Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402 (9th Cir. 1975)
The government acts arbitrarily and violates its procurement regulations when it corrects a bid's total to reconcile with item prices, allowing a bidder to revise its bid after opening.
An unsuccessful bidder on a federal government contract sued after the government adjusted the total bid of a competing bidder to correct an addition error. The displaced low bidder had standing to sue, and jurisdiction existed under the Tucker Act because the invitation to bid and submission of a bid created an implied contract requiring fair and honest consideration of bids. The court held the government acted arbitrarily and in violation of its own regulations by correcting the total rather than the component items, since the error could not be identified from the face of the bid. The judgment awarding bid preparation costs is affirmed.
At page 403Determining the scope of administrative agency authority12 citing cases
- Club Italia Soccer & Sports Org., Inc. v. Charter Twp. of Shelby, 470 F.3d 286 (6th Cir. 2006).published Admin., 528 F.2d 1294, 1296 (7th Cir. 1975); Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975); Merriam v. Kunzig, 476 F.2d 1233, 1242 (3d Cir. 1973); William F. Wilke, Inc. v. Department of Army, 485 F.2d 180…
- Dist. of Columbia v. Grp. Ins. Admin., 633 A.2d 2 (D.C. 1993).publishedAdmin., 528 F.2d 1294, 1296 (7th Cir.1975); Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir.1975); Merriam v. Kunzig, 476 F.2d 1233, 1241-43 (3d Cir.), cert. denied, 414 U.S. 911 , 94 S.Ct. 233 , 38 L.Ed.2d 149 (19…
- Maruyama & Assocs., Ltd. v. Mariana Islands Hous. Auth., 1 N. Mar. I. Commw. 997 (D. N. Mar. I. 1984).publishedArmstrong & Armstrong, Inc. v. united States, 514 F.2d 402, 403 (9th Cir. 1975); McCarty Corp. v. United States, 499 F.2d 633, 637 (Ct.Claims 1974).
- B.K. Instrument, Inc. v. United States, 715 F.2d 713 (2d Cir. 1983).published Merriam v. Kunzig, supra, 476 F.2d 1223, 1241-43 (3 Cir.), cert. denied, 414 U.S. 911 , 94 S.Ct. 233 , 38 L.Ed.2d 149 (1973); William F. Wilke, Inc. v. Department of the Army, 485 F.2d 180, 183 (4 Cir.1973); Hayes International Corp. v. Mc…
- King v. Alaska State Hous. Auth., 633 P.2d 256 (Alaska 1981).publishedArmstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975).
- Scanwell Labs., Inc. v. David D. Thomas, 521 F.2d 941 (D.C. Cir. 1975).publishedSee Heyer Products Co. v. United States, 140 F.Supp. 409, 412-13 , 135 Ct.Cl. 63, 69 (1956); Keco Industries, Inc. v. United States, 428 F.2d 1233, 1237 , 192 Ct.Cl. 773, 780 (1970); McCarty Corp. v. United States, 499 F.2d 633, 637 , 204…
- Airco, Inc. v. Energy Rsch. & Dev. Admin., 528 F.2d 1294 (7th Cir. 1975).publishedSee Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975), and cases cited therein.
- Am. Cargo Transp., Inc. v. Natsios, 429 F. Supp. 2d 139 (D.D.C. 2006).publishedUnder the law that governs procurement decisions, a “[djissappointed bidders may challenge a government contract award under the [APA].” Iceland Steamship Co. v. United States Dep’t of the Army, 201 F.3d 451, 453 (D.C.Cir.2000); accord Sca…
- New England Insulation Co. v. Gen. Dynamics Corp., 522 N.E.2d 997 (Mass. App. Ct. 1988).publishedSee also Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975); Merriam v. Kunzig, 476 F.2d 1233 , 1242 & n.7 (3d Cir.), cert. denied, 414 U.S. 911 (1973).
- Jets Servs., Inc. v. Hoffman, 420 F. Supp. 1300 (M.D. Fla. 1976).publishedSee, e.g., Armstrong & Armstrong, Inc. v. United States, 514 F.2d 402, 403 (9th Cir. 1975); Hayes Internad Corp. v. McLucas, 509 F.2d 247, 254-57 (5th Cir. 1975).
Other citing cases
- Look v. United States, 113 F.3d 1129 (9th Cir. 1997).published
- Big Country Foods, Inc. v. Bd. of Educ. of the Anchorage Sch. Dist., 952 F.2d 1173 (9th Cir. 1992).published
- Coalition for the Pres. of Hispanic Broad. v. Fed. Commc'ns Comm'n, 893 F.2d 1349 (D.C. Cir. 1990).published
v.
The United States of America, Acting by and Through Rogers C. B. Morton, Secretary of the Department of the Interior, the United States Department of the Interior, Its Bureaus, Agents, Servants and Representatives
ARMSTRONG & ARMSTRONG, INC., Plaintiff-Appellee,
v.
The UNITED STATES of America, acting By and Through Rogers
C. B. MORTON, Secretary of the Department of the Interior,
the United States Department of the Interior, its Bureaus,
Agents, Servants and Representatives, Defendants-Appellants.
No. 73-1983.
United States Court of Appeals,
Ninth Circuit.
April 10, 1975.
David M. Cohen, Atty., Civ. Div., Dept. of Justice, Washington, D. C. (argued), for defendants-appellants.
William B. Moore (argued), Seattle, Wash., for plaintiff-appellee.
OPINION
Before KOELSCH, BROWNING, and GOODWIN, Circuit Judges.
PER CURIAM:
The United States appeals from a judgment awarding bid preparation costs to an unsuccessful bidder on a government contract. We affirm for the reasons stated by the district court. 356 F.Supp. 514 (E.D.Wash. 1973).
We agree with the district court that in the circumstances of this case appellee, as the displaced low bidder, had standing to sue. Scanwell Laboratories v. Shaffer, 137 U.S.App.D.C. 371, 424 F.2d 859 (1970); Merriam v. Kunzig, 476 F.2d 1233 (3d Cir. 1973); Wilke v. United States, 485 F.2d 180 (4th Cir. 1973); Cincinnati Electronics Corp. v. Kleppe, 509 F.2d 1080 (6th Cir. 1975); and Hayes International Corp. v. McLucas, 509 F.2d 247 (5th Cir. 1975).
We also agree with the district court that jurisdiction was conferred by the Tucker Act, 28 U.S.C. § 1346(a)(2). The invitation to bid, followed by submission of a bid, created an implied contract obligating the government to consider the bid fairly and honestly. Keco Industries, Inc. v. United States, 428 F.2d 1233, 192 Ct.Cl. 773 (1970); Continental Business Enterprises, Inc. v. United States, 452 F.2d 1016, 196 Ct.Cl. 627 (1971).
Finally, on the merits, we agree with the district court that the government acted arbitrarily, and in violation of its own regulations, by adjusting the total bid of another bidder, Bovee & Crail, in order to reconcile that total with the correct sum of the 82 item bids that comprised the overall bid.
The government could not know from the face of the bid whether the error lay in one of the component items or in the summation. Bovee & Crail stated that the error was in the addition. Correction of the total made Bovee & Crail the low bidder. If, however, it had appeared that Bovee & Crail was already the low bidder, Bovee & Crail could have informed the government that the error was not in the addition but in one of the component items, and thus maintain the higher bid. This opportunity to second guess one's bid after the bids have been opened subverts the competitive bidding process, and creates the potential for abuse that federal procurement regulations are designed to prevent.
Affirmed.