(a) You must prepare a siting analysis if you commence construction of a large municipal waste combustor after January 23, 2024.

(b) You must prepare a siting analysis if you are required to submit an initial application for a construction permit, under 40 CFR part 51, subpart I, or 40 CFR part 52, as applicable, for the reconstruction or modification of your municipal waste combustor.