Idaho Code § 50-219 (2026)
Damage claims.
Edition and currency
Other sources
Courts have cited this section in 22 opinions since 1971, 2 of them in the last five years.
Damage claims.
All claims for damages against a city must be filed as prescribed by chapter 9, title 6, Idaho Code.
- Where it cites § 50-219
- “The district court granted a directed verdict in favor of the City of Post Falls on the grounds that Sweitzer had failed to file a timely notice of claim pursuant to I.C. § 50-219 and alternatively that there was insufficient evidence to support the cause of action.”
- The case’s holding
- All damage claims against a municipality must follow the notice procedures prescribed in the Idaho Tort Claims Act regardless of whether the claim is tortious.
- Later courts cite it for
- “it is incumbent upon this court to interpret a statute in a manner that will not nullify it, and it is not to be presumed that the legislature performed an idle act of enacting a superfluous statute.” · 3 citing courts
- Where it cites § 50-219
- “The City then filed a motion for summary judgment on the ground Magnuson's claim was barred by I.C. §§ 50-219 and 6-906, which require filing notice of a claim against a municipality within 180 days from when the claim arises.”
- The case’s holding
- Under the Idaho Tort Claims Act, the notice period is ordinarily triggered by the occurrence of the wrongful act, even if the full extent of damages is not yet known.
- Later courts cite it for
- “to raise an issue on appeal, the record must contain an adverse ruling to form the basis for assignment of error and this court will not consider or review an issue raised for the first time on appeal.” · 4 citing courts
- Where it cites § 50-219
- “With respect to the first and second causes of action, the City alleged that Bryant had failed to comply with Idaho Code § 50-219 which required her to give timely notice to the City of those claims.”
- The case’s holding
- Under the Idaho Human Rights Act, filing a complaint with the Idaho Human Rights Commission is a condition precedent to suing, so failure to file requires dismissal of the related claims.
- Later courts cite it for
- “a statute that is procedural or remedial and does not create, enlarge, diminish or destroy contractual or vested rights is generally held not to be a retroactive statute, even though it was enacted subsequent to the events to which it operates.” · 2 citing courts
- Where it cites § 50-219
- “tituted a taking or inverse condemnation under Article I, Section 14 of the Idaho Constitution and that if relief is denied on the state claim then a taking occurred under the Fifth Amendment of the United States Constitution; (2) Alpine’s inverse condemnation claim was timely…”
- Where it cites § 50-219
- “At the time of Harkness’ discharge — the time when the claim for damages occurred —I.C. § 50-219 provided: Damage claims. — All claims for damages against a city must be filed with the city clerk within sixty (60) days after the time when such claim for damages shall have…”
- The case’s holding
- An employment contract may create a constitutionally protected property interest in continued employment (defining an employee’s property interest in his employment contract).
- Later courts cite it for
- “evidence having any tendency to make the existence of any fact that is of consequence to the determination of the action more probable or less probable than it would be without the evidence.” · 2 citing courts
- Where it cites § 50-219
- “The City argued that Brown’s failure to comply with the notice of claim requirement under Idaho Code § 50-219 deprived the court of subject matter jurisdiction over Brown’s state law claims for damages.”
- Where it cites § 50-219
- “On December 17, 2003, the district court issued its memorandum decision and order denying Bravo and Splitting Kings’s motion for summary judgment and granting the City’s motion for summary judgment.”
- The case’s holding
- A city’s exaction of a liquor license transfer fee without statutory authority constitutes a taking of property, and state notice-of-claim requirements do not bar federal takings claims.
- Where it cites § 50-219
- “This is an appeal from the dismissal of a complaint against a city on the ground that the plaintiff had failed to file a timely notice of claim under Idaho Code § 50-219 . The city also cross-appeals the denial of its claim for attorney fees under Idaho Code § 12-120 (1).”
- Where it cites § 50-219
- “The statute which has application to claims against a city not based on tortious conduct would be I.C. § 50-219: Damage Claims. — All claims for damages against a city must be filed with the city clerk within sixty (60) days after the time when such claim for damages shall have…”
- The case’s holding
- Compliance with the notice requirement of the Idaho Tort Claims Act is a mandatory condition precedent to bringing suit and failure to comply is fatal to a claim.
- Later courts cite it for
- “knowledge of facts which would put a reasonably prudent person on inquiry is the equivalent to knowledge of the wrongful act and will start the running of the 120-day period.” · 4 citing courts
- Where it cites § 50-219
- “The City moved for summary judgment, arguing that Turner’s claim for unpaid compensation was barred by the applicable statute of limitations and that both claims were barred because Turner failed to provide adequate notice of her claims as required by Idaho Code section 50-219.…”
- Where it cites § 50-219
- “It found that the complaint did not allege, nor was any proof offered at the time of trial that any notice of claim was served upon respondent city as required under I.C. § 50-219. The trial court dismissed Count III of the complaint as against respondents mayor and city…”
- Where it cites § 50-219
- “Idaho Code § 50-219 provides that “[a]ll claims for damages against a city must be filed as prescribed by [the ITCA].”
- The case’s holding
- A construction manager is entitled to an equitable fee adjustment when the owner directs changes to the project scope despite the absence of prior fee approval.
- Later courts cite it for
- “this court will not consider an argument not supported by cogent argument or authority.” · 5 citing courts
- Where it cites § 50-219
- “C. § 50-219. Where the ITCA applies, a claim must “be presented to and filed with the clerk or secretary of the political subdivision” within 180 days “from the date the claim arose or reasonably should have been discovered, whichever is later.”
- Where it cites § 50-219
- “The court held: (1) NIBCA's state law claims were barred because of their failure to comply with the Idaho Tort Claims Act (ITCA) and Idaho Code section 50-219 ; (2) NIBCA's federal claims were not barred despite the failure to comply with available state remedies; (3) any…”
- Later courts cite it for
- “the failure to comply with notice requirements of the itca cannot serve as a bar for federal takings claims.” · 1 citing court
- Where it cites § 50-219
- “Idaho Code § 50-219 states, “All claims for damages against a city must be filed as prescribed by chapter 9, title 6, Idaho Code.”
- Where it cites § 50-219
- “The City filed a motion to dismiss, arguing that Cox failed to file a claim pursuant to Idaho Code § 50-219 , which requires a claimant to follow the ITCA, chapter 9, title 6, of the Idaho Code, before filing a lawsuit for damages against a city.”
- Where it cites § 50-219
- “The facts are not in dispute and the only issue is whether the provisions of I.C. § 50-219, requiring “claims for damages” to be submitted to a city within sixty days of the time the “damages” occurred, are applicable under the circumstances presented in the case at bar.”
- Where it cites § 50-219
- “The only question posed is whether the notice of claim requirements of I.C. § 50-219 and the Idaho Tort Claims Act, I.”
- Where it cites § 50-219
- “According to the Court: Idaho Code § 50-219 states, “All claims for damages against a city must be filed as prescribed by chapter 9, title 6, Idaho Code.”
- Where it cites § 50-219
- “Idaho Tort Claims Act Additionally, all of the state law claims, including the breach of contract claim, are barred by the notice requirement in ITCA.”
Show all 22 citing cases (list view) →
The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.
One bar per year. Tallest: 3 cases in 2013. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.
Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.
Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.
Edition shown: text as last checked Oct. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.