C.F.R. homeSearch C.F.R.
C.F.R.Title 48Chapter 1—Federal Acquisition RegulationSubchapter B—Acquisition PlanningPart 9—Contractor QualificationsSubpart 9.1—Responsible Prospective Contractors

48 C.F.R. § 9.105 (2026)

9.105 Procedures.

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026 cited 1993–2016 10citing cases
At a glance

Courts have cited this section in 10 opinions since 1993.

The 10 cases that cite 48 C.F.R. § 9.105 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 9.105 2×cited by 1,106 cases
Where it cites § 9.105
“The court noted that under the FAR, the contracting officer’s signing of a contract constitutes a determination that the contractor is responsible ( 48 C.F.R. § 9.105 — 2(a)(1)) and that the contracting officer had also specifically found that JVC was responsible.”
The case’s holding
A bid award may be set aside if the procurement official's decision lacks a rational basis or the procurement procedure involves a violation of regulation or procedure.
Later courts cite it for
“the procurement procedure involved a violation of regulation or procedure.” · 194 citing courts
2
GREENOSG Prod. Tankers LLC v. United States, 82 Fed. Cl. 570 (Fed. Cl. 2008).
cites § 9.105 2×cited by 15 cases
Later courts cite it for
“affiliates must have been involved in or affected -by the contractor's wrongdoing to be named in the debarment” · 2 citing courts
3
GREENNaplesyacht.Com, Inc. v. United States, 60 Fed. Cl. 459 (Fed. Cl. 2004).
cites § 9.105 2×cited by 10 cases
Where it cites § 9.105
“11 Rather than request a deposition of the CO, the court offered the Government a less intrusive option either to provide documents or an affidavit that would demonstrate: “1) whether the contracting officer, as required by 48 C.F.R. § 9.105 -l(a), possessed or obtained…”
4
GREENHickey v. Chadick, 649 F. Supp. 2d 770 (S.D. Ohio 2009).
cites § 9.105 6×cited by 2 cases
Where it cites § 9.105
“” 48 C.F.R. § 9.105 -l(a). In making that determination of responsibility, the contracting officer should consider relevant past performance information, including the Past Performance Information Retrieval System (PPIRS), the EPLS, records and experience data (including…”
5
GREENAkal Sec., Inc. v. United States, 103 Fed. Cl. 310 (Fed. Cl. 2011).
cites § 9.105 1×cited by 19 cases
Where it cites § 9.105
“” 48 C.F.R. § 9.105 -l(a). The United States Court of Appeals for the Federal Circuit, however, has determined that “the contracting officer is the arbiter of what, and how much, information he needs.”
Later courts cite it for
“should not second guess challenges to 'such matters as technical ratings . . . which involve discretionary determinations of procurement officials.” · 2 citing courts
6
GREENAnthem Builders, Inc. v. United States, 121 Fed. Cl. 15 (Fed. Cl. 2015).
cites § 9.105 7×cited by 1 case
Where it cites § 9.105
“at 16-17 (citing 48 C.F.R. § 9.105 -l(a); 48 C.F.R. § 9.105-2 (a)); see also Gov’t Reply at 13 (same).”
7
GREENSupreme Foodservice GmbH v. United States, 112 Fed. Cl. 402 (Fed. Cl. 2013).
cites § 9.105 1×cited by 12 cases
Where it cites § 9.105
“) Supreme correctly contends that 48 C.F.R. § 9.105 -l(a) requires the CO gather sufficient information for its responsibility evaluation of the sufficiency of the putative awar-dees’ facilities to perform the contract.”
8
cites § 9.105 1×cited by 12 cases
Where it cites § 9.105
“In order to answer the question of whether there was a lack of rational basis for the contracting officer’s decision, we must know: (1) whether the contracting officer, as required by 48 C.F.R. § 9.105 -l(a), possessed or obtained information sufficient to decide the integrity…”
Later courts cite it for
“having knowledge that carmelo la mastra was a company principal "would certainly have had a major bearing on what he would do.” · 1 citing court
9
GREENYRT Servs. Corp. v. United States, 28 Fed. Cl. 366 (Fed. Cl. 1993).
cites § 9.105 1×cited by 20 cases
Where it cites § 9.105
“48 C.F.R. § 9.105 -l(b) (1991). 22 At oral argument, plaintiff’s counsel also argued that, notwithstanding any authority the NPS might have under the CPA, the concepts of responsiveness and responsibility have been long established, that they predate the Competition in…”
Later courts cite it for
“must give reasonable meaning to all parts of the contract and not render portions of the contract meaningless.” · 3 citing courts
10
GREENTri-Cnty. Contractors, Inc. v. Thomas Perez, 155 F. Supp. 3d 81 (D.D.C. 2016).
cites § 9.105 1×cited by 4 cases
Where it cites § 9.105
“” 48 C.F.R. § 9.105 — 1(b)(1). And while the regulations caution that an expired debarment “may not be relevant to a determination of present responsibility,” see id.”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199320042016

One bar per year. Tallest: 1 case in 1993. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Fed. Cl.7Fed. Cir.1D.D.C.1S.D. Ohio1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com