C.F.R. homeSearch C.F.R.
C.F.R.Title 23Chapter I—Federal Highway Administration, Department of TransportationSubchapter H—Right-Of-Way and EnvironmentPart 771—Environmental Impact and Related Procedures

23 C.F.R. § 771.113 (2026)

Timing of Administration activities when NEPA applies

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1984–2011 16citing cases
At a glance

Courts have cited this section in 16 opinions since 1984.

(a) The lead agencies, in cooperation with the applicant and project sponsor, as appropriate, will perform the work necessary to complete the environmental review process. This work includes drafting environmental documents and completing environmental studies, related engineering studies, agency coordination, public involvement, and identification of mitigation measures. Except as otherwise provided in law or in paragraph (d) of this section, final design activities, property acquisition, purchase of construction materials or rolling stock, or project construction must not proceed until the following have been completed:

(1)(i) The Administration has classified the action as a CE;

(ii) The Administration has issued a FONSI; or

(iii) The Administration has issued a combined final EIS/ROD or a final EIS and ROD;

(2) For actions proposed for FHWA funding, the Administration has received and accepted the certifications and any required public hearing transcripts required by 23 U.S.C. 128;

(3) For activities proposed for FHWA funding, the programming requirements of 23 CFR part 450, subpart B, and 23 CFR part 630, subpart A, have been met.

(b) For FHWA actions, completion of the requirements set forth in paragraphs (a)(1) and (2) of this section is considered acceptance of the general project location and concepts described in the environmental review documents unless otherwise specified by the approving official.

(c) Letters of Intent issued under the authority of 49 U.S.C. 5309(g) are used by FTA to indicate an intention to obligate future funds for multi-year capital transit projects. Letters of Intent will not be issued by FTA until the NEPA process is completed. Letters of Intent issued by FRA under the authority of 49 U.S.C. 24911(g) may be issued prior to completion of the NEPA process.

(d) The prohibition in paragraph (a)(1) of this section do not apply to:

(1) Early acquisition, hardship and protective acquisitions of real property in accordance with 23 CFR part 710, subpart E for FHWA. Exceptions for the acquisitions of real property are addressed in paragraphs (c)(6) and (d)(3) of § 771.118 for FTA.

(2) The early acquisition of right-of-way for future transit use in accordance with 49 U.S.C. 5323(q) and FTA guidance.

(3) A limited exception for rolling stock is provided in 49 U.S.C. 5309(l)(6).

(4) FRA may make exceptions on a case-by-case basis for purchases of railroad components or materials that can be used for other projects or resold.

The 16 cases that cite 23 C.F.R. § 771.113 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENSw. Williamson Cnty. Cmty. Ass'n v. Slater, 976 F. Supp. 1119 (M.D. Tenn. 1997).
cites § 771.113 8×cited by 7 cases
Where it cites § 771.113
““According to the Federal Highway Administration’s (FHWA) implementation of its environmental regulations found at 23 C.F.R. § 771.113 , a FONSI, standing alone, is not the final agency action.”
2
GREENJersey Heights Neighborhood Ass'n v. Glendening, 174 F.3d 180 (4th Cir. 1999).
cites § 771.113 2×cited by 79 cases
Where it cites § 771.113
“See 23 C.F.R. § 771.113 . On the fundamental question of where the highway would be located, the ROD thus signaled the end of the decisionmaking process.”
The case’s holding
Section 1983 claims are governed by the forum state's personal injury statute of limitations, and Fair Housing Act site-selection claims fail absent allegations of actual discriminatory eviction or housing denial.
Later courts cite it for
“it is well-settled that sections 1983 and 1985 borrow the state's general personal injury limitations period, which in maryland is three years.” · 6 citing courts
3
GREENBurkholder v. Peters, 58 F. App'x 94 (6th Cir. 2003).
cites § 771.113 2×cited by 13 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 (a)(l)(ii). Although federal regulations permit agencies to delegate responsibility for preparing an EA to a private contractor, such contractors must provide disclosure statements indicating that they have no “financial or other interest in the outcome of…”
4
GREENCity of Alexandria v. Rodney E. Slater, 198 F.3d 862 (D.C. Cir. 1999).
cites § 771.113 1×cited by 91 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 (a)(iii). Furthermore, then-existing Council regulations explicitly encouraged flexible, staged planning in the section 106 process.”
The case’s holding
Courts must grant considerable deference to an agency's expertise and policy-making role when evaluating whether a proposed alternative is reasonable in light of project objectives.
Later courts cite it for
“requires that agencies assess the environmental consequences of federal projects by following certain procedures during the decision-making process.” · 9 citing courts
5
GREENDep't of Transp. v. Blue, 556 S.E.2d 609 (N.C. Ct. App. 2001).
cites § 771.113 1×cited by 27 cases
Where it cites § 771.113
“125 (e); see also 23 C.F.R. § 771.113 (b). Here, NCDOT submitted the FEIS to FHWA for location approval to preserve the State’s option of obtaining federal funding in the future.”
The case’s holding
A party must file a petition for judicial review of a final agency decision within thirty days to maintain subject matter jurisdiction over environmental counterclaims.
Later courts cite it for
“when reviewing a motion to dismiss for lack of subject matter jurisdiction pursuant to rule 12(b)(1), a trial court may consider and weigh matters outside the pleadings.” · 6 citing courts
6
cites § 771.113 2×cited by 11 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 (a). Trump alleges, inter alia, that no Environmental Impact Statement or Finding of No Significant Impact has been approved with regard to the West-side Connector.”
7
GREENCnty. of Bergen v. Dole, 620 F. Supp. 1009 (D.N.J. 1985).
cites § 771.113 1×cited by 20 cases
Where it cites § 771.113
“9(e)(1), and an EIS has been prepared and approved, 23 C.F.R. 771.113, 40 C.F.R. § 1500.1 (b), 1501.”
Later courts cite it for
“may be validly approved by the agency even though conditioned on further development of mitigation measures.” · 3 citing courts
8
GREENCity of South Pasadena v. Slater, 56 F. Supp. 2d 1106 (C.D. Cal. 1999).
cites § 771.113 1×cited by 20 cases
Where it cites § 771.113
“” 23 C.F.R. § 771.113 (a)(1)(iii). The plaintiffs argue that the Court should enjoin final design activities because these activities are dependent on the signing of a valid ROD.”
Later courts cite it for
“routinely impose either no 17 bond or a minimal bond in public interest environmental cases.” · 5 citing courts
cites § 771.113 1×cited by 8 cases
Where it cites § 771.113
“Defendants also refer the Court to 23 C.F.R. § 771.113 (a), which states that “final design activities .”
Later courts cite it for
“must be supported by specific findings of the court.” · 2 citing courts
cites § 771.113 1×cited by 7 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 (a) (1988). Because hydrology and hydraulics are studied in detail during the design phase of project development (Thompson Aff.”
Later courts cite it for
“as a 'temporary park' until construction began” · 2 citing courts
11
GREENSave Barton Creek Ass'n v. Fed. High. Admin., 950 F.2d 1129 (5th Cir. 1992).
cites § 771.113 1×cited by 43 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 . Furthermore, for a highway to qualify for federal-aid funding, it must also have its plans, specifications, and estimates approved by the FHWA, and receive prior concurrence from the FHWA before the award of the construction contracts.”
The case’s holding
State-funded highway projects with independent utility and insufficient federal involvement do not constitute major federal actions requiring environmental impact statements under NEPA.
Later courts cite it for
“an attempt by an agency to divide artificially a 'major federal action' into smaller components to escape the application of nepa to some of its segments.” · 8 citing courts
cites § 771.113 1×cited by 15 cases
Where it cites § 771.113
“23 C.F.R. § 771.113 (a)(1). On June 7, 2002, a not-for-profit corporation called the Citizens Against the Pel-lissippi Parkway Extension, or CAPPE, filed suit against the FHWA and TDOT officials in federal district court to enjoin further action on the project.”
The case’s holding
Courts should permit an agency remand to correct legal defects unless the request is frivolous, made in bad faith, or lacks a reasonable timeframe for completion.
Later courts cite it for
“when an agency seeks a remand to take further action consistent with correct legal standards, courts should permit such a remand in the absence of apparent or clearly articulated countervailing reasons.” · 6 citing courts
13
GREENBurkholder v. Wykle, 268 F. Supp. 2d 835 (N.D. Ohio 2002).
cites § 771.113 1×cited by 3 cases
Where it cites § 771.113
“1 and 23 C.F.R. § 771.113 provide, inter alia: (a) Until an agency issues a record of decision .”
14
GREENMaryland Wildlife Fed'n v. Dole, 747 F.2d 229 (4th Cir. 1984).
cites § 771.113 1×cited by 12 cases
Where it cites § 771.113
“an EIS,” 23 CFR § 771.113 (a), other design work cannot proceed until an FEIS has been approved and a location decision made.”
Later courts cite it for
“the quantitative weighing of harm to numerous and different types of valued resources is itself difficult, and the relative harm is not likely often to be capable of precise objective measurement.” · 2 citing courts
15
GREENWest v. Sec'y of the Dep't of Transp., 206 F.3d 920 (9th Cir. 2000).
cites § 771.113 1×cited by 5 cases
Where it cites § 771.113
“107 (defining “action” and “administration action”), and 23 C.F.R. § 771.113 (project construction shall not proceed until the action has been classified as a categorical exclusion or the agency makes a finding of no significant impact or issues a final EIS).”
Later courts cite it for
“a category of actions which do not individually or cumulatively have a significant effect on the human environment and which have been found to have no such effect in procedures adopted by a federal agency in implementation of these regulations.” · 5 citing courts
16
NO FLAG233 East 69th Street Owners Corp. v. Lahood, 797 F. Supp. 2d 326 (S.D.N.Y. 2011).
cites § 771.113 1×cited by 1 case
Where it cites § 771.113
“” 23 C.F.R. § 771.113 (a)(iii). The FEIS provided only broad design guidelines for ancillary facilities collectively.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198419972011

One bar per year. Tallest: 3 cases in 1999. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
4th Cir.26th Cir.2D.N.J.25th Cir.19th Cir.1C.D. Cal.1D.C. Cir.1N.C. Ct. App.1

The 8 courts with the most citing cases, of 13 courts in all.

By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com