Massachusetts General Laws homeSearch Massachusetts
Mass. Gen. LawsPart I Title XXI Chapter 149

Mass. Gen. Laws ch. 149, § 29 (2026)

Bonds for payment for labor, materials, rentals or transportation charges; enforcement of claim; notice of claim; speedy trial, appeal, consolidation; dismissal; legal fees; posting statute

Edition and currency
text as last checked Sept. 2026 (this copy records no edition or section history). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTtext as last checked Sept. 2026 (this copy records no edition or section history) cited 1921–2026 139citing cases
At a glance

Courts have cited this section in 139 opinions since 1921, 3 of them in the last five years.

Section 29. Officers or agents contracting in behalf of the commonwealth or in behalf of any county, city, town, district or other political subdivision of the commonwealth or other public instrumentality for the construction, reconstruction, alteration, remodeling, repair or demolition of public buildings or other public works when the amount of the contract is more than $25,000 shall obtain security by bond in an amount not less than one half of the total contract price, for payment by the contractor and subcontractors for labor performed or furnished and materials used or employed therein, including lumber so employed which is not incorporated therein and is not wholly or necessarily consumed or made so worthless as to lose its identity, but only to the extent of its purchase price less its fair salvage value, and including also any material specially fabricated at the order of the contractor or subcontractor for use as a component part of said public building or other public work so as to be unsuitable for use elsewhere, even though such material has not been delivered and incorporated into the public building or public work, but only to the extent of its purchase price less its fair salvage value and only to the extent that such specially fabricated material is in conformity with the contract, plans and specifications or any changes therein duly made; for payment of transportation charges for materials used or employed therein which are consigned to the contractor or to a subcontractor who has a direct contractual relationship with the contractor; for payment by such contractor and subcontractors of any sums due for the rental or hire of vehicles, steam shovels, rollers propelled by steam or other power, concrete mixers, tools and other appliances and equipment employed in such construction, reconstruction, alteration, remodeling, repair or demolition; for payment of transportation charges directly related to such rental or hire; and for payment by such contractor and subcontractors of any sums due trustees or other persons authorized to collect such payments from the contractor or subcontractors, based upon the labor performed or furnished as aforesaid, for health and welfare plans, supplementary unemployment benefit plans and other fringe benefits which are payable in cash and provided for in collective bargaining agreements between organized labor and the contractor or subcontractors; provided, that any such trustees or other persons authorized to collect such payments for health and welfare plans, supplementary unemployment benefit plans and other fringe benefits shall, subject to the following provisions, be entitled to the benefit of the security only in an amount based upon labor performed or furnished as aforesaid for a maximum of two hundred and forty consecutive calendar days.

In order to obtain the benefit of such bond for any amount claimed due and unpaid at any time, any claimant having a contractual relationship with the contractor principal furnishing the bond, who has not been paid in full for any amount claimed due for the labor, materials, equipment, appliances or transportation included in the paragraph (1) coverage within sixty-five days after the due date for same, shall have the right to enforce any such claim (a) by filing a petition in equity within one year after the day on which such claimant last performed the labor or furnished the labor, materials, equipment, appliances or transportation included in the claim and (b) by prosecuting the claim thereafter by trial in the superior court to final adjudication and execution for the sums justly due the claimant as provided in this section.

Any claimant having a contractual relationship with a subcontractor performing labor or both performing labor and furnishing materials pursuant to a contract with the general contractor but no contractual relationship with the contractor principal furnishing the bond shall have the right to enforce any such claim as provided in subparagraphs (a) and (b) of paragraph (2) only if such claimant gives written notice to the contractor principal within sixty-five days after the day on which the claimant last performed the labor or furnished the labor, materials, equipment, appliances or transportation included in the paragraphs (1) coverage, stating with substantial accuracy the amount claimed, the name of the party for whom such labor was performed or such labor, materials, equipment, appliances or transportation were furnished; provided, that any such claimant shall have the right to enforce any part of a claim covering specially fabricated material included in the paragraph (1) coverage only if such claimant has given the contractor principal written notice of the placement of the order and the amount thereof not later than twenty days after receiving the final approval in writing for the use of the material. The notices provided for in this paragraph (3) shall be served by mailing the same by registered or certified mail postage prepaid in an envelope addressed to the contractor principal at any place at which the contractor principal maintains an office or conducts his business, or at the contractor principal's residence, or in any manner in which civil process may be served.

Upon motion of any party, the court shall advance for speedy trial a petition to enforce a claim pursuant to this section. Sections fifty-nine and fifty-nine B of chapter two hundred thirty-one shall apply to petitions to enforce claims pursuant to this section. The court shall enter an interlocutory decree upon which execution shall issue for any part of a claim found due pursuant to said sections fifty-nine or fifty-nine B and shall, upon motion of any party, advance for speedy trial the petition to enforce the remainder of the claim. Any party aggrieved by such interlocutory decree shall have the right to appeal therefrom as from a final decree. The court shall not consolidate for trial the petition of any claimant under this section with the petition of one or more other claimants on the same bond, unless the court finds that a substantial portion of the evidence of the same events during the course of construction (other than the fact that the claims sought to be consolidated arise under the same general contract) is applicable to the petitions sought to be consolidated, and that such consolidation will prevent unnecessary duplication of evidence.

The court shall not dismiss any petition on the ground that it was filed before the sixty-fifth day after the day the claimant last performed the labor or furnished the labor, materials, equipment, appliances or transportation included in the claim, nor shall the court dismiss any petition on the ground that a claim involves more than one contract with the same party and that the one year period has elapsed as to any one contract; provided, that the court shall not enter a decree upon any claim or part thereof prior to the seventieth day after the day the claimant last performed the labor or furnished the labor, materials, equipment, appliances or transportation included in the claim.

A decree in favor of any claimant under this section shall include reasonable legal fees based upon the time spent and the results accomplished as approved by the court and such legal fees shall not in any event be less than published rate of any recommenced fee schedule of a state-wide bar association or of a bar association in which the office of counsel for claimant is located, whichever is higher.

Any person employing persons on any public works hereinbefore referred to shall post conspicuously, at such place or places as will provide reasonable opportunity for all employees to read the same, a correct copy of this section. The attorney general shall enforce this paragraph.

The 20 cases that cite Mass. Gen. Laws ch. 149, § 29 most heavily, weighted by court and treatment. RelevanceNewestTreatment
cites § 29 7×cited by 96 cases
Where it cites § 29
“See G. L. c. 149, § 29. 2 The punitive damages were awarded after a judge in the Superior Court concluded that USF&G had wilfully and knowingly violated G.”
The case’s holding
When a plaintiff recovers a judgment on an underlying claim, the amount of that judgment serves as the basis for calculating multiple damages for bad faith multiplication.
Later courts cite it for
“a ruling that conduct violates g.l.c. 93a is a legal, not a factual, determination.” · 5 citing courts
2
GREENAggregate Indus. - Ne. Region, Inc. v. Hugo Key & Sons, Inc., 57 N.E.3d 1027 (Mass. App. Ct. 2016).
cites § 29 15×cited by 3 cases
Where it cites § 29
“A dispute arose about payment, and Aggregate filed a complaint in the Superior Court asserting contract and quantum meruit claims under G. L. c. 149, § 29, the Commonwealth’s bond statute for publicly funded construction projects, and violations of G.”
3
GREENCosta v. Brait Builders Corp., 972 N.E.2d 449 (Mass. 2012).
cites § 29 7×cited by 15 cases
Where it cites § 29
“This case raises the question whether a subcontractor providing labor or materials to a public construction project for which a payment bond has been obtained by the general contractor pursuant to G. L. c. 149, § 29, may by private agreement forgo its right to pursue payment…”
4
GREENPeters v. Hartford Accident & Indem. Co., 389 N.E.2d 63 (Mass. 1979).
cites § 29 16×cited by 8 cases
Where it cites § 29
“This case, which arises under G. L. c. 149, § 29, involves the scope of the payment bond which prime contractors are required to provide as surety for work done on public projects.”
5
GREENSalem Bldg. Supply Co. v. J.B.L. Constr. Co., 407 N.E.2d 1302 (Mass. App. Ct. 1980).
cites § 29 9×cited by 20 cases
Where it cites § 29
“In allowing the plaintiff’s motion for summary judgment, the judge ruled that the bond had been given as security for payment of the plaintiff’s claim under G. L. c. 149, § 29. Section 29, as appearing in St.”
6
GREENDrywall Sys., Inc. v. ZVI Constr. Co., 761 N.E.2d 482 (Mass. 2002).
cites § 29 3×cited by 67 cases
Where it cites § 29
“In that case the court held that a subcontractor was not entitled to attorney’s fees under G. L. c. 149, § 29, the public works payment bond statute, for legal services rendered during arbitration of the underlying contract claim.”
The case’s holding
A broad arbitration clause encompassing claims arising out of a contract authorizes arbitrators to award multiple damages and attorney's fees under the consumer protection statute.
Later courts cite it for
“(any controversy or claim . . . arising out of or related to this (s)ubcontract.” · 5 citing courts
7
GREENManganaro Drywall, Inc. v. White Constr. Co., 363 N.E.2d 669 (Mass. 1977).
cites § 29 7×cited by 27 cases
Where it cites § 29
“The defendants appeal from a judgment against them as principal and surety respectively in a proceeding brought by the plaintiff subcontractor under G. L. c. 149, § 29, to collect the balance due it on a public works project.”
Later courts cite it for
“places the expense of litigation on a contractor and a surety who decline to pay a rightful claim and tends to achieve the legislative goal of expeditious payments to subcontractors.” · 2 citing courts
8
GREENFloors, Inc. v. B. G. Danis of New England, Inc., 401 N.E.2d 839 (Mass. 1980).
cites § 29 5×cited by 45 cases
Where it cites § 29
“This case presents two questions: (1) whether a suit on a contractor’s bond under G. L. c. 149, § 29 (as amended through St.”
The case’s holding
Attorneys' fees incurred in obtaining and confirming an arbitration award are not recoverable under the prevailing party statute.
Later courts cite it for
“(in the absence of special arrangement to the contrary, legal fees arising out of arbitration have never been awarded in the past, and we shall not depart from this practice in the absence of a legislative determination to do so.” · 3 citing courts
9
GREENReliance Ins. v. City of Boston, 884 N.E.2d 524 (Mass. App. Ct. 2008).
cites § 29 4×cited by 26 cases
Where it cites § 29
“On January 4, 1999, Sciaba obtained both *552 performance and payment bonds from Reliance as required by G. L. c. 149, § 29. The city and Sciaba executed the contract on January 26,1999.”
Later courts cite it for
“properly considered public records include the records of other courts in related proceedings, of which the judge may take judicial notice in any event” · 2 citing courts
10
GREENC. C. & T. Constr. Co. v. Coleman Bros., 391 N.E.2d 1256 (Mass. App. Ct. 1979).
cites § 29 5×cited by 29 cases
Where it cites § 29
“More particularly in this case, the cost to the plaintiff of acquiring the specially fabricated materials was pertinent because G. L. c. 149, § 29, as amended through St.”
11
GREENWorcester Air Conditioning Co. v. Com. Union Ins., 439 N.E.2d 845 (Mass. App. Ct. 1982).
cites § 29 11×cited by 7 cases
Where it cites § 29
“The plaintiff, a sub-subcontractor, commenced this suit to recover under G. L. c. 149, § 29, for labor and materials upon a statutory payment bond executed by the defendant, a surety company, in connection with the construction of a building.”
12
GREENHeller v. Silverbranch Constr. Corp., 382 N.E.2d 1065 (Mass. 1978).
cites § 29 2×cited by 249 cases
Where it cites § 29
“G. L. c. 149, § 29, discussed at note 7 infra.”
The case’s holding
Attorney fees cannot be awarded without evidence regarding the time expended and the reasonableness of the rates charged (affirming award of fees in absence of evidence concerning time expended by attorney or rate or reasonableness of charges).
Later courts cite it for
“not dependent on traditional tort or contract law concepts for its definition.” · 10 citing courts
13
GREENAm. Air Filter Co. v. Innamorati Bros., 260 N.E.2d 718 (Mass. 1970).
cites § 29 11×cited by 13 cases
Where it cites § 29
“(American), brought this bill under G. L. c. 149, § 29, against Innamorati Brothers, Inc.”
14
REDFloors, Inc. v. B. G. Danis of New England, Inc., 387 N.E.2d 1166 (Mass. App. Ct. 1979).
cites § 29 6×cited by 12 cases
Reversed by Floors, Inc. v. B. G. Danis of New England, Inc. (1980): the Massachusetts Supreme Judicial Court's own opinion in this case.
Where it cites § 29
“We are asked to decide in this case whether a subcontractor who brings suit under G. L. c. 149, § 29 (as amended by St. 1972, c.”
15
GREENCity Rentals, LLC v. BBC Co., 947 N.E.2d 1103 (Mass. App. Ct. 2011).
cites § 29 5×cited by 7 cases
Where it cites § 29
“In this case we address the application of the Commonwealth’s labor and material payment bond statute for publicly funded construction projects, G. L. c. 149, § 29 (bond statute). At the conclusion of a bench trial, a judge of the Superior Court found that a general contractor…”
16
GREENCont'l Bronze Co. v. Salvo & Armstrong Steel Co., 397 N.E.2d 1143 (Mass. App. Ct. 1979).
cites § 29 6×cited by 10 cases
Where it cites § 29
“(Collins), and Collins’ surety, Travelers Insurance Company, on the bond posted in conformance with G. L. c. 149, § 29. Those rights had been lost as a result of Continental’s tardiness in complying with the notice provisions set forth in the third paragraph of § 29.”
Later courts cite it for
“the terms of the promised performance ... are restricted ... to benefit the general contractor.” · 2 citing courts
17
GREENCinder Prods. Corp. v. Schena Constr. Co., 492 N.E.2d 744 (Mass. App. Ct. 1986).
cites § 29 4×cited by 12 cases
Where it cites § 29
“Adequacy of Notice Under G. L. c. 149, § 29. (a) Special fabrication.”
18
GREENC & I Steel, LLC v. Travelers Cas. & Sur. Co. of Am., 876 N.E.2d 442 (Mass. App. Ct. 2007).
cites § 29 4×cited by 6 cases
Where it cites § 29
“The contract and G. L. c. 149, § 29, required a payment bond, which Peabody obtained from Travelers in the penal sum of $22,411,590, the full value of the contract.”
19
GREENJ.P. Constr. Co. v. Stateside Builders, Inc., 699 N.E.2d 358 (Mass. App. Ct. 1998).
cites § 29 4×cited by 10 cases
Where it cites § 29
“This is an appeal from an award of attorney’s fees pursuant to G. L. c. 149, § 29. The plaintiff, J.P. Construction Co.”
20
GREENNorth Am. Specialty Ins. v. Lapalme, 258 F.3d 35 (1st Cir. 2001).
cites § 29 1×cited by 61 cases
Where it cites § 29
“See Mass. Gen. Laws ch. 149, § 29 . CRS routinely bid on public works jobs and, thus, from time to time required bonds.”
The case’s holding
An accountant is liable to a third party for negligent misrepresentation only if the accountant has actual knowledge of the third party and the specific transaction or a substantially similar one.
Later courts cite it for
“there are few principles more securely settled in this court than the principle which holds that, absent exceptional circumstances, an appellant cannot raise an argument for the first time in a reply brief.” · 7 citing courts

Show all 139 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
192019732026

One bar per 2 years. Tallest: 9 cases in 2000–2001. 2026 is a partial year. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mass.55Mass. App. Ct.46Mass. Super. Ct.24D. Mass.6Mass. Dist. Ct., App. Div.61st Cir.2
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 139 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: text as last checked Sept. 2026 (this copy records no edition or section history). Syfert holds no earlier or later version of this section.

Massachusetts General Laws Home  |  Search Massachusetts  |  Search cases for this section  |  syfert.com