. § 796 (2). The United States, acting through the condition-imposing department, the Secretary of Agriculture’s Forest Servicé, is the proper party.”
The case’s holding
A court may take judicial notice of the existence and authenticity of public records but not of the veracity or validity of the arguments and disputed facts contained therein.
Later courts cite it for
“while the 21 authenticity and existence of a particular order, motion, pleading or judicial proceeding, 22 which is a matter of public record, is judicially noticeable, veracity and validity of its 23 contents . . . are not.” · 10 citing courts
cites § 796 5×cited by 10 cases
Later courts cite it for
“must reverse an agency action that is 'arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 2 citing courts
cites § 796 2×cited by 156 cases
Where it cites § 796
“16 U. S. C. §796 (2). 25 Indeed, in another provision of the Act, Congress provided that the term “project” includes “all water-rights .”
The case’s holding
Statutory language is conclusive unless Congress expresses a contrary intention through its chosen words (interpreting the word shall as mandatory).
Later courts cite it for
“all aspects of indian sovereignty are subject to defeasance by congress.” · 4 citing courts
16
GREENSierra Pac. Power Co. v. Fed. Energy Regulatory Comm'n, 681 F.2d 1134 (9th Cir. 1982).
cites § 796 6×cited by 14 cases
Where it cites § 796
“TRASK, Circuit Judge: Petitioner, Sierra Pacific Power Company (Sierra), challenges a ruling made by respondent, the Federal Energy Regulatory Commission (Commission or FERC), which found the Truckee River to be a navigable water of the United States as defined by section 3(8)…”
17
GREENExelon Wind 1, L.L.C. v. Donna Nelson, 766 F.3d 380 (5th Cir. 2014).
cites § 796 2×cited by 37 cases
The case’s holding
An agency is not entitled to deference when it offers an interpretation of a regulation that is unambiguously foreclosed by the regulatory text.
Later courts cite it for
“an agency is not entitled to deference when it offers up an interpretation of the regulation that we have already said to be unambiguously foreclosed by the regulatory text.” · 2 citing courts
18
GREENFed. Power Comm'n v. Oregon, 349 U.S. 435 (1955).
cites § 796 4×cited by 73 cases
Where it cites § 796
“838 , 16 U. S. C. § 796 (8). We do not pass either upon that question or upon the relationship to interstate commerce of the proposed use of the waters of the river.”
The case’s holding
The federal government possesses exclusive authority to regulate land reserved from the public domain under the Property Clause of the Constitution.
Later courts cite it for
“in relation to public lands and reservations of the united states springs from the property clause” · 1 citing court
19
GREENUnited States v. City of Tacoma, 332 F.3d 574 (9th Cir. 2003).
cites § 796 1×cited by 175 cases
Where it cites § 796
“The Federal Power Act defines reservations as "national forests, tribal lands embraced within Indian reservations, military reservations, and other land and interests in lands owned by the United States, and withdrawn, reserved or withheld from private appropriation and disposal…”
The case’s holding
The United States is an indispensable party to condemnation proceedings involving trust allotments, and state courts lack jurisdiction to adjudicate such proceedings without joining the United States.
Later courts cite it for
“determine, viewing the evidence in the light most favorable to the nonmoving party, whether there are any genuine issues of material fact and whether the district court correctly applied substantive law.” · 14 citing courts
20
GREENCity of Vanceburg v. Fed. Energy Regulatory Comm'n, 571 F.2d 630 (D.C. Cir. 1978).
cites § 796 3×cited by 35 cases
Where it cites § 796
“16 U.S.C. § 796 (3): (3) “corporation” means any corporation, joint-stock company, partnership, association, business trust, organized group of persons, whether incorporated or not, or a receiver or receivers, trustee or trustees of any of the foregoing.”
The case’s holding
The Commission may base dam-use charges on the actual value of the benefit received by a licensee, including real tax savings.
Later courts cite it for
“as the supreme court has stated, it is the purpose of this provision to give the commission notice of its alleged errors so that it may have the opportunity to correct them.” · 2 citing courts

Show all 263 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
192819762025

One bar per 2 years. Tallest: 20 cases in 1994–1995. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.579th Cir.24Pa. Commw. Ct.16SCOTUS112d Cir.10Cal. Ct. App.91st Cir.86th Cir.7

The 8 courts with the most citing cases, of 71 courts in all.

By subsection
(2)1 case
(8)2 cases
Montana Power Co. v. Fed. Power Comm'n, 185 F.2d 491 (D.C. Cir. 1950).
Georgia Power Co. v. Fed. Power Comm'n, 152 F.2d 908 (5th Cir. 1946).
(11)1 case
(13)1 case
Alabama Power Co. v. McNinch, 94 F.2d 601 (D.C. Cir. 1937).
(15)1 case
(18)(A)1 case
Grays Ferry Cogeneration P'ship v. PECO Energy Co., 998 F. Supp. 542 (E.D. Pa. 1998).

Show all 263 citing cases (list view) →

Enactment and amendments
(June 10, 1920, ch. 285, pt. I, § 3, 41 Stat. 1063; renumbered pt. I and amended, Aug. 26, 1935, ch. 687, title II, §§ 201, 212, 49 Stat. 838, 847; Pub. L. 95–617, title II, § 201, Nov. 9, 1978, 92 Stat. 3134; Pub. L. 96–294, title VI, § 643(a)(1), June 30, 1980, 94 Stat. 770; Pub. L. 101–575, § 3, Nov. 15, 1990, 104 Stat. 2834; Pub. L. 102–46, May 17, 1991, 105 Stat. 249; Pub. L. 102–486, title VII, § 726, Oct. 24, 1992, 106 Stat. 2921; Pub. L. 109–58, title XII, §§ 1253(b), 1291(b), Aug. 8, 2005, 119 Stat. 970, 984.)
Amendment years (notes): 2005, 1992, 1991, 1990, 1980, 1978, 1935
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com