33 C.F.R. § 149.610

What must the District Commander be notified of and when?

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

The District Commander must be notified of the following:

When—The District Commander must be notified—
(a) Construction of a pipeline, platform, or single point mooring (SPM) is plannedAt least 30 days before construction begins.
(b) Construction of a pipeline, platform, or SPM beginsWithin 24 hours, from the date construction begins, that the lights and sound signals are in use at the construction site.
(c) A light or sound signal is changed during constructionWithin 24 hours of the change.
(d) Lights or sound signals used during construction of a platform, buoy, or SPM are replaced by permanent fixtures to meet the requirements of this partWithin 24 hours of replacement.
(e) The first cargo transfer operation beginsAt least 60 days before the operation.