(a) After endorsement, the Servicer may collect reasonable and customary fees and costs from the Borrower only as provided below. The Servicer may collect these fees or costs from the Borrower only to the extent that the Servicer is not reimbursed for such fees or costs by HUD. Permissible fees and costs include:

(1) Late fee in accordance with § 1005.511;

(2) Costs for processing or reprocessing a check returned as uncollectible (where bank policy permits, the Servicer must deposit a check for collection a second time before assessing an insufficient funds charge);

(3) Fees for processing a change of ownership of the property;

(4) Fees and costs for processing an assumption of the Section 184 Guaranteed Loan in connection with the sale or transfer of the property;

(5) Costs for processing a request for credit approval incurred in the course of processing an assumption or substitute Borrower;

(6) Costs for substitution of a hazard insurance policy at other than the expiration of term of the existing hazard insurance policy;

(7) Costs for modification of the Section 184 Guaranteed Loan requiring recordation of the agreement, including those for extension of term or re-amortization;

(8) Fees and costs for processing a partial release of the property;

(9) Attorney's and trustee's fees and costs actually incurred (including the cost of appraisals and advertising) when a Section 184 Guaranteed Loan has been referred to foreclosure counsel and subsequently the Section 184 Guaranteed Loan is reinstated. No attorney's fee and cost that exceeds the reasonable limits prescribed by Section 184 Program Guidance may be collected from the Borrower, unless approved by HUD;

(10) A trustee's fee, if the security instrument provides for payment of such a fee, for execution of a satisfactory release when the deed of trust is paid in full;

(11) Where permitted by the security instrument, attorney's fees and costs actually incurred in the defense of any suit or legal proceeding wherein the Servicer shall be made a party thereto by reason of the Section 184 Guaranteed Loan. No attorney's fee may be charged for the services of the Servicer's staff attorney or other employee;

(12) property preservation costs incurred, subject to reasonable limits prescribed by Section 184 Program Guidance, or otherwise approved by HUD;

(13) Fees permitted for providing a beneficiary notice under applicable Tribal, Federal and/or State law, if such a fee is not otherwise prohibited by the applicable law(s); and

(14) Such other reasonable and customary costs as may be authorized by HUD.

(b) Reasonable and customary fees must be based upon the actual cost of the work performed, including out-of-pocket expenses. HUD may establish maximum fees and costs which are reasonable and customary in different geographic areas. Except as provided in this part, no fee or costs shall be based on a percentage of either the face amount of the Section 184 Guaranteed Loan or the unpaid principal balance due.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.