30 U.S.C. § 1256 (2026)
Permits
Edition and currency
Other sources
Courts have cited this section in 64 opinions since 1978, 1 of them in the last five years. The most litigated part is subsection (a) (1 case).
No later than eight months from the date on which a State program is approved by the Secretary, pursuant to section 1253 of this title, or no later than eight months from the date on which the Secretary has promulgated a Federal program for a State not having a State program pursuant to section 1254 of this title, no person shall engage in or carry out on lands within a State any surface coal mining operations unless such person has first obtained a permit issued by such State pursuant to an approved State program or by the Secretary pursuant to a Federal program; except a person conducting surface coal mining operations under a permit from the State regulatory authority, issued in accordance with the provisions of section 1252 of this title, may conduct such operations beyond such period if an application for a permit has been filed in accordance with the provisions of this chapter, but the initial administrative decision has not been rendered.
All permits issued pursuant to the requirements of this chapter shall be issued for a term not to exceed five years: Provided, That if the applicant demonstrates that a specified longer term is reasonably needed to allow the applicant to obtain necessary financing for equipment and the opening of the operation and if the application is full and complete for such specified longer term, the regulatory authority may grant a permit for such longer term. A successor in interest to a permittee who applies for a new permit within thirty days of succeeding to such interest and who is able to obtain the bond coverage of the original permittee may continue surface coal mining and reclamation operations according to the approved mining and reclamation plan of the original permittee until such successor’s application is granted or denied.
A permit shall terminate if the permittee has not commenced the surface coal mining operations covered by such permit within three years of the issuance of the permit: Provided, That the regulatory authority may grant reasonable extensions of time upon a showing that such extensions are necessary by reason of litigation precluding such commencement or threatening substantial economic loss to the permittee, or by reason of conditions beyond the control and without the fault or negligence of the permittee: Provided further, That in the case of a coal lease issued under the Federal Mineral Leasing Act, as amended [30 U.S.C. 181 et seq.], extensions of time may not extend beyond the period allowed for diligent development in accordance with section 7 of that Act [30 U.S.C. 207]: Provided further, That with respect to coal to be mined for use in a synthetic fuel facility or specific major electric generating facility, the permittee shall be deemed to have commenced surface mining operations at such time as the construction of the synthetic fuel or generating facility is initiated.
The Federal Mineral Leasing Act, as amended, referred to in subsec. (c), probably means act Feb. 25, 1920, ch. 85, 41 Stat. 437, known as the Mineral Leasing Act, which is classified generally to chapter 3A (§ 181 et seq.) of this title. For complete classification of this Act to the Code, see Short Title note set out under section 181 of this title and Tables.
- Where it cites § 1256
- “[6] 30 U.S.C. § 1256 (a) (2000). In West Virginia, the federally approved regulatory authority is the Department of Environmental Protection ("WVDEP").”
- The case’s holding
- An agency's interpretation of its own regulations is entitled to deference unless it is plainly erroneous or inconsistent with the regulation.
- Later courts cite it for
- “settlement agreements operate on contract principles, . . . the preclusive effect of a settlement agreement should be measured by the intent of the parties.” · 103 citing courts
- The case’s holding
- Congress may regulate intrastate activities under the Commerce Clause if there is a rational basis for finding that the activity substantially affects interstate commerce.
- Later courts cite it for
- “summary administrative action may be justified in emergency situations.” · 18 citing courts
- Where it cites § 1256
- “[2] Among the remaining provisions of the federal Act apparently binding on the anthracite industry, along with the federal regulations related thereto, are: Permit requirements (Section 506, 30 U.S.C. § 1256 ), application requirements (Section 507, 30 U.”
- The case’s holding
- A pre-enforcement challenge to agency regulations is justiciable if the regulations have a direct and immediate effect on the regulated industry.
- Later courts cite it for
- “where the effect of the challenged regulations upon the industry regulated is direct and immediate, the hardship thus presented suffices to establish the justiciability of the challenge in advance of enforcement.” · 13 citing courts
- Where it cites § 1256
- “See 30 U.S.C. § 1256 . The Department of the Interior’s Office of Surface Mining Reclamation and Enforcement oversees Department of Interior-approved state programs for issuing those permits.”
- The case’s holding
- An agency action explaining how it will exercise enforcement or permitting discretion is a general statement of policy rather than a final agency action subject to judicial review.
- Later courts cite it for
- “the most important factor concerns the actual legal effect (or lack thereof) of the agency action in question on regulated entities.” · 26 citing courts
- Where it cites § 1256
- “30 U.S.C. § 1256 . Any permit issued under SMCRA must comply with certain environmental performance standards.”
- The case’s holding
- A court maintains jurisdiction over a takings claim even if the government action is subject to legal challenge on other grounds.
- Later courts cite it for
- “an uncompensated taking and an unlawful government action constitute 'two separate wrongs that give rise to two separate causes of action.” · 7 citing courts
- The case’s holding
- A property owner lacks reasonable investment-backed expectations for a regulatory takings claim if they acquired the property after the enactment of the relevant regulatory scheme.
- Later courts cite it for
- “(1) whether the plaintiff operated in a 'highly regulated industry;' (2) whether the plaintiff was aware of the problem that spawned the regulation at the time it purchased the allegedly taken property; and (3) whether the plaintiff could have 'reasonably anticipated' the possibility of such regulation in light of the 'regulatory environment' at the time of purchase.” · 3 citing courts
- The case’s holding
- Administrative exhaustion requirements may be excused when pursuing such remedies would be futile (basis: administrative exhaustion may be excused if it would be futile).
- Later courts cite it for
- “narrow anomaly reserved for extreme situations.” · 5 citing courts
- Where it cites § 1256
- “” For example, section 506, 30 U.S.C. § 1256 , is entitled “Permits” and provides for the terms, termination, and renewal of permits.”
- Later courts cite it for
- “we begin, as always, with the plain language of the statute in question.” · 6 citing courts
- Where it cites § 1256
- “See 30 U.S.C. § 1256 (a). Although a SMCRA permit authorizes all of the activities related to a surface mining operation, it alone may not be sufficient to allow a mine operator to conduct surface mining operations.”
- The case’s holding
- An agency may limit its environmental review to the effects of specifically authorized actions when it lacks control over the broader operation regulated by a state.
- Later courts cite it for
- “requires the exercise of complex scientific judgment and deference to the corps' expertise.” · 1 citing court
- The case’s holding
- When reviewing a surface coal mining permit, the agency must consider the probable cumulative impact of all anticipated related activities, whether or not they are covered by the permit under review.
- Later courts cite it for
- “consider the probable cumulative impact of all anticipated activities which will be a part of a 'surface coal mining operation,' whether or not the activities are part of the permit under review.” · 2 citing courts
- The case’s holding
- When statutes address particularly complicated subject matters, a reviewing court gives due consideration to the administering agency's construction of those statutes.
- Later courts cite it for
- “conditions as highlighted by the appellees, the commission is also beyond the control and without the fault or negligence of charged with considering, among other things, the potential the permit holder.” · 2 citing courts
- Where it cites § 1256
- “§ 506(a), 30 U.S.C. § 1256 (a). The Act spells out in detail the minimum information that an applicant must submit to the regulatory authority to accompany its permit request.”
- The case’s holding
- Judicial appeals of permit decisions fall under state jurisdiction in which the Secretary plays no role.
- Later courts cite it for
- “direct intervention by the secretary in the operation of state regulatory programs is clearly intended as an extraordinary remedy.” · 4 citing courts
- Where it cites § 1256
- “3d at 189 (citing 30 U.S.C. § 1256 (a)). The SMCRA permit application “must provide detailed infor *319 mation about possible environmental consequences of the proposed operations, as well as assurances that damage to the site will be prevented or minimized during mining and…”
- Later courts cite it for
- “a court will set aside an agency action if it is 'arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” · 4 citing courts
- Where it cites § 1256
- “” 30 U.S.C. § 1256 (a). Thus, under ordinary circumstances, the doctrine of exhaustion of administrative remedies would require filing of a permit with the OSM.”
- Later courts cite it for
- “in holding a claim to be unripe, the court essentially is refusing to exercise jurisdiction over the case.” · 3 citing courts
- Where it cites § 1256
- “30 U.S.C. § 1256 . . Before the Corps issues a CWA § 404 permit, an applicant is also required to provide certification from the proper state authority that the proposed project will comply with state water quality standards under CWA § 401.”
- Later courts cite it for
- “because plaintiffs complain about injuries caused by downstream water quality impacts, their injuries fall under the zone of interests protected by a 402 national pollutant discharge elimination system permit and not a 404 fill permit.” · 1 citing court
- Where it cites § 1256
- “30 U.S.C. § 1256 . The permit must require the surface coal mining operation to satisfy certain environmental protection performance standards.”
- Later courts cite it for
- “had not met its burden of demonstrating that any alleged classification was unreasonable and not rationally related to any legitimate state purpose.” · 1 citing court
- Where it cites § 1256
- “30 U.S.C. § 1256 (d)(2). C. The Agency Decisions There are two mines whose mining plan modifications are at issue in this case: the Colowyo Mine and the Trapper Mine.”
- Where it cites § 1256
- “30 U.S.C. §§ 1256 , 1300(c). Because the court has found that sections 710(a) and (e) imply that the Secretary shall be the regulatory authority and enforce the requirements of the Act, the court concludes that the Secretary’s action in including the definition of a permit in…”
- The case’s holding
- An agency's interpretation and implementation of a statute is not arbitrary or capricious if the agency makes reasonable policy judgments in uncertain environmental areas.
- Later courts cite it for
- “(a)lthough a more lenient standard also might be reasonable, the court cannot conclude that the secretary's action in promulgating the regulation was arbitrary, capricious, or inconsistent with law.” · 2 citing courts
- Where it cites § 1256
- “2d 1021 (2002) (Eastern Minerals); 30 U.S.C. §§ 1256 , 1272. In 1980 and 1981, Eastern Minerals obtained two separate one-year permits from the State of Tennessee that authorized Eastern Minerals to prepare approximately 33 acres on the Sewanee coal seam on the Cane property for…”
- The case’s holding
- Multiple tracts purchased under a single deed and treated as a single investment unit constitute a single parcel for takings analysis purposes.
- Later courts cite it for
- “a comparison of the market value of the property immediately before the governmental action with the market value of that same property immediately after the action.” · 2 citing courts
- Where it cites § 1256
- “30 U.S.C. §§ 1256 , 1257. The permit application must contain the names and addresses of the applicant and the operator of the mining operation “if he is a person different from the applicant.”
- Later courts cite it for
- “an actual conflict between the ... law of the interested jurisdictions” · 2 citing courts
Show all 64 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 5 cases in 2013. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 24 courts in all.
(a)1 case
Edition shown: U.S. Code current through Pub. L. 119-102 (OLRC release point). Syfert holds no earlier or later version of this section.