18 C.F.R. § 157.9

Notice of application and notice of schedule for environmental review

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

(a) Notice of each application filed, except when rejected in accordance with § 157.8, will be issued within 10 business days of filing, and subsequently will be published in the Federal Register and copies of such notice sent to States affected thereby, by electronic means if practical, otherwise by mail. Persons desiring to receive a copy of the notice of every application shall so advise the Secretary.

(b) For each application that will require an environmental assessment or an environmental impact statement, notice of a schedule for the environmental review will be issued within 90 days of the notice of the application, and subsequently will be published in the Federal Register.

[Order 653, 70 FR 8724, Feb. 23, 2005, as amended by Order 687, 71 FR 62920, Oct. 27, 2006]
Notes of Decisions
Cited in 7 cases (1 in the last 5 years), 1978–2022 · leading case: Tennessee Gas Pipeline v. 104 Acres in Prov. Cty., 749 F. Supp. 427 (D.R.I. 1990).
Tennessee Gas Pipeline v. 104 Acres in Prov. Cty., 749 F. Supp. 427 (D.R.I. 1990). “"); 18 C.F.R. § 157.9 (1990) ("Notice of each application filed .”
Lng v. Loqa, 79 F. Supp. 2d 49 (D.R.I. 2000). “Moreover, FERC’s regulations require that notice of applications for CPCNs be published in the Federal Register and that all interested parties may petition to intervene.”
Nat'l Fuel Gas Supply Corp. v. Pub. Serv. Comm'n, 894 F.2d 571 (2d Cir. 1990). “18 C.F.R. §§ 157.9 , 157.10. State commissions may intervene as of right.”
Moreau v. Fed. Energy Regulatory Comm'n, 982 F.2d 556 (D.C. Cir. 1993). “” 18 C.F.R. § 157.9 (1992). FERC did exactly that in this case, thereby presumptively giving notice of the FERC proceedings regarding TN Gas’s application “to all persons residing within the States of the Union and the District of Columbia,” 44 U.”
ANR Pipeline Co. v. Iowa State Com. Comm'n, 828 F.2d 465 (8th Cir. 1987). “FERC regulations require that affected states receive notice of any application for a certificate under the NGA, 18 C.F.R. § 157.9 (1987), and state agencies may intervene in any FERC proceeding on an application for a certificate, 4 18 C.”
McCombs v. Fed. Energy Regulatory Comm'n, 570 F.2d 1376 (10th Cir. 1978). “Thus it is unnecessary for me to address these issues. I will consider only the holding of the majority on the central abandonment issue.”
Daubenmire v. Columbia Gas Transmission, LLC (S.D. Ohio 2022). “§ 4332 ; 18 C.F.R. § 157.9 (b). At the end of the process, FERC will issue a certificate if it finds that the proposed pipeline “is or will be required by the present or future public convenience and necessity.”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.