C.F.R. homeSearch C.F.R.
C.F.R.Title 23Chapter I—Federal Highway Administration, Department of TransportationSubchapter H—Right-Of-Way and EnvironmentPart 771—Environmental Impact and Related Procedures

23 C.F.R. § 771.109 (2026)

Applicability and responsibilities

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1982–2020 24citing cases
At a glance

Courts have cited this section in 24 opinions since 1982. The most litigated part is subsection (c)(1) (1 case).

(a)(1) The provisions of this part only apply to major Federal actions. Steps taken by the applicant that do not require Federal approvals, such as preparation of a regional transportation plan, are not subject to this part.

(2) The Administration has determined the following additional actions are not major Federal actions subject to NEPA:

(i) Extraterritorial activities or decisions, which means agency activities or decisions with effects located entirely outside the jurisdiction of the United States.

(ii) [Reserved]

(3) This part does not apply to or alter final agency action the Administration made prior to July 3.

(4) Environmental documents accepted or prepared after July 3, 2025 must be developed in accordance with this part.

(b)(1) The project sponsor, in cooperation with the Administration, is responsible for implementing those mitigation measures stated as commitments in the environmental documents prepared pursuant to this part unless the Administration approves of their deletion or modification in writing. FHWA will ensure that this is accomplished as part of its stewardship and oversight responsibilities. FRA and FTA will ensure implementation of committed mitigation measures through incorporation by reference in the grant agreement, followed by reviews of designs and construction inspections.

(2) When entering into Federal-aid project agreements pursuant to 23 U.S.C. 106, FHWA must ensure the State highway agency constructs the project in accordance with and incorporates all committed environmental impact mitigation measures listed in approved environmental review documents.

(c) The following roles and responsibilities apply during the environmental review process:

(1) The Federal lead agencies are responsible for managing the environmental review process and the contents of the appropriate environmental documents.

(2) Any State or local governmental entity applicant that is or is expected to be a direct recipient of funds under title 23 of the United States Code or 49 U.S.C. ch. 53 for the action, or is or is expected to be a direct recipient of financial assistance for which FRA is responsible (e.g., 49 U.S.C. Subtitle V) must serve as a joint lead agency with the Administration in accordance with 23 U.S.C. 139, and may prepare environmental review documents if the Administration furnishes guidance, and independently evaluates the environmental documents.

(3) The Administration may invite other Federal, State, local, or federally recognized Indian Tribal governmental units to serve as joint lead agencies in accordance with 42 U.S.C. 4336(a)(1)(B). If the applicant is serving as a joint lead agency under 23 U.S.C. 139(c)(3), then the Administration and the applicant will decide jointly which other agencies to invite to serve as joint lead agencies.

(4) When the applicant seeks an Administration action other than the approval of funds, the Administration will determine the role of the applicant in accordance with this part and 23 U.S.C. 139.

(5) Regardless of its role under paragraphs (c)(2) through (c)(4) of this section, a public agency that has statewide jurisdiction (for example, a State highway agency or a State department of transportation) or a local unit of government acting through a statewide agency, that meets the requirements of 42 U.S.C. 4332(G), may prepare the environmental documents with the Administration furnishing guidance, participating in the preparation, and independently evaluating the document. All FHWA applicants qualify under this paragraph.

(6) A participating agency must provide input during the times specified in the coordination plan under 23 U.S.C. 139(g) and within the agency's special expertise or jurisdiction. Participating agencies provide comments and concurrence on the schedule within the coordination plan. For projects not subject to 23 U.S.C. 139, participating agencies will participate in the environmental review process consistent with 42 U.S.C. 4336a, as appropriate.

(d) When entering into Federal-aid project agreements pursuant to 23 U.S.C. 106, the State highway agency must ensure the project is constructed in accordance with and incorporates all committed environmental impact mitigation measures listed in approved environmental documents unless the State requests and receives written FHWA approval to modify or delete such mitigation features.

(e) When FRA is the lead agency, the project sponsor is a private entity, and there is no applicant acting as a joint-lead agency, FRA may provide written authorization to the project sponsor to prepare the environmental document under FRA supervision. FRA's written authorization will establish the project sponsor's and FRA's respective responsibilities in preparing the environmental document.

The 20 cases that cite 23 C.F.R. § 771.109 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 771.109 4×cited by 10 cases
Where it cites § 771.109
“§139 ; 23 C.F.R. §771.109 (c)(1). But the question is not whether the state suffers insult from the district court’s evaluation of its handiwork or injury from the judgment—it does, because the district court’s judgment costs it a lot of money (unless USDOT comes up with a new…”
Later courts cite it for
“record of decision permitting the use of federal funds.” · 3 citing courts
cites § 771.109 1×subsections: (c)(1)cited by 225 cases
Where it cites § 771.109
“5 (a); 23 C.F.R. 771.109(c)(1). They rely upon the lack of any independent evaluation of project costs submitted by UDOT.”
The case’s holding
A federal permit is arbitrary and capricious if the agency fails to consider all practicable alternatives and fails to adequately address environmentally significant impacts.
Later courts cite it for
“issues will be deemed waived if they are not adequately briefed.” · 11 citing courts
3
GREENStop H-3 Ass'n v. Lewis, 538 F. Supp. 149 (D. Haw. 1982).
cites § 771.109 3×cited by 26 cases
Where it cites § 771.109
“23 C.F.R. § 771.109 (a)(4) (1981). Since the original draft EIS (Moanalua) was filed with the EPA in 1972, and the Draft NHV-SEIS was filed in 1977, defendants properly applied the older regulations in preparing the NHV-SEIS and Ho’omaluhia Park 4(f) Statement.”
The case’s holding
A federal agency must prepare a supplemental environmental impact statement when significant new information regarding environmental aspects of a proposed action becomes available.
Later courts cite it for
“for further documentation that no feasible and prudent alternatives exist to the use of the golf course lands and all possible measures to minimize harm to the golf course have been taken.” · 2 citing courts
cites § 771.109 1×cited by 26 cases
Where it cites § 771.109
“§ 5309(d)(1); 23 C.F.R. § 771.109 (c)(2). This review culminates in a Record of Decision (“ROD”) in which FTA identifies the alternative chosen and demonstrates the project’s compliance with NEPA.”
Later courts cite it for
“agencies need not reanalyze alternatives previously rejected, particularly when an earlier analysis of numerous reasonable alternatives was incorporated into the final analysis and the agency has considered and responded to public comment favoring other alternatives.” · 3 citing courts
cites § 771.109 1×cited by 33 cases
Where it cites § 771.109
“3 ) and as stipulated in regulations by the FHWA ( 23 C.F.R. § 771.109 (b)). ROD at 1,17-20.”
The case’s holding
Courts evaluate an agency's choice of reasonable alternatives in light of the federal action's objectives and goals, upholding a purpose statement that considered broader transportation objectives and alternatives.
Later courts cite it for
“another location with similar characteristics” · 2 citing courts
6
GREENCity of South Pasadena v. Slater, 56 F. Supp. 2d 1106 (C.D. Cal. 1999).
cites § 771.109 2×cited by 20 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 (a)(1), (b). In interpreting similar regulations under the National Environmental Protection Act (“NEPA”), the Ninth Circuit has held that once an agency makes a commitment to certain mitigation measures, those mitigation measures must be implemented.”
Later courts cite it for
“routinely impose either no 17 bond or a minimal bond in public interest environmental cases.” · 5 citing courts
7
cites § 771.109 1×cited by 27 cases
Where it cites § 771.109
“In support of its position, Citizens points to 23 C.F.R. § 771.109 (c)(5), which states that a local agency “may prepare the EIS and other environmental review documents with the Administration furnishing guidance, participating in the preparation, and independently evaluating…”
The case’s holding
The National Environmental Policy Act does not impose a minimum number of alternatives that an agency must evaluate.
Later courts cite it for
“nepa does not impose any minimum number of alternatives that must be evaluated.” · 4 citing courts
8
GREENSw. Williamson Cnty. Cmty. Ass'n v. Slater, 243 F.3d 270 (6th Cir. 2001).
cites § 771.109 1×cited by 27 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 (a)(1). An “action” in turn is defined as an activity such as “changes in access control .”
The case’s holding
A major federal action under NEPA does not require federal funding if federal involvement restricts reasonable alternatives or allows agencies to control the project outcome.
Later courts cite it for
“do not affect the rights of the litigants.” · 6 citing courts
9
GREENSierra Club v. Marsh, 714 F. Supp. 539 (D. Me. 1989).
cites § 771.109 2×cited by 15 cases
Where it cites § 771.109
“5 (c); see 23 C.F.R. § 771.109 (c)(1). In its supplemental memorandum denying plaintiffs’ motion for a preliminary injunction, this court found that FHwA personnel did participate in the preparation of the EIS.”
The case’s holding
A procedural violation of NEPA supports preliminary injunctive relief only if it results in uninformed agency decisionmaking that causes irreparable environmental harm.
Later courts cite it for
“all further project construction” · 1 citing court
10
GREENRobert MacHt v. Samuel K. Skinner, 916 F.2d 13 (D.C. Cir. 1990).
cites § 771.109 1×cited by 41 cases
The case’s holding
Federal funding for preliminary studies or the issuance of permits for a negligible portion of a project does not constitute major federal action requiring NEPA compliance.
Later courts cite it for
“in this era of federal fiscal shortcomings there is a wide gulf between what a state may want and what the federal government is willing to provide.” · 4 citing courts
11
GREENClairton Sportsmen's Club v. Pennsylvania Tpk. Comm'n, 882 F. Supp. 455 (W.D. Pa. 1995).
cites § 771.109 1×cited by 20 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 (a)(1) (1993). 10 . The Court went even further in Kleppe .”
Later courts cite it for
“a document need not literally pass before the eyes of the final agency decision maker to be considered part of the administrative record.” · 4 citing courts
12
GREENSenville v. Peters, 327 F. Supp. 2d 335 (D. Vt. 2004).
cites § 771.109 1×cited by 8 cases
Where it cites § 771.109
“§ 4332 (2)(D); see also 23 C.F.R. § 771.109 (e)(1) (if applicant meets requirements of § 4332(2)(D), it may prepare EIS with FHWA furnishing guidance, participating in preparation and independently evaluating document).”
13
GREENHickory Neighborhood Def. League v. Burnley, 703 F. Supp. 1208 (W.D.N.C. 1988).
cites § 771.109 1×cited by 15 cases
Where it cites § 771.109
“These individuals in turn delegated much of the task of developing the 4(f) Statement and its accompanying exhibits to state officials (as they are specifically authorized to do by 23 C.F.R. § 771.109 (c)). Wade v. Dole, 631 F.”
Later courts cite it for
“the ultimate question for the court is whether the agency took a hard look at all relevant factors, and used plain common sense in its determination as to whether the facts before the secretary support his decision that there is no prudent and feasible alternative to the taking of some 4(f) property in this case for the project.” · 1 citing court
14
GREENHells Canyon Pres. Council v. Jacoby, 9 F. Supp. 2d 1216 (D. Or. 1998).
cites § 771.109 1×cited by 15 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 . When the regulations are read as a whole, 23 C.”
15
GREENWade v. Dole, 631 F. Supp. 1100 (N.D. Ill. 1986).
cites § 771.109 1×cited by 8 cases
Where it cites § 771.109
“These individuals in turn delegated much of the task of developing the 4(f) Statement and its accompanying exhibits to state officials (as they are specifically authorized to do by 23 C.F.R. § 771.109 (c)). Due to the complex nature of the decision making process in this case,…”
16
GREENMerritt Parkway Conservancy v. Mineta, 424 F. Supp. 2d 396 (D. Conn. 2006).
cites § 771.109 1×cited by 4 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 (b). Yet, when asked by the Court where it should look in the record for confirmation that the future steps to mitigate harm promised by the Final EA and MOA were taken prior to final approval of the Interchange Project design in December 2001, counsel for…”
17
GREENGeer v. Fed. High. Admin., 975 F. Supp. 47 (D. Mass. 1997).
cites § 771.109 1×cited by 6 cases
Where it cites § 771.109
“” 23 C.F.R. § 771.109 (b). In addition, “the Secretary must be permitted to make decisions in what might be called a progressive manner— not everything can be pulled together all at once.”
18
GREENMaryland Wildlife Fed'n v. Dole, 747 F.2d 229 (4th Cir. 1984).
cites § 771.109 2×cited by 12 cases
Where it cites § 771.109
“” 23 CFR § 771.109 (b). While the FHWA and the state highway officials are obliged to complete “any necessary design work[J required to make those engineering and environmental decisions necessary to complete .”
Later courts cite it for
“the quantitative weighing of harm to numerous and different types of valued resources is itself difficult, and the relative harm is not likely often to be capable of precise objective measurement.” · 2 citing courts
19
GREENSave Our Sound OBX, Inc. v. N.C. Dep't of Transp., 324 F. Supp. 3d 597 (E.D.N.C. 2018).
cites § 771.109 1×cited by 1 case
Where it cites § 771.109
“(2) [n]ew information or circumstances relevant to environmental concerns and bearing on the proposed action or its impacts would result in significant environmental impacts not evaluated in the EIS.”
20
GREENNat'l Wildlife Fed'n v. Goldschmidt, 677 F.2d 259 (2d Cir. 1982).
cites § 771.109 1×cited by 10 cases
Where it cites § 771.109
“See 23 C.F.R. § 771.109 (a)(4) (1981). As a result, “prior concurrence” as to Sections I and II is governed by 23 C.”
Later courts cite it for
“courts have no business adjudicating the legality of non-events.” · 4 citing courts

Show all 24 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198220012020

One bar per year. Tallest: 2 cases in 1982. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
11th Cir.2D.C. Cir.210th Cir.12d Cir.14th Cir.16th Cir.17th Cir.19th Cir.1

The 8 courts with the most citing cases, of 22 courts in all.

By subsection
(c)(1)1 case
Utahns for Better Transp. v. United States Dep't of Transp., 305 F.3d 1152 (10th Cir. 2002).“5 (a); 23 C.F.R. 771.109(c)(1). They rely upon the lack of any independent evaluation of project costs submitted by UDOT.”

Show all 24 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com