Already have an account? Sign in instead.
You stay signed in for 30 days on this browser.
Continue with Google Continue with MicrosoftNo account yet? Create a free one.
We sent a six-digit code.
It expires in ten minutes, works once, and only in this browser. Five wrong tries void it. Send another code.
Your account is live and the Cloudflare checks are off for this browser.
211.274-3 Policy for valuation.
(a) It is DoD policy that contractors shall be required to identify the Government's unit acquisition cost for all deliverable end items to which item unique identification applies.
(b) The Government's unit acquisition cost is—
(1) For fixed-price type line, subline, or exhibit line items, the unit price identified in the contract at the time of delivery;
(2) For cost-type or undefinitized line, subline, or exhibit line items, the contractor's estimated fully burdened unit cost to the Government at the time of delivery; and
(3) For items delivered under a time-and-materials contract, the contractor's estimated fully burdened unit cost to the Government at the time of delivery.
(c) The Government's unit acquisition cost of subassemblies, components, and parts embedded in delivered items shall not be separately identified.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.