Michigan Compiled Laws homeSearch Michigan
Mich. Comp. LawsMichigan Compiled LawsChapter 129Act 213 of 1963

Mich. Comp. Laws § 129.206 (2026)

Public works, contractor's bond; definitions.

Edition and currency
laws through the 2026 session (checked Aug. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Aug. 2026) cited 1975–2016 14citing cases
At a glance

Courts have cited this section in 14 opinions since 1975.

CONTRACTOR'S BOND FOR PUBLIC BUILDINGS OR WORKS


Act 213 of 1963


129.206 Public works, contractor's bond; definitions.

Sec. 6.

    A "claimant" means a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract. "Labor and material" includes that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the contract.

History: 1963, Act 213, Eff. Sept. 6, 1963

The 14 cases that cite Mich. Comp. Laws § 129.206 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
cites § 129.206 12×cited by 37 cases
Where it cites § 129.206
“203 provides: The payment bond shall be in an amount fixed by the governmental unit but not less than 25% of the contract amount solely for the protection of claimants, as defined in [MCL 129.206], supplying labor or materials to the principal contractor or his subcontractors in…”
The case’s holding
Contract interpretation requires determining the parties' intent through the plain and unambiguous language of the agreement.
Later courts cite it for
“when parties enter into multiple agreements relating to the same subject-matter, we must read those agreements together to determine the parties' intentions.” · 4 citing courts
2
GREENKammer Asphalt Paving Co. v. East China Twp. Schs., 504 N.W.2d 635 (Mich. 1993).
cites § 129.206 2×cited by 143 cases
Where it cites § 129.206
“2321(3), however, mandates that payment bonds need only be posted "in an amount fixed by the governmental unit but not less than twenty-five percent of the contract amount.”
The case’s holding
A governmental unit has a duty under the public works act to verify the validity of payment bonds furnished by a general contractor.
Later courts cite it for
“even though no contract may exist between two parties, under the equitable doctrine of unjust enrichment, 'a person who has been unjustly enriched at the expense of another is required to make restitution to the other.” · 14 citing courts
3
GREENMorris Pumps v. Centerline Piping, Inc., 729 N.W.2d 898 (Mich. Ct. App. 2007).
cites § 129.206 1×cited by 206 cases
Where it cites § 129.206
“203; MCL 129.206; see also W T Andrew Co, Inc v Mid-State Surety Corp, 450 Mich 655 , 659; 545 NW2d 351 (1996).”
The case’s holding
An implied contract cannot exist if an express contract governs the same parties and subject matter, though unjust enrichment claims may proceed if the defendant is not a party.
Later courts cite it for
“the theory underlying quantum meruit recovery is that the law will imply a contract in order to prevent unjust enrichment when one party inequitably receives and retains a benefit from another.” · 19 citing courts
4
GREENRoyalite Co. v. Fed. Ins., 457 N.W.2d 96 (Mich. Ct. App. 1990).
cites § 129.206 4×cited by 7 cases
Where it cites § 129.206
“MCL 129.206; MSA 5.2321(6). It is also undisputed that plaintiff did not have a direct contractual relationship with the principal contractor.”
5
GREENWT ANDREW Co. v. Mid-State Sur. Corp., 545 N.W.2d 351 (Mich. 1996).
cites § 129.206 2×cited by 20 cases
Where it cites § 129.206
“Under the language of this bond, plaintiff could not meet the definition of a claimant because it never entered into a direct contract with the principal, Shmina. The only contract that plaintiff had was with Marino, a subcontractor.”
The case’s holding
The public works bond statute applies to a constitutionally created university as a valid exercise of the Legislature's police power to protect contractors and materialmen in the public sector.
Later courts cite it for
“protect contractors and materialmen in the public sector to ensure that they do not suffer injury when other contractors default on their obligations.” · 2 citing courts
cites § 129.206 2×cited by 4 cases
Where it cites § 129.206
“§ 129.206. This does not preclude the inclusion as compensation of employer contributions to a fringe benefits fund as required under the laborers’ collective bargaining agreement.”
7
GREENThomas Indus., Inc v. C & L Elec., Inc, 550 N.W.2d 558 (Mich. Ct. App. 1996).
cites § 129.206 1×cited by 7 cases
Where it cites § 129.206
“Section 7 of the act specifies the procedure by which a claimant not having a direct contractual relationship with the principal contractor may perfect a claim against the payment bond: A claimant who has furnished labor or material in the prosecution of the work provided for in…”
8
GREENLeonard C. Carnaghi, Inc. v. Amwest Sur. Ins. Co., 617 N.W.2d 49 (Mich. Ct. App. 2000).
cites § 129.206 1×cited by 3 cases
Where it cites § 129.206
“” MCL 129.206; MSA 5.2321(6). As noted by the Court in W T Andrew, supra, p 659, the Legislature adopted MCL 129.”
9
GREENWT Andrew Co. v. Mid-State Sur. Corp., 450 Mich. 655 (1996).
cites § 129.206 2×cited by 4 cases
Where it cites § 129.206
“Under the language of this bond, plaintiff could not meet the definition of a claimant because it never entered into a direct contract with the principal, Shmina. The only contract that plaintiff had was with Marino, a subcontractor.”
10
REDW T Andrew Co. v. Mid-State Sur. Corp., 529 N.W.2d 658 (Mich. Ct. App. 1995).
cites § 129.206 2×cited by 4 cases
Reversed by WT ANDREW COMPANY v. Mid-State Surety Corp. (1996): the Michigan Supreme Court's own opinion in this case.
Where it cites § 129.206
“Further, MCL 129.206; MSA 5.2321(6) defines a claimant as "a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract.”
11
GREENHub Elec. Co. v. Aetna Cas. & Sur. Co., 400 F. Supp. 77 (E.D. Mich. 1975).
cites § 129.206 1×cited by 3 cases
Where it cites § 129.206
“§ 129.206), and if so, whether plaintiff gave the proper statutory notice to defendant as is required by Section 7 (M.”
cites § 129.206 1×cited by 1 case
Where it cites § 129.206
“The Public Works Act defines a “claimant” in the following terms: *430 Mich. Comp. Laws § 129.206 . Seaboard contends that, given this definition, trust funds seeking unpaid fringe benefits are simply not claimants because they did not provide labor or materials to the project.”
13
NEUTRALKMH Equip. Co. v. Chas J. Rogers, Inc., 305 N.W.2d 266 (Mich. Ct. App. 1981).
cites § 129.206 1×cited by 1 case
Where it cites § 129.206
“, by virtue of a statutory redefinition of the terms "labor” and "material” in MCL 129.206; MSA 5.2321(6). The Legislature elected to afford protection to equipment lessors in such statutes by specific language.”
14
NO FLAGAssemblers, Inc. v. Am. Mfrs. Mut. Ins., 761 N.W.2d 399 (Mich. Ct. App. 2008).
cites § 129.206 2×cited by 0 cases
Where it cites § 129.206
“As a consequence, for plaintiff to make a claim under the bond, it must have “given written notice to the principal contractor and the governmental unit involved within 90 days from the date on which the claimant performed the last of the labor or furnished or supplied the last…”

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
197519952016

One bar per year. Tallest: 4 cases in 1996. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mich. Ct. App.7Mich.4E.D. Mich.26th Cir.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Aug. 2026). Syfert holds no earlier or later version of this section.

Michigan Compiled Laws Home  |  Search Michigan  |  Search cases for this section  |  syfert.com