C.F.R. homeSearch C.F.R.
C.F.R.Title 49Chapter I—Pipeline and Hazardous Materials Safety Administration, Department of TransportationSubchapter D—Pipeline SafetyPart 195—Transportation of Hazardous Liquids By PipelineSubpart C—Design Requirements

49 C.F.R. § 195.134 (2026)

Leak detection

Edition and currency
eCFR text as of Sept. 29, 2026. The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTeCFR text as of Sept. 29, 2026

(a) Scope. This section applies to each hazardous liquid pipeline transporting liquid in single phase (without gas in the liquid).

(b) General. (1) For each pipeline constructed prior to October 1, 2019. Each pipeline must have a system for detecting leaks that complies with the requirements in § 195.444 by October 1, 2024.

(2) For each pipeline constructed on or after October 1, 2019. Each pipeline must have a system for detecting leaks that complies with the requirements in § 195.444 by October 1, 2020.

(c) CPM leak detection systems. A new computational pipeline monitoring (CPM) leak detection system or replaced component of an existing CPM system must be designed in accordance with the requirements in section 4.2 of API RP 1130 (incorporated by reference, see § 195.3) and any other applicable design criteria in that standard.

(d) Exception. The requirements of paragraph (b) of this section do not apply to offshore gathering or regulated rural gathering lines.

[Amdt. 195-102, 84 FR 52295, Oct. 1, 2019]
Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: eCFR text as of Sept. 29, 2026. Syfert holds no earlier or later version of this section.

C.F.R. Home  |  Search C.F.R.  |  Search cases for this section  |  syfert.com