43 C.F.R. § 3282.3

When must the unit operator submit an application for BLM approval of a proposed initial participating area?

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

The unit operator must submit an application for BLM approval of a proposed participating area no later than:

(a) 60 days after receiving BLM's determination identified in § 3281.15(a)(3) that a unit well will produce or utilize in commercial quantities; or

(b) 30 days before the initiation of commercial operations, whichever occurs earlier.