42 C.F.R. § 405.818 (2026)
Deadline for processing provider enrollment initial determinations
Edition and currency
Other sources
Contractors approve or deny complete provider or supplier enrollment applications to approval or denial within the following timeframes:
(a) Initial enrollments. Contractors process new enrollment applications within 180 days of receipt.
(b) Revalidation of existing enrollments. Contractors process revalidations within 180 days of receipt.
(c) Change-of-information and reassignment of payment request. Contractors process change-of-information and reassignment of payment requests within 90 days of receipt.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.