Connecticut General Statutes homeSearch Connecticut
Conn. Gen. Stat.Title 49 — Mortgages and LiensChapter 847 — Liens

Conn. Gen. Stat. § 49-41a (2025)

Enforcement of payment by general contractor to subcontractor and by subcontractor to its subcontractors

Edition and currency
laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026) cited 1985–2021 22citing cases
At a glance

Courts have cited this section in 22 opinions since 1985, 1 of them in the last five years. The most litigated part is subsection (b) (1 case).

(a) When any public work is awarded by a contract for which a payment bond is required by section 49-41, the contract for the public work shall contain the following provisions: (1) A requirement that the general contractor, within thirty days after payment to the contractor by the state or a municipality, pay any amounts due any subcontractor, whether for labor performed or materials furnished, when the labor or materials have been included in a requisition submitted by the contractor and paid by the state or a municipality; (2) a requirement that the general contractor shall include in each of its subcontracts a provision requiring each subcontractor to pay any amounts due any of its subcontractors, whether for labor performed or materials furnished, within thirty days after such subcontractor receives a payment from the general contractor which encompasses labor or materials furnished by such subcontractor.

(b) Each payment requisition submitted in accordance with the requirements of subsection (a) of this section, except for any such payment requisition submitted pursuant to a contract administered by or in conjunction with the Department of Transportation, shall include a statement showing the status of all pending construction change orders, other pending change directives and approved changes to the original contract or subcontract. Such statement shall identify the pending construction change orders and other pending change directives, and shall include the date such change orders and directives were initiated, the costs associated with their performance and a description of any work completed. As used in this section, “pending construction change order” or “other pending change directive” means an authorized directive for extra work that has been issued to a contractor or a subcontractor.

(c) If payment is not made by the general contractor or any of its subcontractors in accordance with such requirements, the subcontractor shall set forth his claim against the general contractor and the subcontractor of a subcontractor shall set forth its claim against the subcontractor through notice by registered or certified mail. Ten days after the receipt of that notice, the general contractor shall be liable to its subcontractor, and the subcontractor shall be liable to its subcontractor, for interest on the amount due and owing at the rate of one per cent per month. In addition, the general contractor, upon written demand of its subcontractor, or the subcontractor, upon written demand of its subcontractor, shall be required to place funds in the amount of the claim, plus interest of one per cent, in an interest-bearing escrow account in a bank in this state, provided the general contractor or subcontractor may refuse to place the funds in escrow on the grounds that the subcontractor has not substantially performed the work according to the terms of his or its employment. In the event that such general contractor or subcontractor refuses to place such funds in escrow, and the party making a claim against it under this section is found to have substantially performed its work in accordance with the terms of its employment in any arbitration or litigation to determine the validity of such claim, then such general contractor or subcontractor shall pay the attorney's fees of such party.

(d) No payment may be withheld from a subcontractor for work performed because of a dispute between the general contractor and another contractor or subcontractor.

(e) This section shall not be construed to prohibit progress payments prior to final payment of the contract and is applicable to all subcontractors for material or labor whether they have contracted directly with the general contractor or with some other subcontractor on the work.

(1969, P.A. 427, S. 1, 2; P.A. 75-626; P.A. 76-164; P.A. 79-602, S. 99; P.A. 80-115; P.A. 86-12, S. 1; P.A. 05-229, S. 5; P.A. 06-59, S. 1; P.A. 09-146, S. 2.)

History: P.A. 75-626 added provisions re deposit of claim amount in escrow account and prohibiting withholding of payment from subcontractor for work performed because of dispute between general or prime contractor and another contractor or subcontractor; P.A. 76-164 substituted reference to requirements included in contract for reference to requirements issued by public works commissioner and added references to payments by municipalities; P.A. 79-602 divided section into Subsecs. and made minor changes in wording, substituting “the” or “that” for “such”, etc.; P.A. 80-115 restated provisions, eliminating references to “prime” contractors and added Subsec. (a)(2) re requirements of subcontracts; P.A. 86-12 changed time limits for payment by general contractor to subcontractor and subcontractor to subcontractor from 45 and 20 days respectively, to 30 days in each case; P.A. 05-229 amended Subsec. (b) to require the general contractor to place funds claimed in an escrow account if a surety bond is not in place; P.A. 06-59 amended Subsec. (b) to delete “if a surety bond is not in place,” re placing funds in escrow; P.A. 09-146 added new Subsec. (b) re payment requisition statement requirements and redesignated existing Subsecs. (b) to (d) as Subsecs. (c) to (e), effective July 1, 2009.

See chapter 60, part II re public building contracts.

Remedies afforded by this section and Sec. 49-42 are independent of each other. 207 C. 468. Cited. 238 C. 293; 239 C. 708.

Cited. 5 CA 61; 13 CA 253; 15 CA 504; 32 CA 118; 40 CA 89.

The 20 cases that cite Conn. Gen. Stat. § 49-41a most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENNor'easter Grp., Inc. v. Colossale Concrete, Inc., 542 A.2d 692 (Conn. 1988).
cites § 49-41a 36×cited by 134 cases
Where it cites § 49-41a
“The defendants argue that § 49-41a (b) is an integral part of the statutory scheme that furnishes a subcontractor with a cause of action against the general contractor and the surety on a payment bond under § 49-42.”
Holding on this section
The notice requirement in General Statutes section 49-41a (b) is not a jurisdictional prerequisite to a suit brought under General Statutes section 49-42.
Later courts cite it for
“whether a building contract has been substantially performed is ordinarily a question of fact for the trier to determine.” · 4 citing courts
2
GREENSaturn Constr. Co. v. Premier Roofing Co., 680 A.2d 1274 (Conn. 1996).
cites § 49-41a 32×cited by 87 cases
Where it cites § 49-41a
“s that the trial court improperly confirmed the award for the following reasons: (1) the arbitration panel improperly denied the plaintiffs request to open the arbitration proceedings to review relevant and material new evidence; and (2) the arbitration panel manifestly…”
The case’s holding
An arbitration award is not vacated for manifest disregard if the panel's statutory interpretation is reasonable or supported by an alternative legal theory.
Later courts cite it for
“the test consists of the following three elements, all of which must be satisfied in order for a court to vacate an arbitration award on the ground that the arbitration panel manifestly disregarded the law: (1) the error was obvious and capable of being readily and instantly perceived by the average person qualified to serve as an arbitrator; (2) the arbitration panel appreciated the existence of a clearly governing legal principle but decided to ignore it; and (3) the governing law alleged to have been ignored by the arbitration panel is well defined, explicit, and clearly applicable.” · 2 citing courts
3
GREENErnst Steel Corp. v. Reliance Ins., 536 A.2d 969 (Conn. App. Ct. 1988).
cites § 49-41a 35×cited by 19 cases
Where it cites § 49-41a
“Ernst claimed payments and interest due under its contract with Yonkers as damages and also claimed counsel fees by application of General Statutes § 49-41a. 1 *255 Although Yonkers was not named as a party in the initial complaint, the general contractor moved to be added as a…”
Later courts cite it for
“although designated a third party cross-complaint,' under our practice such a pleading by a defendant against the plaintiff is called a counter-claim and the trial court properly referred to it as such.” · 1 citing court
4
GREENUnited Concrete Prods., Inc. v. NJR Constr., LLC, 263 A.3d 823 (Conn. App. Ct. 2021).
cites § 49-41a 30×cited by 3 cases
Where it cites § 49-41a
“t of NJR’s counterclaim; (2) concluded that NJR did not fail to mitigate its damages; (3) failed to render judgment against Aegis on the plaintiff’s payment bond claim and award interest and attorney’s fees pursuant to General Statutes § 49-42; (4) failed to render judgment…”
5
GREENGennarini Constr. Co. v. Messina Painting & Decorating Co., 496 A.2d 539 (Conn. App. Ct. 1985).
cites § 49-41a 13×cited by 15 cases
Where it cites § 49-41a
“The submission encompassed two issues: (1) what money, if any, was owed to the defendant; and (2) whether General Statutes § 49-41a (b) 1 could be applied by the arbitrator in this case, and, if so, what remedy was to be awarded.”
6
GREENGennarini Constr. Co. v. Messina Painting & Decorating Co., 545 A.2d 579 (Conn. App. Ct. 1988).
cites § 49-41a 10×cited by 19 cases
Where it cites § 49-41a
“The defendant appeals from the trial court’s denial of its postjudgment motion for supplemental interest and attorney’s fees, filed pursuant to General Statutes § 49-41a. 1 We find no error.”
Later courts cite it for
“a collateral attack is an attack upon a judgment, decree or order offered in an action or proceeding other than that in which it was obtained , in support of the contentions of an adversary in the action or proceeding, as where the judgment is offered in support of a title or as a foundation for applying the doctrine of res judicata.” · 3 citing courts
7
GREENSuntech of Conn., Inc. v. Lawrence Brunoli, Inc., 164 A.3d 36 (Conn. App. Ct. 2017).
cites § 49-41a 5×cited by 8 cases
Where it cites § 49-41a
“The plaintiff alleged four counts against the contractor for breach of contract, unjust enrichment, delay, and violation of General Statutes § 49-41a ; 5 and one count against the insurer pursuant to General Statutes § 49-42.”
8
GREENBldg. Supply Corp. v. Lawrence Brunoli, Inc., 669 A.2d 620 (Conn. App. Ct. 1996).
cites § 49-41a 7×cited by 13 cases
Where it cites § 49-41a
“The plaintiff also asserted a claim pursuant to General Statutes § 49-41a 3 *92 et seq. The defendant filed its answer as well as a counterclaim.”
9
GREENTDS Painting & Restoration, Inc. v. Copper Beech Farm, Inc., 808 A.2d 726 (Conn. App. Ct. 2002).
cites § 49-41a 2×cited by 16 cases
Where it cites § 49-41a
“involved an award of counsel fees to a subcontractor against a general contractor under the provisions of General Statutes § 49-41a. That statute authorizes attorney’s fees for a prevailing subcontractor against a general contractor who refuses to deposit the disputed contract…”
10
GREENBlakeslee Arpaia Chapman, Inc. v. El Constructors, Inc., 628 A.2d 601 (Conn. App. Ct. 1993).
cites § 49-41a 3×cited by 17 cases
Where it cites § 49-41a
“” General Statutes § 49-41a provides in relevant part: “(b) If payment is not made by the general contractor .”
Later courts cite it for
“thus, a plaintiff may be entitled to a prejudgment remedy because it has demonstrated the requisite probable cause, but it may still be denied the remedy if its interest is already adequately secured.” · 2 citing courts
11
GREENComm'r of Labor v. C.J.M. Servs., Inc., 842 A.2d 1124 (Conn. 2004).
cites § 49-41a 2×cited by 15 cases
Where it cites § 49-41a
“General Statutes § 49-42 provides in relevant part: “(a) Any person who performed work or supplied materials for which a requisition was submitted to, or for which an estimate was prepared by, the awarding authority and who does not receive full payment for such work or…”
12
NEUTRALComm'r of Labor v. C.J.M. Servs., Inc., 806 A.2d 1105 (Conn. App. Ct. 2002).
cites § 49-41a 5×cited by 3 cases
Where it cites § 49-41a
“” General Statutes § 49-42 provides in relevant part: “(a) Any person who performed work or supplied materials for which a requisition was submitted to, or for which an estimate was prepared by, the awarding authority and who does not receive full payment for such work or…”
cites § 49-41a 1×cited by 96 cases
Where it cites § 49-41a
““(b) Every suit instituted under this section shall be brought in the name of the person suing, in the superior court for the judicial district where the contract was to be performed, irrespective of the amount in controversy in the suit, but no such suit may be commenced after…”
The case’s holding
A contract modification may be inferred from the attendant circumstances and conduct of the parties.
Later courts cite it for
“as with any issue of statutory interpretation, our initial guide is the language of the statute itself.” · 5 citing courts
14
GREENBlondeau v. Baltierra, 252 A.3d 317 (Conn. 2020).
cites § 49-41a 1×cited by 12 cases
Where it cites § 49-41a
“Here, the plaintiff argues that the arbitrator manifestly disregarded a binding, contractual choice of law provision in the premarital agreement executed by the parties.”
15
GREENNielsen v. Wisniewski, 628 A.2d 25 (Conn. App. Ct. 1993).
cites § 49-41a 2×cited by 18 cases
Where it cites § 49-41a
“, General Statutes §§ 49-41a (b) and *140 49-42.”
16
GREENSuntech of Connecticut, Inc. v. Lawrence Brunoli, Inc., 72 A.3d 1113 (Conn. App. Ct. 2013).
cites § 49-41a 2×cited by 5 cases
Where it cites § 49-41a
“Suntech brought an action against Brunoli and Safeco, an insurance company that had issued a payment bond to Brunoli for the project at issue.”
17
GREENBarreira Landscaping & Masonry v. Frontier Ins., 779 A.2d 244 (Conn. Super. Ct. 2000).
cites § 49-41a 4×cited by 3 cases
Where it cites § 49-41a
“The second is against the defendant Frontier Insurance Company (surety or defendant surety) under each payment bond issued to support the contract pursuant to General Statutes §§ 49-41a and 49-42, known as the “Little Miller Act.”
18
GREENEacott v. Ins. Co. of North Am., 673 A.2d 587 (Conn. App. Ct. 1996).
cites § 49-41a 2×cited by 4 cases
Where it cites § 49-41a
“g authority and who does not receive full payment for such work or materials within sixty days of the applicable payment date provided for in subsection (a) of section 49-41a, or any person who supplied materials or performed subcontracting work not included on a requisition or…”
19
cites § 49-41a 1×cited by 5 cases
Where it cites § 49-41a
“2d 1274 (1996)(eomplaint alleging violations of § 49-41a and CUTPA). Further, a number of federal circuit courts have held that the federal Miller Act does not provide a plaintiff with an exclusive remedy.”
cites § 49-41a 3×cited by 2 cases
Where it cites § 49-41a
“to 1995) § 49-42 provides in relevant pari,: “(a) Any person who performed work or supplied materials for which a requisition was submitted to, or for which an estimate was prepared by, the awarding authority and who does not receive full payment for such work or materials…”

Show all 22 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
198520032021

One bar per year. Tallest: 4 cases in 1996. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Conn. App. Ct.12Conn.7D. Conn.2Conn. Super. Ct.1
By subsection
(b)1 case
Steward Mach. Co. v. White Oak Corp., 462 F. Supp. 2d 251 (D. Conn. 2006).

Show all 22 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2024 session: the source has not yet published 2025 Public Acts (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Connecticut General Statutes Home  |  Search Connecticut  |  Search cases for this section  |  syfert.com