Missouri Revised Statutes homeSearch Missouri
Mo. Rev. Stat.Chapter 429

Mo. Rev. Stat. § 429.170 (2026)

Actions commenced in six months

Edition and currency
laws through the 2026 session (checked Sept. 2026). The text is the edition Syfert holds; for a past event, check the version in force on that date.
Other sources
CURRENTlaws through the 2026 session (checked Sept. 2026) cited 1954–2017 36citing cases
At a glance

Courts have cited this section in 36 opinions since 1954.

  429.170.  Actions commenced in six months. — All actions under sections 429.010 to 429.340 shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay to final judgment; and no lien shall continue to exist by virtue of the provisions of said sections, for more than six months after the lien shall be filed, unless within that time an action shall be instituted thereon, as herein prescribed.

­­--------

(RSMo 1939 § 3562, A.L. 1959 S.B. 257 & 295)

Prior revisions: 1929 § 3172; 1919 § 7232; 1909 § 8228

(1953) Where lien appears of record, the timely filing of a suit to enforce same may be treated as a cross bill to a previously filed equitable lien action and should be consolidated with such action on application or on court's own motion. E.  C. Robinson Lumber Co. v. Baugher (A.), 258 S.W.2d 259.

(1954) Where contract for machines to be attached to realty was made with one corporation which was later dissolved and machines thereunder were delivered to and accepted by another corporation having same name, suit for mechanic's lien timely filed against first corporation which was not then in existence held timely. Drew's Hdw. & App. Co. v. Willis Housing Projects (A.), 268 S.W.2d 596.

(1956) Where ninetieth day for filing mechanic's lien occurred on Decoration Day, May 30, which was Sunday, the time for filing under § 506.060 was extended until Tuesday, June 1, because Monday became the holiday under § 9.010.  Hermann v. Dixon (A.), 285 S.W.2d 716.

(1963) Where both the property owner and subcontractor were made parties defendant in action to establish and enforce materialman's lien and petition was filed and process issued within six months' period, suit was timely although service was not had on subcontractor within six months' period.  Continental Electric Co. v. Ebco (A.), 365 S.W.2d 746.

(1964) In suit in equity to enforce mechanic's lien where another lien claimant filed application asking for order joining claimant as party defendant and filed no further pleading, application was not timely commencement of action as required by sections 429.170 and 429.310 to preserve claimant's lien.  Truog v. Elbel Construction Co. (A.), 374 S.W.2d 612.

(1964) Although action to enforce lien was commenced within statutory period, materialman's unexcused neglect for a period in excess of the period of limitation after first summons was issued against necessary party and returned unserved to request issuance of alias summons was fatal to the action.  Continental Electric Co. v. Ebco, Inc. (Mo.), 375 S.W.2d 134.

The 20 cases that cite Mo. Rev. Stat. § 429.170 most heavily, weighted by court and treatment. RelevanceNewestTreatment
1
GREENJ.H. Berra Paving Co. v. City of Eureka, 50 S.W.3d 358 (Mo. Ct. App. 2001).
cites § 429.170 21×cited by 7 cases
Where it cites § 429.170
“City claims the trial court erred in granting the motion because: (1) the trial court was without jurisdiction to enforce Berra’s mechanic’s lien due to Berra’s failure to join City as a necessary party within the applicable statute of limitations under section 429.170 RSMo…”
2
GREENWest Cent. Concrete, LLC v. Reeves, 310 S.W.3d 778 (Mo. Ct. App. 2010).
cites § 429.170 20×cited by 5 cases
Where it cites § 429.170
“West Central maintains that the findings included in the trial court’s judgment are inconsistent with the docket entries and that the trial court erred by failing to include a finding in its judgment that West Central’s delay in securing service on Reeves was “unnecessary” as…”
Later courts cite it for
“section 429.170 requires an action to enforce a mechanic's lien 'shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay.” · 2 citing courts
3
GREENMajor Lumber Co. v. G & B Remodeling, Inc., 817 S.W.2d 474 (Mo. Ct. App. 1991).
cites § 429.170 12×cited by 16 cases
Where it cites § 429.170
“Svetlic as trustee, filed a motion to dismiss Major Lumber’s petition on grounds that the six-month statute of limitation for enforcing a mechanics lien, as set out in § 429.170 RSMo Supp. 1990, 2 expired. The applicable federal bankruptcy provisions are now set out by way of…”
4
GREENSachs Elec. Co. v. HS Constr. Co., 86 S.W.3d 445 (Mo. Ct. App. 2002).
cites § 429.170 11×cited by 7 cases
Where it cites § 429.170
“By the plain terms of Section 429.170, RSMo 2000, Jarrell was obliged to file its action with[in] six months after filing notice of hen with the Circuit Clerk.”
5
GREENHome Bldg. Corp. v. Ventura Corp., 568 S.W.2d 769 (Mo. 1978).
cites § 429.170 7×cited by 31 cases
Where it cites § 429.170
“The second threshold issue involves the question of whether HBC commenced this action within six months after filing its lien statement as required by § 429.170. Authority recognizes that the suit actually was filed within the six month deadline but it claims that HBC did not…”
The case’s holding
A municipality taking title to encumbered land takes subject to a previously attached mechanic's lien.
Later courts cite it for
“comparable to the filing of a lis pendens notice.” · 2 citing courts
6
GREENTrilogy Dev. Co. v. BB Syndication Servs., Inc., 468 B.R. 854 (Bankr. W.D. Mo. 2011).
cites § 429.170 13×cited by 3 cases
Where it cites § 429.170
“8 It is undisputed that Gould Evans did not file a timely action pursuant to Mo.Rev.Stat. § 429.170, nor did it file a Notice of Continued Perfection in the bankruptcy case under 11 U.”
7
GREENWebcon Grp., Inc. v. S.M. Props., L.P., 1 S.W.3d 538 (Mo. Ct. App. 1999).
cites § 429.170 5×cited by 23 cases
Where it cites § 429.170
“The trial court held that Webcon failed to comply with the requirements of Section 429.170 RSMo because it filed its action to perfect its mechanic’s hen within six months after filing the hen, but failed to join the record owner of the property, William Wade, Trustee, as a…”
Later courts cite it for
“a person retains the benefit and enjoys the benefit conferred upon him without paying its reasonable value.” · 2 citing courts
8
GREENCont'l Elec. Co. v. Ebco, Inc., 375 S.W.2d 134 (Mo. 1964).
cites § 429.170 7×cited by 25 cases
Where it cites § 429.170
“This action against Ebco and Ford was filed in the Clay County Circuit Court on February 5, 1960, well within the 6-month limitation prescribed by Section 429.170 RSMo 1959, V.A.M.S. Summons issued on the same date.”
Later courts cite it for
“such delay in the issuance of other process following the return of the original writ as to interrupt the continuity of the suit so that the running of the statute became a bar to the suit.” · 1 citing court
9
GREENCent. Wholesale Distributors v. Day, 672 S.W.2d 88 (Mo. Ct. App. 1984).
cites § 429.170 6×cited by 9 cases
Where it cites § 429.170
“The Missouri Supreme Court noted that the lien statement had been filed on December 23,1959 and an action against Ebco and Ford was commenced on February 5, 1960, both such actions being well within the six-month limitation period prescribed by § 429.170, RSMo 1959 (now 1978).…”
cites § 429.170 5×cited by 6 cases
Where it cites § 429.170
“2010) (“Section 429.170 requires an action to enforce a mechanic’s hen ‘shall be commenced within six months after filing the lien, and prosecuted without unnecessary delay.”
11
GREENEC Robinson Lumber Co. v. Lowrey, 276 S.W.2d 636 (Mo. Ct. App. 1955).
cites § 429.170 4×cited by 34 cases
Where it cites § 429.170
“Mercantile insists that the judgment was erroneous, insofar as it subjected the real estate to a materialman’s lien, (1) because it was not shown that “the act that subjected the land to the lien was the joint act of tenants by (the) entirety” and (2) because (as Mercantile…”
Later courts cite it for
“the stipulated fact that mrs. lowrey executed such deed of trust tends to indicate her knowledge of and participation in the building project and is evidence of such character as has been considered significant and important in other cases.” · 2 citing courts
12
GREENFrank Dusselier Basement Builders, Inc. v. Gwico Builders, Inc., 449 S.W.2d 865 (Mo. Ct. App. 1969).
cites § 429.170 14×cited by 4 cases
Where it cites § 429.170
“This defendant filed a motion to dismiss plaintiff’s amended petition on the ground that the action was barred by the statute of limitations (Section 429.170, V.A.M.S.). The trial court sustained the motion and dismissed the amended petition with prejudice.”
13
GREENMcCarney v. Nearing, Staats, Prelogar & Jones, 866 S.W.2d 881 (Mo. Ct. App. 1993).
cites § 429.170 2×cited by 29 cases
Where it cites § 429.170
“Nearing did not file suit to foreclose by April 1, 1992, the end of the statutory six-month period in § 429.170, RSMo 1986, 2 and its mechanic’s lien expired as a matter of law.”
The case’s holding
Where a construction contract involving interstate commerce contains a broad arbitration clause, the Federal Arbitration Act governs and doubts about arbitrability are resolved in favor of arbitration.
14
GREENMeek Lumber Yard, Inc. v. Houts (In re Houts), 23 B.R. 705 (Bankr. W.D. Mo. 1982).
cites § 429.170 2×cited by 27 cases
Where it cites § 429.170
“It strikes the Court as peculiar that plaintiff would recognize that it needed a ruling from the bankruptcy court before proceeding to enforce its lien and began the proceeding to get that ruling, yet filed in state court before the ruling was issued.”
15
GREENHennis v. Tucker, 447 S.W.2d 580 (Mo. Ct. App. 1969).
cites § 429.170 4×cited by 21 cases
Where it cites § 429.170
“The issue here is whether the claimants failed to prosecute their claims without unnecessary delay and are therefore barred by Section 429.170 V.A.M.S. This section dealing with mechanic’s lien requires that the action to enforce a lien be “commenced” within six months after…”
16
GREENDierks & Sons Lumber Co. v. McSorley, 289 S.W.2d 164 (Mo. Ct. App. 1956).
cites § 429.170 7×cited by 8 cases
Where it cites § 429.170
“The appellants contend that respondent McSorley’s amended cross-petition filed on April 19, 1955, claimed for the first time a mechanic’s lien on appellants’ property after more than a year since the filing of his lien statement in the office of the circuit clerk; that since the…”
17
GREENWesterhold v. Mullenix Corp., 777 S.W.2d 257 (Mo. Ct. App. 1989).
cites § 429.170 2×cited by 22 cases
Where it cites § 429.170
“Defendants argued at trial that plaintiffs failed to comply with § 429.170 RSMo 1986, because plaintiffs’ suit, requesting this lien, was not “commenced until November 27, 1985, more than six (6) months after the filing of plaintiffs’ mechanic’s lien herein.”
Later courts cite it for
“manifest their promises by language or conduct which is not explicit.” · 2 citing courts
18
GREENDrilling Serv. Co. v. Baebler, 484 S.W.2d 1 (Mo. 1972).
cites § 429.170 3×cited by 26 cases
Where it cites § 429.170
“, and proceeding without unnecessary delay by either of these lien claimants as is required by § 429.170, V.A.M.S. *13 Franchi was a necessary party to this equitable mechanics lien action as it became the record owner of the property August 6, 196S.”
Later courts cite it for
“after substantial work was begun and at a time when the lender was aware of the total project being built.” · 2 citing courts
19
GREENHackmann v. Sommerfor Dev. Corp., 741 S.W.2d 857 (Mo. Ct. App. 1987).
cites § 429.170 4×cited by 5 cases
Where it cites § 429.170
“§ 429.170 RSMo. (1978). This argument mistakenly assumes that all individuals with an interest in the property are necessary parties in any mechanic’s lien action.”
20
GREENEC Robinson Lumber Co. v. Hughes, 355 F. Supp. 1363 (E.D. Mo. 1972).
cites § 429.170 3×cited by 17 cases
Where it cites § 429.170
“Plaintiff filed suit to enforce its mechanic's lien, as provided in § 429.170, R.S.Mo.1969, V.A.M.S., [2] on March 26, 1970 in the Circuit Court of Dunklin County seeking: 1) a judgment in the amount of $5,170.”

Show all 36 citing cases (list view) →

The flag is Syfertize’s treatment of the citing case itself, not of the statute. “Where it cites” is the passage in the opinion; the holding is a summary of the whole case and may concern another point. Annotations are extracted automatically from the opinions in the Syfert caselaw corpus.

Citing cases by year
195419852017

One bar per year. Tallest: 3 cases in 2001. These are opinions in the Syfert collection, which holds more of some courts’ recent opinions than their older ones, so a rise can reflect what the collection holds and not more litigation.

By court
Mo. Ct. App.28Mo.5Bankr. W.D. Mo.2E.D. Mo.1
By subsection

Courts have not cited this section by subsection, so its cases are not split up here. The Leading cases tab lists the cases that cite it most heavily.

Show all 36 citing cases (list view) →

Enactment and amendments

Syfert holds no separate history line for this section. Where this code prints a source or history note, it appears with the text, usually at the end.

Versions

Edition shown: laws through the 2026 session (checked Sept. 2026). Syfert holds no earlier or later version of this section.

Missouri Revised Statutes Home  |  Search Missouri  |  Search cases for this section  |  syfert.com