8.406-3 Remedies for nonconformance.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026

(a) If a contractor delivers a supply or service, but it does not conform to the order requirements, the ordering activity shall take appropriate action in accordance with the inspection and acceptance clause of the contract, as supplemented by the order.

(b) If the contractor fails to perform an order, or take appropriate corrective action, the ordering activity may terminate the order for cause or modify the order to establish a new delivery date (after obtaining consideration, as appropriate). Ordering activities shall follow the procedures at 8.406-4 when terminating an order for cause.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.