46 C.F.R. § 139.145 (2026)
Suspension of approval
Edition and currency
Other sources
(a) The Coast Guard may suspend the approval of a TPO approved under this part whenever the Coast Guard determines that the TPO does not comply with the provisions of this part. The Coast Guard must:
(1) Notify the TPO in writing of the intention to suspend the approval;
(2) Provide the details of the TPO's failure to comply with this part; and
(3) Advise the TPO of the time period, not to exceed 60 days, within which the TPO must correct its failure to comply with this part. If the TPO fails to correct its failure to comply with this part within the time period allowed, the approval will be suspended.
(b) The Coast Guard may also partially suspend the approval of a TPO, using the process described in paragraph (a) of this section. This may include suspension of an individual auditor or surveyor or suspension of the authority of the TPO to carry out specific duties whenever the Coast Guard determines that the provisions of this part are not complied with.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.