Illinois Compiled Statutes homeSearch Illinois
ILCSChapter 770Act 60

770 ILCS 60/28 (2026)

Suits by laborers, materialmen or sub-contractors

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1995–2021 25citing cases
(770 ILCS 60/28) (from Ch. 82, par. 28)
    Sec. 28. Suits by laborers, materialmen or sub-contractors. If any money due to the laborers, materialmen, or sub-contractors be not paid within 10 days after his notice is served as provided in Sections 5, 24, and 25, then such person may file a claim for lien or file a complaint and enforce such lien within the same limits as to time and in such other manner as hereinbefore provided for the contractor in Section 7 and Sections 9 to 20 inclusive, of this Act, or he may sue the owner and contractor jointly for the amount due in the circuit court, and a personal judgment may be rendered therein, as in other cases. In such actions, as in suits to enforce the lien, the owner shall be liable to the plaintiff for no more than the pro rata share that such person would be entitled to with other sub-contractors out of the funds due to the contractor from the owner or one knowingly permitted by the owner to contract for such improvements and the contractor, except as hereinbefore provided for laborers and materialmen, and such action shall be maintained against the owner only in case the plaintiff establishes a right to the lien. All suits and actions by sub-contractors shall be against both contractor and owner jointly, and no judgment shall be rendered therein until both are duly brought before the court by process or publication, and such process may be served and publication made as to all persons except the owners as in other civil actions. All such judgments, where the lien is established shall be against both jointly, but shall be enforced against the owner only to the extent that he is liable under his contract as by this Act provided, and shall recite the date from which the lien thereof attached according to the provisions of Sections 1 to 20 of this Act; but this shall not preclude a judgment against the contractor, personally, where the lien is defeated.
(Source: P.A. 94-627, eff. 1-1-06.)

    
The 20 cases that cite 770 ILCS 60/28 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENCordeck Sales, Inc. v. Constr. Sys., Inc., 887 N.E.2d 474 (Ill. App. Ct. 1st Dist. 2008).
cites § 770 ILCS 60/28 2×cited by 58 cases
Where it cites § 770 ILCS 60/28
“As an alternative argument, First Midwest maintains that even if ALL’s section 24 notice was timely, ALL nonetheless still failed to perfect its lien claim because it recorded and provided notice of its claim on the same date and thus failed to abide by the timing requirements…”
The case’s holding
A mechanic's lien is not invalidated by an overstatement of the amount due unless there is evidence of an intent to defraud.
Later courts cite it for
“even under a constructive fraud theory, a lien claim will not be invalidated simply because the claim contains an overstatement. rather, in most cases, 'the intent to defraud is shown by executed documents that on their face overstate the amount due in combination with some other evidence of record from which intent could be inferred.” · 6 citing courts
2
GREENPremier Elec. Constr. Co. v. Am. Nat'l Bank, 658 N.E.2d 877 (Ill. App. Ct. 1st Dist. 1995).
cites § 770 ILCS 60/28 3×cited by 42 cases
Where it cites § 770 ILCS 60/28
“Premier’s amended complaint included the following claims: (1) count I was a claim to foreclose its mechanic’s lien under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 1992)); (2) count II was a claim on the Bond against Federal as surety; (3) count III was a…”
The case’s holding
A subcontractor is entitled to a pro rata share of settlement proceeds used to release liens but cannot assert a direct lien claim against a foreclosure purchaser.
Later courts cite it for
“once the statutory requirements are met, however, the act should be liberally construed to carry out its remedial purpose.” · 2 citing courts
3
GREENA.E.I. Music Network, Inc. v. Bus. Computers, Inc., 290 F.3d 952 (7th Cir. 2002).
cites § 770 ILCS 60/28 1×cited by 40 cases
Where it cites § 770 ILCS 60/28
“Out $159,000, it brought this suit, charging that the statutory requirement *954 of a bond was an implied-by-law term of the contract between the Board and BCI that it can enforce as a third-party beneficiary, and also seeking to impress a mechanic’s lien, 770 ILCS 60/28; R.W.…”
The case’s holding
The statutory bond requirement is an implied term of a public contract making a subcontractor a third-party beneficiary entitled to sue for a failure to post a bond.
Later courts cite it for
“has divided illinois's intermediate appellate court.” · 3 citing courts
4
GREENNw. Millwork Co. v. Komperda, 788 N.E.2d 399 (Ill. App. Ct. 2d Dist. 2003).
cites § 770 ILCS 60/28 1×cited by 16 cases
Where it cites § 770 ILCS 60/28
“It sought to foreclose on its mechanic's lien, damages for breach of contract, and damages under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 2000)). The contract claim was directed against Andrew Lipowski only, and the remaining claims were directed against…”
The case’s holding
Reversing a dismissal, the court held that a construction manager's failure to furnish a sworn contractor's statement under the Mechanics Lien Act does not bar its lien or contract claim against owners.
Later courts cite it for
“if the owner pays the contractor before receiving the sworn statement, the owner may be compelled to pay subcontractors even if he or she has paid the contractor in full.” · 1 citing court
5
GREENState Farm Mut. Auto. Ins. v. George Hyman Constr. Co., 715 N.E.2d 749 (Ill. App. Ct. 4th Dist. 1999).
cites § 770 ILCS 60/28 1×cited by 24 cases
Where it cites § 770 ILCS 60/28
“Concept, Economy, Levy, and Moran brought separate actions to hold Clark and State Farm jointly liable under section 28 of the Lien Act (770 ILCS 60/28 (West 1994)). Concept, Economy, and Gibson sought recovery under a quantum meruit theory for materials- and supplies they had…”
The case’s holding
Arbitration clauses governing disputes arising from a contract are interpreted more broadly than those governing disputes in connection with a contract.
Later courts cite it for
“arbitration clauses applying to disputes 'relating to or arising from' a contract are given broader meaning than those governing disputes 'in connection with' a contract.” · 2 citing courts
6
GREENMerchants Env't Indus., Inc. v. SLT Realty Ltd. P'ship, 731 N.E.2d 394 (Ill. App. Ct. 1st Dist. 2000).
cites § 770 ILCS 60/28 1×cited by 23 cases
Where it cites § 770 ILCS 60/28
“” Alternatively, in count II, designated “Action Against Owner and Contractor Jointly Pursuant to 770 ILCS 60/28,” MEI seeks judgment jointly and severally against SLT and Gold for $219,317.”
The case’s holding
A mechanic's lien claim is unenforceable against a third-party purchaser if it fails to include a completion date to allow verification of the filing deadline.
Later courts cite it for
“raise a genuine issue of material fact as to whether there was such reliance.” · 4 citing courts
7
GREENPetroline Co. v. Advanced Env't Contractors, Inc., 711 N.E.2d 1146 (Ill. App. Ct. 1st Dist. 1999).
cites § 770 ILCS 60/28 1×cited by 21 cases
Where it cites § 770 ILCS 60/28
“770 ILCS 60/28 (West 1996). Under the “relation back doctrine,” a subcontractor’s lien complying with the provisions of the Act is considered to have attached as of the date of the contract between the contractor and the owner.”
The case’s holding
Failure to give a mortgagee the statutory 90-day mechanic's lien notice renders the lien unenforceable against the lender only; the owner who received proper notice remains bound.
Later courts cite it for
“the paramount objective in construing a statute is to give effect to the intent of the legislature.” · 2 citing courts
8
GREENOnsite Eng'g & Mgmt., Inc. v. Illinois Tool Works, Inc., 744 N.E.2d 928 (Ill. App. Ct. 1st Dist. 2001).
cites § 770 ILCS 60/28 1×cited by 8 cases
Where it cites § 770 ILCS 60/28
“Count IV was an action to obtain a judgment in the amount of $46,984 against QST, as general contractor, and ITW and 3635 Touhy, as owners of the property, pursuant to section 28 of the Mechanics Lien Act (770 ILCS 60/28 (West 1996)). On August 3, 1999, ITW and 3635 Touhy filed…”
Later courts cite it for
“when the contractor shall sub-let his contract or a specific portion thereof to a sub-contractor, the party furnishing material to or performing labor for such sub-contractor shall have a lien therefor; and may enforce his lien in the same manner as is herein provided for the enforcement of liens by sub-contractors. 770 ilcs 60/22 (west 1996).” · 1 citing court
cites § 770 ILCS 60/28 1×cited by 7 cases
Where it cites § 770 ILCS 60/28
“Here, AES and RMS settled and released their respective claims against the owner AES under the EPC Contract for $2.5 million. Therefore, if Raymond were due any debt relating to its lien and trust claim for work performed, Pope would have to share the Current Account in…”
10
GREENBrown & Kerr, Inc. v. Am. Stores Props., Inc., 715 N.E.2d 804 (Ill. App. Ct. 1st Dist. 1999).
cites § 770 ILCS 60/28 1×cited by 56 cases
Where it cites § 770 ILCS 60/28
“In count I, B&K requested judgment pursuant to section 28 of the Mechanics Lien Act (770 ILCS 60/28 (West 1996)) against American and Trapani and an award of interest, attorney fees, and expenses.”
11
GREENChicago Whirly, Inc. v. Amp Rite Elec. Co., 710 N.E.2d 45 (Ill. App. Ct. 1st Dist. 1999).
cites § 770 ILCS 60/28 2×cited by 3 cases
Where it cites § 770 ILCS 60/28
“” 770 ILCS 60/28 (West 1996). In finding that the statute of limitations was extended, the Garbe court relied on section 108(c) of the Bankruptcy Act, which provides: “[I]f applicable nonbankruptcy law *** fixes a period for commencing or continuing a civil action in a court…”
12
GREENO'Connor Constr. Co. v. Belmont Harbor Home Dev., LLC, 909 N.E.2d 294 (Ill. App. Ct. 1st Dist. 2009).
cites § 770 ILCS 60/28 1×cited by 4 cases
Where it cites § 770 ILCS 60/28
“ANALYSIS As a preliminary matter, we note that under the Act a subcontractor may elect to enforce its rights for breach of contract through the simultaneous use of several remedies, including an action at law for breach of contract against the general contractor and the owners…”
13
GREENBrown & Kerr v. Am. Stores Props., 715 N.E.2d 804 (Ill. App. Ct. 1st Dist. 1999).
cites § 770 ILCS 60/28 1×cited by 7 cases
Where it cites § 770 ILCS 60/28
“In count I, B & K requested judgment pursuant to section 28 of the Mechanics Lien Act (770 ILCS 60/28 (West 1996)) against American and Trapani and an award of interest, attorney fees, and expenses.”
The case’s holding
Tender of an amount less than what is due is ineffective if acceptance is conditioned on an admission that no greater amount is owed.
Later courts cite it for
“tender of an amount less than the creditor claims is due is ineffective when acceptance is conditioned on an admission that no greater amount is due” · 4 citing courts
14
NEUTRALMatteo Constr. Co. v. Teckler Blvd Dev. Site, LLC, 2020 IL App (2d) 190766, 177 N.E.3d 747.
cites § 770 ILCS 60/28 2×cited by 1 case
Where it cites § 770 ILCS 60/28
“OPINION ¶1 Plaintiff, Matteo Construction Company, appeals the trial court’s dismissal of its complaint seeking to foreclose a subcontractor’s lien under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 2014)) against defendant, Teckler Blvd Development Site, LLC…”
15
GREENConcrete Prods., Inc. v. Centex Homes, 721 N.E.2d 802 (Ill. App. Ct. 2d Dist. 1999).
cites § 770 ILCS 60/28 1×cited by 2 cases
Where it cites § 770 ILCS 60/28
“” 770 ILCS 60/28 (West 1996). Thus, the contractor is a necessary party without whom the action cannot go forward.”
Later courts cite it for
“acts in violation of the section 362(a) automatic stay are void ab initio.” · 1 citing court
16
NEUTRALCB Constr. & Design, LLC v. Atlas Brookview, LLC, 2021 IL App (1st) 200924, 196 N.E.3d 115.
cites § 770 ILCS 60/28 1×cited by 3 cases
Where it cites § 770 ILCS 60/28
“” 770 ILCS 60/28 (West 2018). The issue before the supreme court was “whether a bankruptcy filing by a necessary party in an action to enforce a mechanic’s lien extends the amount of time the subcontractor has to file suit.”
Later courts cite it for
“second amended complaint shall stand, except count ii for foreclosure of mechanic's lien,” · 2 citing courts
17
NEUTRALGerdau Ameristeel US, Inc. v. Broeren Russo Constr., Inc., 2013 IL App (4th) 120547, 992 N.E.2d 27.
cites § 770 ILCS 60/28 1×cited by 3 cases
Where it cites § 770 ILCS 60/28
“Section 28 of the Act ¶ 35 Section 28 of the Act (770 ILCS 60/28 (West 2008)), dealing with suits by subcontractors, provides, in part, as follows: “If any money due to the *** sub-contractors be not paid within 10 days after his notice -7- is served as provided in sections 5,…”
Later courts cite it for
“it shall be the duty of the contractor to give the owner, and the duty of the owner to require of the contractor, before the owner or his agent shall pay or cause to be paid to the contractor any moneys , a statement in writing, under oath or verified by affidavit, of the names and addresses of all parties furnishing labor, services, material, fixtures, apparatus or machinery, forms or form work and of the amounts due or to become due to each.” · 2 citing courts
18
NEUTRALMatteo Constr. Co. v. Teckler Blvd Dev. Site, LLC, 2020 IL App (2d) 190766, 177 N.E.3d 747.
cites § 770 ILCS 60/28 1×cited by 1 case
Where it cites § 770 ILCS 60/28
“) 1 770 ILCS 60/28 (West 2014). ¶ 13 Section 7, which is generally applicable to contactors, provides: “No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within 4 months after completion,…”
19
GREENNw. Millwork Co. v. Komperda, 338 Ill. App. 3d 997 (Ill. App. Ct. 2d Dist. 2003).
cites § 770 ILCS 60/28 1×cited by 1 case
Where it cites § 770 ILCS 60/28
“It sought to foreclose on its mechanic’s hen, damages for breach of contract, and damages under section 28 of the Mechanics Lien Act (Act) (770 ILCS 60/28 (West 2000)). The contract claim was directed against Andrew Lipowski only, and the remaining claims were directed against…”
20
GREENCordeck Sales v. Constr. Sys., No. 1-06-3702 Rel (Ill. App. Ct. 1st Dist. Mar. 31, 2008).
cites § 770 ILCS 60/28 2×cited by 0 cases
Where it cites § 770 ILCS 60/28
“As an alternative argument, First Midwest maintains that even if ALL’s section 24 notice was timely, ALL nonetheless still failed to perfect its lien claim because it recorded and provided notice of its claim on the same date and thus failed to abide by the timing requirements…”

Show all 25 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
199520082021

One bar per year. Tallest: 8 cases in 1999. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Ill. App. Ct.237th Cir.1Bankr. N.D. Ill.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 25 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.