Declaration of policy; application of subchapter

Edition and currency
U.S. Code current through Pub. L. 119-102 (OLRC release point). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTU.S. Code current through Pub. L. 119-102 (OLRC release point) cited 1939–2026 522citing cases
At a glance

Courts have cited this section in 522 opinions since 1939, 74 of them in the last five years. The most litigated part is subsection (a) (3 cases).

(a) Federal regulation of transmission and sale of electric energy

It is declared that the business of transmitting and selling electric energy for ultimate distribution to the public is affected with a public interest, and that Federal regulation of matters relating to generation to the extent provided in this subchapter and subchapter III of this chapter and of that part of such business which consists of the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce is necessary in the public interest, such Federal regulation, however, to extend only to those matters which are not subject to regulation by the States.

(b) Use or sale of electric energy in interstate commerce(1) The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but except as provided in paragraph (2) shall not apply to any other sale of electric energy or deprive a State or State commission of its lawful authority now exercised over the exportation of hydroelectric energy which is transmitted across a State line. The Commission shall have jurisdiction over all facilities for such transmission or sale of electric energy, but shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or over facilities for the transmission of electric energy consumed wholly by the transmitter.(2) Notwithstanding subsection (f), the provisions of sections 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, and 824v of this title shall apply to the entities described in such provisions, and such entities shall be subject to the jurisdiction of the Commission for purposes of carrying out such provisions and for purposes of applying the enforcement authorities of this chapter with respect to such provisions. Compliance with any order or rule of the Commission under the provisions of section 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title, shall not make an electric utility or other entity subject to the jurisdiction of the Commission for any purposes other than the purposes specified in the preceding sentence.(c) Electric energy in interstate commerce

For the purpose of this subchapter, electric energy shall be held to be transmitted in interstate commerce if transmitted from a State and consumed at any point outside thereof; but only insofar as such transmission takes place within the United States.

(d) “Sale of electric energy at wholesale” defined

The term “sale of electric energy at wholesale” when used in this subchapter, means a sale of electric energy to any person for resale.

(e) “Public utility” defined

The term “public utility” when used in this subchapter and subchapter III of this chapter means any person who owns or operates facilities subject to the jurisdiction of the Commission under this subchapter (other than facilities subject to such jurisdiction solely by reason of section 824e(e), 824e(f),11 So in original. Section 824e of this title does not contain a subsec. (f). 824i, 824j, 824j–1, 824k, 824o, 824o–1, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title).

(f) United States, State, political subdivision of a State, or agency or instrumentality thereof exempt

No provision in this subchapter shall apply to, or be deemed to include, the United States, a State or any political subdivision of a State, an electric cooperative that receives financing under the Rural Electrification Act of 1936 (7 U.S.C. 901 et seq.) or that sells less than 4,000,000 megawatt hours of electricity per year, or any agency, authority, or instrumentality of any one or more of the foregoing, or any corporation which is wholly owned, directly or indirectly, by any one or more of the foregoing, or any officer, agent, or employee of any of the foregoing acting as such in the course of his official duty, unless such provision makes specific reference thereto.

(g) Books and records(1) Upon written order of a State commission, a State commission may examine the books, accounts, memoranda, contracts, and records of—(A) an electric utility company subject to its regulatory authority under State law,(B) any exempt wholesale generator selling energy at wholesale to such electric utility, and(C) any electric utility company, or holding company thereof, which is an associate company or affiliate of an exempt wholesale generator which sells electric energy to an electric utility company referred to in subparagraph (A),wherever located, if such examination is required for the effective discharge of the State commission’s regulatory responsibilities affecting the provision of electric service.(2) Where a State commission issues an order pursuant to paragraph (1), the State commission shall not publicly disclose trade secrets or sensitive commercial information.(3) Any United States district court located in the State in which the State commission referred to in paragraph (1) is located shall have jurisdiction to enforce compliance with this subsection.(4) Nothing in this section shall—(A) preempt applicable State law concerning the provision of records and other information; or(B) in any way limit rights to obtain records and other information under Federal law, contracts, or otherwise.(5) As used in this subsection the terms “affiliate”, “associate company”, “electric utility company”, “holding company”, “subsidiary company”, and “exempt wholesale generator” shall have the same meaning as when used in the Public Utility Holding Company Act of 2005 [42 U.S.C. 16451 et seq.].(June 10, 1920, ch. 285, pt. II, § 201, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 847; amended Pub. L. 95–617, title II, § 204(b), Nov. 9, 1978, 92 Stat. 3140; Pub. L. 102–486, title VII, § 714, Oct. 24, 1992, 106 Stat. 2911; Pub. L. 109–58, title XII, §§ 1277(b)(1), 1291(c), 1295(a), Aug. 8, 2005, 119 Stat. 978, 985; Pub. L. 114–94, div. F, § 61003(b), Dec. 4, 2015, 129 Stat. 1778.)Editorial NotesReferences in Text

The Rural Electrification Act of 1936, referred to in subsec. (f), is act May 20, 1936, ch. 432, 49 Stat. 1363, which is classified generally to chapter 31 (§ 901 et seq.) of Title 7, Agriculture. For complete classification of this Act to the Code, see section 901 of Title 7 and Tables.

The Public Utility Holding Company Act of 2005, referred to in subsec. (g)(5), is subtitle F of title XII of Pub. L. 109–58, Aug. 8, 2005, 119 Stat. 972, which is classified principally to part D (§ 16451 et seq.) of subchapter XII of chapter 149 of Title 42, The Public Health and Welfare. For complete classification of this Act to the Code, see Short Title note set out under section 15801 of Title 42 and Tables.

Amendments

2015—Subsec. (b)(2). Pub. L. 114–94, § 61003(b)(1), inserted “824o–1,” after “824o,” in two places.

Subsec. (e). Pub. L. 114–94, § 61003(b)(2), inserted “824o–1,” after “824o,”.

2005—Subsec. (b)(2). Pub. L. 109–58, § 1295(a)(1), substituted “Notwithstanding subsection (f), the provisions of sections 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824p, 824q, 824r, 824s, 824t, 824u, and 824v of this title” for “The provisions of sections 824i, 824j, and 824k of this title” and “Compliance with any order or rule of the Commission under the provisions of section 824b(a)(2), 824e(e), 824i, 824j, 824j–1, 824k, 824o, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title” for “Compliance with any order of the Commission under the provisions of section 824i or 824j of this title”.

Subsec. (e). Pub. L. 109–58, § 1295(a)(2), substituted “section 824e(e), 824e(f), 824i, 824j, 824j–1, 824k, 824o, 824p, 824q, 824r, 824s, 824t, 824u, or 824v of this title” for “section 824i, 824j, or 824k of this title”.

Subsec. (f). Pub. L. 109–58, § 1291(c), which directed amendment of subsec. (f) by substituting “political subdivision of a State, an electric cooperative that receives financing under the Rural Electrification Act of 1936 (7 U.S.C. 901 et seq.) or that sells less than 4,000,000 megawatt hours of electricity per year,” for “political subdivision of a state,”, was executed by making the substitution for “political subdivision of a State,” to reflect the probable intent of Congress.

Subsec. (g)(5). Pub. L. 109–58, § 1277(b)(1), substituted “2005” for “1935”.

1992—Subsec. (g). Pub. L. 102–486 added subsec. (g).

1978—Subsec. (b). Pub. L. 95–617, § 204(b)(1), designated existing provisions as par. (1), inserted “except as provided in paragraph (2)” after “in interstate commerce, but”, and added par. (2).

Subsec. (e). Pub. L. 95–617, § 204(b)(2), inserted “(other than facilities subject to such jurisdiction solely by reason of section 824i, 824j, or 824k of this title)” after “under this subchapter”.

Statutory Notes and Related SubsidiariesEffective Date of 2005 Amendment

Amendment by section 1277(b)(1) of Pub. L. 109–58 effective 6 months after Aug. 8, 2005, with provisions relating to effect of compliance with certain regulations approved and made effective prior to such date, see section 1274 of Pub. L. 109–58, set out as an Effective Date note under section 16451 of Title 42, The Public Health and Welfare.

State Authorities; Construction

Nothing in amendment by Pub. L. 102–486 to be construed as affecting or intending to affect, or in any way to interfere with, authority of any State or local government relating to environmental protection or siting of facilities, see section 731 of Pub. L. 102–486, set out as a note under section 796 of this title.

Prior Actions; Effect On Other Authorities

Pub. L. 95–617, title II, § 214, Nov. 9, 1978, 92 Stat. 3149, provided that:“(a)Prior Actions.—No provision of this title [enacting sections 823a, 824i to 824k, 824a–1 to 824a–3 and 825q–1 of this title, amending sections 796, 824, 824a, 824d, and 825d of this title and enacting provisions set out as notes under sections 824a, 824d, and 825d of this title] or of any amendment made by this title shall apply to, or affect, any action taken by the Commission [Federal Energy Regulatory Commission] before the date of the enactment of this Act [Nov. 9, 1978].“(b)Other Authorities.—No provision of this title [enacting sections 823a, 824i to 824k, 824a–1 to 824a–3 and 825q–1 of this title, amending sections 796, 824, 824a, 824d, and 825d of this title and enacting provisions set out as notes under sections 824a, 824d, and 825d of this title] or of any amendment made by this title shall limit, impair or otherwise affect any authority of the Commission or any other agency or instrumentality of the United States under any other provision of law except as specifically provided in this title.”

The 20 cases that cite 16 U.S.C. § 824 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 824 32×cited by 236 cases
Where it cites § 824
“847 , and as amended, 16 U. S. C. § 824 et seq., enacted in 1935.”
The case’s holding
The Federal Power Act grants an agency jurisdiction over interstate electric energy transmission regardless of whether the transmission is associated with a wholesale or retail transaction.
Later courts cite it for
“the sale of electric energy at wholesale in interstate commerce.” · 13 citing courts
cites § 824 6×cited by 180 cases
Where it cites § 824
“The statute provides that "[a]ll rates and charges made, demanded, or received by any public utility for or in connection with" interstate transmissions or wholesale sales-as well as "all rules and regulations affecting or pertaining to such rates or charges"-must be "just and…”
The case’s holding
The Federal Energy Regulatory Commission has authority to regulate the compensation of demand response commitments by wholesale market operators.
Later courts cite it for
“a court is not to ask whether a regulatory decision is the best one possible or even whether it is better than the alternatives.” · 17 citing courts
3
GREENCoal. for Competitive Elec. v. Zibelman, 906 F.3d 41 (2d Cir. 2018).
cites § 824 5×subsections: (a)cited by 71 cases
Where it cites § 824
“16 U.S.C. § 824 (b)(1). FERC regulates electricity sales at wholesale, ensuring "rates and charges made, demanded, or received .”
The case’s holding
A state program exerting downward pressure on wholesale electricity rates is insufficient to state a claim for field preemption under the Federal Power Act (downward pressure on wholesale electricity rates).
Later courts cite it for
“construe the complaint liberally, accept all factual allegations as true, and draw all reasonable inferences in the plaintiff's favor.” · 30 citing courts
4
GREENAllco Fin. Ltd. v. Robert J. Klee, 861 F.3d 82 (2d Cir. 2017).
cites § 824 5×cited by 65 cases
Where it cites § 824
“See 16 U.S.C. § 824 (b)(1); Hughes v. Talen Energy Mktg.”
The case’s holding
A state renewable energy procurement program is not preempted by the Federal Power Act if the resulting contracts remain subject to utility discretion and federal regulatory review.
Later courts cite it for
“determine the economic wisdom and the health and safety effects” · 2 citing courts
cites § 824 20×cited by 11 cases
Reversed by Fed. Energy Regulatory Comm'n v. Elec. Power Supply Ass'n (2016): the U.S. Supreme Court's own opinion in this case.
Where it cites § 824
“” 16 U.S.C. § 824 (b)(1) (emphasis added). Thus, “FERC’s jurisdiction over the sale of electricity has been specifically confined to the wholesale market.”
The case’s holding
FERC may regulate practices affecting wholesale electricity rates, but may not directly regulate retail electricity demand, which the Federal Power Act reserves to the states.
Later courts cite it for
“direct effect . . . on wholesale electricity rates squarely within ferc's jurisdiction.” · 3 citing courts
cites § 824 4×cited by 1,638 cases
Where it cites § 824
“Not surprisingly, the cost of the electricity produced by the reactor greatly exceeded that of power generated by Middle South's conventional facilities.”
The case’s holding
Ratemaking proceedings are legislative rather than judicial in nature and do not trigger Younger abstention.
Later courts cite it for
“while burford is concerned with protecting complex state administrative processes from undue federal interference, it does not require abstention whenever there exists such a process, or even in all cases where there is a 'potential for conflict' with state regulatory law or policy.” · 96 citing courts
7
cites § 824 4×cited by 1,301 cases
The case’s holding
Congress may use its commerce power to impose general employment regulations on states and their political subdivisions.
Later courts cite it for
“state sovereign interests ... are more properly protected by procedural safeguards inherent in the structure of the federal system than by judicially created limitations on federal power.” · 18 citing courts
cites § 824 6×cited by 289 cases
Where it cites § 824
“838 , 847, as amended, 16 U. S. C. § 824 (b) (1976 ed., Supp. V); FPC v.”
The case’s holding
The Rural Electrification Act does not preempt state regulation of rates for rural electric cooperatives (holding that the act does not preempt state rate regulation).
Later courts cite it for
“the regulation of utilities is one of the most important of the functions traditionally associated with the police power of the states.” · 22 citing courts
cites § 824 6×cited by 247 cases
Where it cites § 824
“See 16 U. S. C. §§ 824 (a) and (b)(1); Arkansas Electric Cooperative Corp.”
The case’s holding
Federal regulation of wholesale electricity rates preempts state proceedings that affect interstate rates, even if those state actions impact retail prices.
Later courts cite it for
“congress has drawn a bright line between state and federal authority in the setting of wholesale rates and in the regulation of agreements that affect wholesale rates. states may not regulate in areas where ferc has properly exercised its jurisdiction to determine just and reasonable wholesale rates or to insure that agreements affecting wholesale rates are reasonable.” · 8 citing courts
cites § 824 16×cited by 10 cases
Where it cites § 824
“While the North Carolina Public Utilities Act grants NCUC jurisdiction over intrastate sales and interstate retail sales of electric energy, as well as over the quality and reliability of local electric serv *523 ice, the Federal Power Act granted the Federal Power Commission…”
Later courts cite it for
“a reviewing court confronting this question begins its analysis with a presumption against federal preemption.” · 3 citing courts
11
GREENMetro. Edison Co. v. Pennsylvania Pub. Util. Comm'n, 767 F.3d 335 (3d Cir. 2014).
cites § 824 7×cited by 46 cases
Where it cites § 824
“As it stands today, the FPA grants FERC jurisdiction over “the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce,” 16 U.S.C. § 824 (a), and requires “[a]ll rates and charges … subject to the jurisdiction of the…”
The case’s holding
Issue preclusion bars federal claims identical to issues squarely decided in a prior state proceeding where the party had a full and fair opportunity to litigate, applying the state's preclusion law.
cites § 824 4×cited by 169 cases
Where it cites § 824
“See 16 U. S. C. §824 et seq. Modeled on the Interstate Commerce Act, the FPA requires regulated utilities to file compilations of their rate schedules, or “tariffs,” with the Commission, and to provide service to electricity purchasers on the terms and prices there set forth.”
The case’s holding
The commission must presume contract rates are just and reasonable unless it finds that the rates seriously harm the public interest.
Later courts cite it for
“that it provided a different rationale for the necessary result is no cause for upsetting its ruling” · 10 citing courts
13
GREENHughes v. Talen Energy Mktg., LLC, 578 U.S. 150 (2016).
cites § 824 3×cited by 86 cases
Where it cites § 824
“Exercising its exclusive authority over interstate wholesale sales, see 16 U. S. C. §824 (b)(1), FERC has approved PJM’s capacity auction as the sole ratesetting mechanism for capacity sales to PJM, and has deemed the clearing price per se just and reasonable.”
The case’s holding
Federal law preempts state programs that effectively set interstate wholesale electricity rates by disregarding the rates established by FERC.
Later courts cite it for
“put simply, federal law preempts contrary state law.” · 14 citing courts
cites § 824 4×cited by 161 cases
Where it cites § 824
“See 16 U.S.C. §§ 824 (b)(1), 824d(a), 824e(a); AEP Tex.”
The case’s holding
A state law claim does not create federal question jurisdiction unless it necessarily raises a disputed and substantial federal issue.
Later courts cite it for
“all doubts about federal jurisdiction must be resolved in favor of remand.” · 10 citing courts
15
GREENWyoming v. Oklahoma, 502 U.S. 437 (1992).
cites § 824 4×cited by 417 cases
Where it cites § 824
“Oklahoma argues more seriously that the "saving clause" of the Federal Power Act, 16 U. S. C. § 824 (b)(1), [13] which reserves to the States the regulation of local retail electric rates, makes permissible the Act's discriminatory impact on the movement of Wyoming coal in…”
The case’s holding
A state statute that discriminates against interstate commerce is unconstitutional unless the discrimination is demonstrably justified by a valid factor unrelated to economic protectionism.
Later courts cite it for
“the volume of commerce affected measures only the extent of the discrimination; it is of no relevance to the determination whether a state has discriminated against interstate commerce.” · 19 citing courts
16
GREENState of North Dakota v. Beverly Heydinger, 825 F.3d 912 (8th Cir. 2016).
cites § 824 6×cited by 15 cases
Where it cites § 824
“” 16 U.S.C. § 824 (b)(1). The Act left to the States most matters they had traditionally regulated, including local electric utility rates and the siting of power plants, see § 824(a) and (b), subject to limits imposed by the Commerce Clause.”
Later courts cite it for
“miso controls over 49,000 miles of transmission lines, a grid that spans fifteen states . . . and parts of canada.” · 2 citing courts
17
GREENDuke Energy Trading & Mktg., L.L.C. v. Gray Davis, 267 F.3d 1042 (9th Cir. 2001).
cites § 824 4×cited by 107 cases
Where it cites § 824
“” 16 U.S.C. § 824 (b), (d). FERC’s exclusive jurisdiction extends over all facilities for such transmission or sale of electric energy.”
The case’s holding
State executive orders that nullify the security and default mitigation provisions of FERC-approved wholesale electricity rate schedules are preempted by the Supremacy Clause.
Later courts cite it for
“once the notice of dismissal has been filed, the district court loses jurisdiction over the dismissed claims and may not address the merits of such claims or issue further orders pertaining to them.” · 11 citing courts
cites § 824 8×cited by 163 cases
Where it cites § 824
“847 , 16 U. S. C. § 824 (b), grants the Federal Power Commission jurisdiction over "the transmission of electric energy in interstate commerce and .”
The case’s holding
Courts must defer to an administrative agency's factual findings on technical or scientific matters if those findings are supported by substantial evidence.
Later courts cite it for
“particularly when we consider a purely factual question within the area of competence of an administrative agency created by congress, and when resolution of that question depends on 'engineering and scientific' considerations, we recognize the relevant agency's technical expertise and experience, and defer to its analysis unless it is without substantial basis in fact.” · 8 citing courts
cites § 824 4×cited by 69 cases
Where it cites § 824
“Upon enacting the FPA, Congress determined that federal regulation of interstate electric energy transmission and its sale at wholesale is “necessary in the public interest,” FPA § 201(a), 16 U.S.C. § 824 (a), and vested the Commission with “jurisdiction over all facilities for…”
The case’s holding
A regulatory order based on market competition theory is reasonable if it determines that rights of first refusal would lead to unjust or unreasonable practices (Order 1000).
Later courts cite it for
“opportunities for nonincumbents, such developers must still comply with state law.” · 2 citing courts
20
GREENNat'l Assoc. of Regulatory v. FERC, 964 F.3d 1177 (D.C. Cir. 2020).
cites § 824 6×cited by 9 cases
Where it cites § 824
“760, 766 (2016) (quoting 16 U.S.C. §§ 824 (b), 824e(a)), along with “jurisdiction over all facilities for such transmission or sale of electric energy,” 16 U.”
Later courts cite it for
“a state's regulations aimed directly at matters in ferc's jurisdiction cannot be sustained when they threaten the achievement of the comprehensive scheme of federal regulation.” · 2 citing courts

Show all 522 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
193819822026

One bar per 2 years. Tallest: 45 cases in 2014–2015. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
D.C. Cir.1309th Cir.55SCOTUS345th Cir.248th Cir.211st Cir.197th Cir.182d Cir.17

The 8 courts with the most citing cases, of 91 courts in all.

By subsection
(a)3 cases
Coal. for Competitive Elec. v. Zibelman, 906 F.3d 41 (2d Cir. 2018).“16 U.S.C. § 824 (b)(1). FERC regulates electricity sales at wholesale, ensuring "rates and charges made, demanded, or received .”
Coalition for Competitive Elec. v. Zibelman, No. 17-2654-cv (2d Cir. Sept. 27, 2018).
(b)3 cases
Pennsylvania Water & Power Co. v. Consol. Gas, 184 F.2d 552 (4th Cir. 1950).
(b)(2)1 case
Bpa v. Ferc, No. 02-70262 (9th Cir. Sept. 6, 2005).
(d)1 case
Commonwealth Elec. Co. v. Dep't of Pub. Utils., 491 N.E.2d 1035 (Mass. 1986).
(e)1 case
Florida Power & Light Co. v. Fed. Power Comm'n, 430 F.2d 1377 (5th Cir. 1970).
(f)1 case
New England Power Co. v. Fed. Power Comm'n, 349 F.2d 258 (1st Cir. 1965).

Show all 522 citing cases (list view) →

Enactment and amendments
(June 10, 1920, ch. 285, pt. II, § 201, as added Aug. 26, 1935, ch. 687, title II, § 213, 49 Stat. 847; amended Pub. L. 95–617, title II, § 204(b), Nov. 9, 1978, 92 Stat. 3140; Pub. L. 102–486, title VII, § 714, Oct. 24, 1992, 106 Stat. 2911; Pub. L. 109–58, title XII, §§ 1277(b)(1), 1291(c), 1295(a), Aug. 8, 2005, 119 Stat. 978, 985; Pub. L. 114–94, div. F, § 61003(b), Dec. 4, 2015, 129 Stat. 1778.)
Amendment years (notes): 2015, 2005, 1992, 1978
Versions

Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.

U.S.C. Home  |  Search U.S. Code  |  Search cases for this section  |  syfert.com