49 C.F.R. § 194.115

Response resources

Read at: eCFRecfr.gov CornellLII GovInfogovinfo.gov CasesGoogle Scholar

(a) Each operator shall identify and ensure, by contract or other approved means, the resources necessary to remove, to the maximum extent practicable, a worst case discharge and to mitigate or prevent a substantial threat of a worst case discharge.

(b) An operator shall identify in the response plan the response resources which are available to respond within the time specified, after discovery of a worst case discharge, or to mitigate the substantial threat of such a discharge, as follows:

Tier 1Tier 2Tier 3
High volume area6 hrs30 hrs54 hrs.
All other areas12 hrs36 hrs60 hrs.
Notes of Decisions
Cited in 2 cases, 2017–2019 · leading case: Nat'l Wildlife Fed'n v. Sec'y of the U.S. Dep't of Transp., 286 F. Supp. 3d 836 (E.D. Mich. 2017).
Nat'l Wildlife Fed'n v. Sec'y of the U.S. Dep't of Transp., 286 F. Supp. 3d 836 (E.D. Mich. 2017). · cites it 2× “, 49 C.F.R. § 194.115 . At the same time, DOI issued an Interim Final Rule, 58 Fed.”
Nat'l Wildlife Fed'n v. Sec'y of the Dep't of Transp., 374 F. Supp. 3d 634 (E.D. Mich. 2019). · cites it 3× “, 49 C.F.R. § 194.115 . At the same time, DOI issued an Interim Final Rule, 58 Fed.”
Annotations are extracted automatically from the opinions in the Syfert caselaw corpus and ranked by authority, recency, and treatment. Dots show Syfertize treatment of the citing case itself.