30 C.F.R. § 75.603
Temporary splice of trailing cable
One temporary splice may be made in any trailing cable. Such trailing cable may only be used for the next 24-hour period. No temporary splice shall be made in a trailing cable within 25 feet of the machine, except cable reel equipment. Temporary splices in trailing cables shall be made in a workmanlike manner and shall be mechanically strong and well insulated. Trailing cables or hand cables which have exposed wires or which have splices that heat or spark under load shall not be used. As used in this section, the term “splice” means the mechanical joining of one or more conductors that have been severed.
Notes of Decisions
Cited in 2
cases, 1975–1975 · leading case: Old Ben Coal Corp. v. Interior Bd. of Mine Operations Appeals, 523 F.2d 25 (7th Cir. 1975).
Old Ben Coal Corp. v. Interior Bd. of Mine Operations Appeals, 523 F.2d 25 (7th Cir. 1975). “conditions did not constitute an imminent danger because: (1) ventilation in the area was adequate at the time of inspection; (2) no measurable amounts of methane were present; (3) the allegedly missing bolt did not impair “permissibility” of the shuttle car as that term is…”
Old Ben Coal Corp. v. Interior Bd. Of Mine Operations Appeals, 523 F.2d 25 (7th Cir. 1975). “conditions did not constitute an imminent danger because: (1) ventilation in the area was adequate at the time of inspection; (2) no measurable amounts of methane were present; (3) the allegedly missing bolt did not impair "permissibility" of the shuttle car as that term is…”
Annotations are extracted automatically from the opinions in the
Syfert caselaw corpus and ranked by authority, recency, and
treatment. Dots show Syfertize treatment of the citing case itself.