Massachusetts General Laws

Mass. Gen. Laws ch. 83, § 15 (2026)

Sewerage systems; adoption; assessment; uniform units; separation of costs

✓ current as of July 2026
Find cases: SyfertCases citing this section MAmalegislature.gov (official) JustiaChapter on Justia CornellLII Search CasesGoogle Scholar

Section 15. The city council of a city or a town may adopt a system of sewerage for a part or the whole of its territory, and may provide that assessments under section fourteen shall be made upon owners of land within such territory by a fixed uniform rate or a rate based upon a uniform unit method.

A fixed uniform rate shall be based upon the estimated average cost of all the sewers therein, according to the frontage of such land on any way in which a sewer is constructed, or according to the area of such land within a fixed depth from such way, or according to both such frontage and area; but no assessment in respect to any such land, which by reason of its grade or level or any other cause cannot be drained into such sewer, shall be made until such incapacity is removed. If the assessment is according to the area within such fixed depth, the lien therefor shall attach to the parcel assessed.

A uniform unit method shall be based upon sewerage construction costs divided among the total number of existing and potential sewer units to be served, after having proportioned the cost of special and general benefit facilities. Each sewer unit shall be equal to a single family residence. Potential sewer units shall be calculated on the basis of zoning then in effect. Existing and potential multifamily, commercial, industrial and semipublic uses shall be converted into sewer units on the basis of residential equivalents.

A city by ordinance or a town by by-law may separate the costs of general benefit facilities, including but not limited to pumping stations, trunk and force mains, from that of special benefit facilities, including but not limited to the sewer mains, serving adjacent properties. A portion of costs of the general benefit facilities may be apportioned by the uniform unit method on all areas to receive benefits within the pumping district or combination of districts. The cost of the general benefit facilities, attributable to undeveloped land not abutting a sewered street, may not be assessed until properties are serviced by public sewerage. The proportional cost of the special benefit and general benefit facilities may be assessed against all properties abutting a sewered street.

Notes of Decisions
Cited in 8 cases (1 in the last 5 years), 1979–2024 · leading case: W.R. Grace & Co.-Conn. v. Town of Acton, 817 N.E.2d 806 (Mass. App. Ct. 2004).
Sort: Relevance Newest Treatment
W.R. Grace & Co.-Conn. v. Town of Acton, 817 N.E.2d 806 (Mass. App. Ct. 2004). · cites it 11× “Pursuant to G. L. c. 83, § 15, Acton adopted a sewer assessment by-law in 1998 and amended it in 1999.”
Ninety Six, LLC v. Wareham Fire Dist., 94 N.E.3d 397 (Mass. App. Ct. 2017). · cites it 2× “2d 806 , (uniform unit method under G. L. c. 83, § 15, allows municipalities to consider "existing and potential sewer units to be served," "[r]ather than making assessments based upon frontage and area as required by the fixed uniform *759 rate").”
Bd. of Pub. Works v. Bd. of Selectmen, 387 N.E.2d 146 (Mass. 1979). “139), and to employ a method of apportioning sewerage construction costs other than those described in G. L. c. 83, § 15 (St. 1973, c. 104). And by art.”
Stepan Chem. Co. v. Town of Wilmington, 391 N.E.2d 1247 (Mass. App. Ct. 1979). “161, the defendants must be guided by G. L. c. 83, § 15, as in effect prior to St.”
Notre Dame Training Sch. v. Town of Tyngsborough & Others. (Mass. App. Ct. 2024). · cites it 3× “See G. L. c. 83, § 15 (town may adopt a system of sewerage and may provide that betterment assessments "shall be made upon owners of land within such territory by a fixed uniform rate or a rate based upon a uniform unit method").”
Ninety Six, LLC v. Wareham Fire Dist. (Mass. App. Ct. 2018). · cites it 2× “at 463 , (uniform unit method under G. L. c. 83, § 15, allows municipalities to consider "existing and potential sewer units to be served," "[r]ather than making assessments based upon frontage and area as required by the fixed uniform rate").”
Bozenhard v. Town of Shrewsbury, 18 Mass. L. Rptr. 141 (Mass. Super. Ct. 2004). · cites it 2× “The Utility Easement Does Not Fall Under the Exception for “Any Other Cause” Provided in G.L.c. 83, §15 G.L.c. 83, §15 states in part, “.”
Lemansky v. Charlton Water & Sewer Comm'n, 20 Mass. L. Rptr. 363 (Mass. Super. Ct. 2005). “Chartier’s sale of a narrow strip of his frontage to Wolanski is sufficient to allow Wolanski to connect, at no additional betterment cost, 66 additional units, Wolanski would receive a major windfall which would be plainly inconsistent with G.L.c. 83, §15 which demonstrates a…”