23 C.F.R. § 771.130 (2026)
Supplemental environmental impact statements
Edition and currency
Other sources
Courts have cited this section in 39 opinions since 1988, 6 of them in the last five years. The most litigated part is subsection (a) (1 case).
(a) A draft EIS, final EIS, or supplemental EIS may be supplemented at any time. An EIS must be supplemented whenever the Administration determines:
(1) Changes to the proposed action would result in significant environmental impacts not evaluated in the EIS; or
(2) New information or circumstances relevant to environmental concerns and bearing on the proposed action or its impacts would result in significant environmental impacts not evaluated in the EIS.
(b) However, a supplemental EIS will not be necessary where:
(1) The changes to the proposed action, new information, or new circumstances result in a lessening of adverse environmental impacts evaluated in the EIS without causing other reasonably foreseeable environmental impacts that are significant and were not evaluated in the EIS; or
(2) The Administration decides to approve an alternative fully evaluated in an approved final EIS but not identified as the preferred alternative. In such a case, a revised ROD must be prepared and circulated in accordance with § 771.127(b).
(c) Where the Administration is uncertain of the significance of the new impacts, the applicant will develop appropriate environmental studies or, if the Administration deems appropriate, an EA to assess the reasonably foreseeable impacts of the changes, new information, or new circumstances. If, based upon the studies, the Administration determines that a supplemental EIS is not necessary, the Administration must so indicate in the project file.
(d) A supplement is to be developed using the same process and format (i.e., draft EIS, final EIS, and ROD) as an original EIS, except scoping is not required.
(e) In some cases, an EA or supplemental EIS may be required to address issues of limited scope, such as the extent of proposed mitigation or the evaluation of location or design variations for a limited portion of the overall project. Where this is the case, the preparation of a supplemental document must not necessarily:
(1) Prevent the granting of new approvals;
(2) Require the withdrawal of previous approvals; or
(3) Require the suspension of project activities, for any activity not directly affected by the supplement. If the changes in question are of such magnitude to require a reassessment of the entire action, or more than a limited portion of the overall action, the Administration must suspend any activities that would have an adverse environmental impact or limit the choice of reasonable alternatives, until the supplemental document is completed.
- Later courts cite it for
- “agencies need not reanalyze alternatives previously rejected, particularly when an earlier analysis of numerous reasonable alternatives was incorporated into the final analysis and the agency has considered and responded to public comment favoring other alternatives.” · 3 citing courts
- Later courts cite it for
- “routinely impose either no 17 bond or a minimal bond in public interest environmental cases.” · 5 citing courts
- Where it cites § 771.130
- “” 23 C.F.R. § 771.130 (a). A SEIS is prepared using virtually the same process and format as an EIS.”
- Where it cites § 771.130
- “The applicable FHWA regulation requires that the FHWA prepare an SEIS: (1) if changes to the proposed action would result in significant environmental impacts that were not evaluated in the EIS, or (2) if new information or circumstances bearing on the proposed action would…”
- The case’s holding
- Arguments raised in a perfunctory manner without developed argumentation are deemed waived for purposes of appeal.
- Later courts cite it for
- “issues adverted to in a perfunctory manner, unaccompanied by some effort at developed argumentation, are deemed waived for purposes of appeal.” · 6 citing courts
- Where it cites § 771.130
- “” 23 C.F.R. § 771.130 (b). Section 1502.9(c) contains no similar language.”
- The case’s holding
- A supplemental environmental impact statement is not required when the final decision is a minor variation of a draft alternative and is qualitatively within the discussed spectrum of alternatives.
- Later courts cite it for
- “supplementation is not required when ... the new alternative is a 'minor variation of one of the alternatives discussed in the draft eis,' and ... the new alternative is 'qualitatively within the spectrum of alternatives that were discussed in the draft eis.” · 8 citing courts
- Where it cites § 771.130
- “The draft supplemental EIS considered the phased option in detail because at that stage the phased option was the preferred option. The Agency has determined a supplemental EIS is not required where the ROD selects an option not identified as the preferred option in the final…”
- Later courts cite it for
- “the relevant environmental impacts have already been considered.” · 2 citing courts
- The case’s holding
- Courts evaluate an agency's choice of reasonable alternatives in light of the federal action's objectives and goals, upholding a purpose statement that considered broader transportation objectives and alternatives.
- Later courts cite it for
- “another location with similar characteristics” · 2 citing courts
- Where it cites § 771.130
- “1990) (internal quotation marks omitted); see 23 C.F.R. § 771.130 .’ On June 13, 1995, the SHA submitted to the FHWA its reevaluation of the 1989 FEIS.”
- The case’s holding
- Section 1983 claims are governed by the forum state's personal injury statute of limitations, and Fair Housing Act site-selection claims fail absent allegations of actual discriminatory eviction or housing denial.
- Later courts cite it for
- “it is well-settled that sections 1983 and 1985 borrow the state's general personal injury limitations period, which in maryland is three years.” · 6 citing courts
- Where it cites § 771.130
- “23 C.F.R. Section 771.130(a) (1987). The FHWA regulations specifically state that “[sjupplements will be necessary when there have been significant changes in the proposed action, the affected environment, the anticipated impacts, or the proposed mitigation measures.”
- Later courts cite it for
- “the ultimate question for the court is whether the agency took a hard look at all relevant factors, and used plain common sense in its determination as to whether the facts before the secretary support his decision that there is no prudent and feasible alternative to the taking of some 4(f) property in this case for the project.” · 1 citing court
- Where it cites § 771.130
- “See 23 C.F.R. § 771.130 (a) (2000). In addition, NEPA regulations require an EA or other “appropriate environmental studies” if the significance of a change or new information is “uncertain.”
- Where it cites § 771.130
- “10; 23 C.F.R. § 771.130 . NEPA regulations also require the FHWA to “determine and analyze expected traffic noise impacts and alternative noise abatement measures to mitigate these impacts.”
- Where it cites § 771.130
- “3d at 529; 23 C.F.R. § 771.130 (a) (FHWA regulations requiring SEIS in response to new information or circumstances).”
- The case’s holding
- An agency may use an environmental reevaluation to determine if a design change produces significant or uncertain environmental impacts requiring a supplemental environmental assessment.
- Later courts cite it for
- “if the environmental impacts resulting from the design change are significant or uncertain, as compared with the original design's impacts, a supplemental ea is required.” · 6 citing courts
- Where it cites § 771.130
- “23 C.F.R. § 771.130 (a). However, an SEIS is not necessary where changes do not result in significant impacts or where there are no new impacts not already considered in the FEIS.”
- Later courts cite it for
- “cause effects which are significantly different from those already studied.” · 3 citing courts
- Where it cites § 771.130
- “See 23 C.F.R. § 771.130 (c) (“Where the Administration is uncertain of the significance of the new impacts, the applicant will develop appropriate environmental studies or, if the Administration deems appropriate, an EA [Environmental Assessment] to assess the impacts of the…”
- Later courts cite it for
- “potentially disruptive effects that could flow from remand without vacatur.” · 2 citing courts
- Where it cites § 771.130
- “They claim that the planned change to the Interstate 280 river crossing will have a significant environmental impact. They claim that the change in the Project specifying an above-ground causeway and altered wetlands fill mitigation plans require a supplemental EIS.”
- Later courts cite it for
- “all other currently pending motions,” · 2 citing courts
- Where it cites § 771.130
- “In addition, the FHWA regulations require that the agency supplement an EIS whenever it determines that: (1) Changes to the proposed action would result in significant environmental impacts that were not evaluated in the EIS; or (2) New information or circumstances relevant to…”
- Where it cites § 771.130
- “See 23 C.F.R. § 771.130 . Although NEPA does not expressly address “[t]he subject of postdecision supplemental environmental impact statements,” Federal Highway regulations require a Supplemental Environmental Impact Statement only when (1) substantial changes are made in the…”
- Later courts cite it for
- “will have a significant impact on the environment in a manner not previously evaluated and considered.” · 2 citing courts
- Where it cites § 771.130
- “The FHWA has its own, similar, regulations, found at 23 C.F.R. § 771.130 . . Plaintiffs also assert a third ground necessitating a SEIS relating to the Indiana bat: that the agencies did not include the results of certain consultations with FWS in their Draft EIS for Section 4.”
- Where it cites § 771.130
- “) Specifically, the project was tailored to include several new rights of way and drainage and equestrian trail easements that required the use of an additional 5.”
Show all 39 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 4 cases in 1999. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
The 8 courts with the most citing cases, of 28 courts in all.
(a)1 case
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.